Present Status and Future Plans for the MKE Kicker Magnets - PowerPoint PPT Presentation

About This Presentation
Title:

Present Status and Future Plans for the MKE Kicker Magnets

Description:

Present Status and Future Plans for the MKE Kicker Magnets – PowerPoint PPT presentation

Number of Views:50
Avg rating:3.0/5.0
Slides: 26
Provided by: uyth
Category:

less

Transcript and Presenter's Notes

Title: Present Status and Future Plans for the MKE Kicker Magnets


1
Present Status and Future Plans for the MKE
Kicker Magnets
  • Acknowledgements some slides are adapted from
    previous presentations by Fritz Caspers, Enrique
    Gaxiola, Tom Kroyer Jan Uythoven.

M.J. BARNES, AB/BT
2
Transmission Line Kicker Magnets
  • The kicker magnets installed at LSS4 LSS6 are
    travelling-wave type magnets, each consisting of
    7 ferrite cells
  • 30 year old, recuperated, equipment
  • Transition piece between vacuum tank and kicker
    magnet
  • Tank length 2174 mm
  • Magnet length 1700mm.

MKE magnet in the clean room
3
Cross-section of MKE Magnet(prior to 2003 at
LSS4 and 2005/2006 at LSS6)
  • Ferrite C core constructed from three ferrites.
  • In general, ferrite used is type 8C11 from
    Ferroxcube.
  • Rectangular aperture for the beam.

Ferrite
Rectangular aperture
4
LSS4
  • LSS4 is used for extraction to CNGS/LHC
  • LSS4 has 5 magnets, magnetically in series, each
    powered by its own PFN and terminated in a
    matched resistor
  • Three of the magnets have large (L) apertures
    (147.7mm x 35mm)
  • Two of the magnets have small (S) apertures
    (135mm x 32mm).

5
LSS4 Parameters
CNGS LHC (Protons)
Energy 400 450 GeV/c
Deflection 0.54 0.48 mrad
Nominal PFN Voltage 50 51.2 kV
Nominal Impedance 10 10 O
Available rise-time 1.1 10 µs
Measured rise-time (1?99) 1.1 1.1 µs
Usable flattop length 10.5 7.9 µs
Flattop ripple ? 2 ? 1
E. Gaxiola et al, Upgrade And Tests Of The SPS
Fast Extraction Kicker System for LHC And CNGS,
EPAC2004.
6
LSS6
  • LSS6 is used for extraction to LHC
  • As of 2006 LSS6 has 3 magnets, magnetically and
    electrically in series, powered by a single PFN
    and terminated in a short-circuit
  • Two of the magnets have large (L) apertures
    (147.7mm x 35mm)
  • One magnet has small (S) aperture (135mm x
    32mm).

7
LSS6 Parameters
  • Before 2006, LSS6 consisted of 4 series magnets
    terminated in 10O. In 2005, proof of principle
    tests were carried out, in lab, for a
    short-circuit system
  • Rise and fall time increased
  • Reduced PFN voltage for same deflection
  • BUT voltage reversal.

LHC (protons)
Energy 450 GeV/c
Deflection 0.429 mrad
Nominal PFN Voltage 33.1 kV
Nominal Impedance 10 O
Available rise-time 8.8 µs
Measured rise-time 8 µs
Usable flattop length 7.9 µs
Flattop ripple ? 1
8
Beam Induced Heating
  • 2004 Need to reduce both beam impedance and
    losses.
  • The MKE (SPS extraction) kickers LSS4 LSS6 are
    heated by the beam due to their beam coupling
    impedance. Ferrite heating is caused by coupling
    between beam and real part of ferrite impedance.
  • High intensity beam can result in high power
    deposition in ferrite.

9
Past Developments
  • Kicker magnets at LSS4 (2003) LLS6 (2005/2006)
    equipped with
  • High thermal conductivity Aluminium-Nitride
    (AlN180) plates
  • Water cooling
  • PT100 temperature sensor.

10
Measured Probe Temperature
  • Design Space simulations were carried out to
    determine the relationship between the highest
    ferrite temperature and probe (PT100) temperature
    (with water cooling).
  • Validated by machine measurements for 8C11
    ferrite kick strength diminishes above 80C
    measured, which corresponds to 125C highest
    ferrite temperature, i.e. Curie temperature of
    ferrite (AB-Note-2004-005 BT, section 5).

11
Summary of situation at 2006
  • Above about 120?C the 8C11 ferrites loose their
    magnetic properties, this has been measured
    during the scrubbing runs.
  • Note 4E2 ferrite has a Curie Temperature of
    400?C.
  • Additional risk is structural damage above about
    150?C.
  • For normal operation the beam is interlocked at
    70 ?C measured (125?C on the ferrites)
  • For scrubbing runs the beam is interlocked
    above 90?C measured, which is about 140?C on the
    ferrites.
  • The water cooling system allows the magnet to be
    operational with approximately double the beam
    power deposition in the ferrite (AB-Note-2004-005
    BT, section 5).

12
Beam Coupling Impedance
  • Beam coupling impedance can be reduced using
    conductive stripes (serigraphy), i.e. interleaved
    comb structure, directly printed onto the
    ferrite blocks and having a reliable contact to
    the metallic HV plates at either side
  • Capacitive coupling between stripes (stripes
    carry beam image current).

13
Longitudinal Measurements (1)
  • Comparison between the two extreme cases
  • MKE-L8, without any serigraphy on 8C11 ferrites
  • MKE-L10, serigraphy on all seven 8C11 ferrite
    cells.
  • Significant reduction of longitudinal impedance
    from serigraphy.
  • Low frequency resonance directly linked to
    geometry of serigraphy.

Note Impedance based on 2.2m length (1.7m
actual) hence should be increased by a factor of
1.3
L8
L8
L10
L10
14
Dissipated Power
  • Calculated using beam spectrum measured during
    2004 SPS scrubbing run (data from J. Uythoven),
    but theoretical beam coupling impedance
  • 272 LHC bunches in SPS at 450 GeV
  • Comparison between fully shielded MKE-L10 and
    MKE-L8 (no shielding at all).

Serigraphy (painted stripes) reduce calculated
power deposition by a factor of gt4, for LHC beam.
15
Longitudinal Measurements (2)
  • In a comprehensive measurement campaign data for
    all types of MKE magnets was collected.
  • Conclusions
  • High Curie temperature ferrite (4E2) displays
    similar Real Impedance as 8C11 (Ferroxcube)
    ferrite.
  • S-Type L-Type magnets, without serigraphy,
    display similar Real Impedance.

16
CNGS Power Depositions
  • Calculated power deposition based on
  • CNGS beam spectra measurements made by G.
    Arduini and T. Bohl (4.5 s period) see
    Note-2004-39
  • 2.5x1013 protons per pulse
  • A total cycle duration of 6 s.
  • From Jan Uythovens presentation to APC, 10
    December 2004 (real part of beam impedance
  • 2 x 210 W/m ? Thottest-equilibrium107?C
  • Replace theoretical beam impedance of SPS kicker
    by measured data, for MKE-L8 (see slide 13),
    scaled by 2.2/1.7
  • 2 x 178 W/m ? Thottest-equilibrium91?C (based
    on 26?C tunnel)
  • Replace theoretical beam impedance of SPS kicker
    by measured data, for MKE-L10 (see slide 13),
    scaled by 2.2/1.7
  • 2 x 25 W/m ? Thottest-equilibrium35?C (based
    on 26?C tunnel)
  • Therefore shielding stripes on MKE-L10 kicker
    reduce beam induced power deposition,
    attributable to nominal CNGS beam, by a factor of
    7 c.f. MKE-L8.
  • For 1.7x1013 protons per pulse 3 cycles per
    39.6s, replace theoretical beam impedance of SPS
    kicker by measured data, for MKE-L10 (see
    slide 13), scaled by 2.2/1.7
  • 75 W/m ? Thottest-equilibrium40?C (based on 26?C
    tunnel)

17
Measured Temperatures (2007)
  • LHC type beam. No serigraphy (yet) at MKE4.

18
Measured Temperatures (2007)
19
Measured Temperatures (2007)
CNGS type beam. MKE6. Serigraphy on L10 results
in a factor of 6.4 (9/1.4) lower temperature rise
than L9 (factor of 7 expected see slide 16).
20
HV Issues Pulse Shape for MKE6
Terminating the series magnets by a short
circuit the magnet peak voltage is reduced in
absolute value (33kV PFN 16.5kV magnet
voltage). However, because of the reflection from
the short circuit, there is a full negative
voltage (-16.5 kV) on the magnet. If we consider
peak to peak, the voltage is 2x16.5 33 kV. The
magnets are designed for 30kV.
21
HV Breakdown in MKE6
  • The MKE6 magnets were tested one by one in the
    lab only S6 (adjacent to short circuit) was
    therefore tested with the actual waveform shape.
  • After re-installation of magnets (2006-2007 shut
    down), some conditioning (breakdown) problems
    with magnet L10 (closest, electrically, to PFN).
    But
  • L10 magnet is exposed to the longest duration
    and dV/dt of both positive and negative voltage
  • Before 2008, the DC conditioning was only made
    with positive polarity. During the past shut down
    (2007-2008) we have also carried out conditioning
    with negative DC so far it seems that such
    conditioning has had good effect i.e. no HV
    problems with L10
  • Last year, we had little time to condition in
    MKE6. Effort has been made, during 2007-2008
    shutdown, to take every opportunity to do
    conditioning, and progressive improvement has
    been observed.
  • Slightly negative effect due to the stripes is
    not excluded, but we have no evidence so far.

22
Summary
  • Aluminium Nitride plates and cooling system
    allows the magnet to be operational with
    approximately double the power deposition in the
    ferrite
  • Serigraphy (painted stripes) reduces predicted
    power deposition, in ferrite, by a factor of gt4,
    for LHC beam this is consistent with temperature
    measurements made during October 2007 scrubbing
    run (slide 18).
  • Serigraphy (painted stripes) reduces predicted
    power deposition , in ferrite, by a factor of 7,
    for CNGS beam this is consistent with
    temperature measurements made during October 2007
    (slide 19).

23
Transverse Impedance
  • Information re Transverse Impedance, and
    measurement techniques, can be found in
  • Tom Kroyers presentation Wire Measurements on
    the MKE Extraction Kicker Magnets APC meeting
    10/11/2006.

Shielding may increase transverse impedance at
100MHz, but reduces transverse impedance above
300MHz.
24
Future Plans
  • All 9 MKE magnets will be equipped (eventually)
    with serigraphy
  • 1 (and 2/7 !) of 5, installed, L-Type magnets
    equipped with serigraphy
  • 0 of 3, installed, S-Type magnets equipped with
    serigraphy
  • We have 1 spare L-Type 1 spare S-Type
    magnet (without serigraphy).
  • Spare Aluminium-Nitride plates ordered (expected
    delivery end of May 2008)
  • 8C11 ferrite in stock (that can be prepared
    serigraphed)
  • L-Type 7 top, 13 middle 8 lower. Therefore one
    complete magnets worth
  • S-Type 7 top, 10 middle 7 lower (including 4
    radioactive ferrites). Therefore one complete
    magnets worth
  • Ferroxcube to manufacture and return following
    L-Type 8C11 ferrites 6 top, 9 lower (date of
    expected return not yet known)
  • Plan is to replace one S and one L magnet at each
    SPS shutdown (using the normal operation year to
    convert the 2 spare magnets for the next
    shutdown) -- 4 shutdowns required!!
  • BUT potential problem of converting 2 spare
    magnets during operation if problem is
    encountered with an installed magnet, there may
    not be an available spare
  • If faster deployment is needed, we need to
    investigate the possibility to equip another 2
    magnets during the shutdown. In which case a
    shutdown of at least 3 months is necessary (work
    includes dismantling, machining of radioactive
    ferrite (radii), serigraphy (by another CERN
    service), mounting, vacuum tests, HV test and
    conditioning in lab, installation, vacuum, DC and
    pulsed conditioning in SPS).

25
Bibliography
  • T. Bohl, CNGS Beam in the SPS Beam Spectra,
    Note-2004-39
  • F. Caspers Impedance Measurement of the SPS MKE
    Kicker by means of the Coaxial Wire Method,
    PS/RF/Note 2000-004
  • F. Caspers, A Retrofit Technique for Kicker
    Beam-Coupling Impedance Reduction,
    CERN-AB-2004-048
  • F. Caspers et al, The Fast Extraction Kicker
    System in SPS LSS6, EPAC 2006
  • E. Gaxiola, Upgrade and Tests of the SPS Fast
    Extraction Kicker System for LHC and CNGS,
    PAC2004
  • E. Gaxiola et al, Performance Of The CERN SPS
    Fast Extraction for the CNGS Facility, PAC2005
  • E. Gaxiola et al, Experience with Kicker Beam
    Coupling Reduction Techniques, PAC2005 E.
    Gaxiola, SPS Extraction Kicker Performance with
    Impedance Reduction Measures, http//ab-div.web.c
    ern.ch/ab-div/Meetings/APC/2006/apc061110/EG-APC-1
    0-11-2006.pdf
  • T. Kroyer, Wire Measurements on the MKE
    Extraction Kicker Magnets, http//ab-div.web.cern
    .ch/ab-div/Meetings/APC/2006/apc061110/TK-APC-10-1
    1-2006.pdf
  • T. Kroyer et al, Longitudinal and Transverse
    Wire Measurements for the Evaluation of Impedance
    Reduction Measures on the MKE Extraction
    Kickers, AB-Note-2007-028
  • M. Timmins et al, SPS Extraction Kicker Magnet
    Cooling Design, AB-Note-2004-005 BT (Rev.2),
    TS-Note-2004-001 DEC (Rev. 2)
  • J. Uythoven, MKE Heating and Measured Power
    Spectra CNGS BEAMS , http//ab-div.web.cern.ch/a
    b-div/Meetings/APC/2004/apc041210/uythoven.pdf
  • J. Uythoven et al, Beam Induced Heating of the
    SPS Fast Pulsed Magnets, EPAC2004
Write a Comment
User Comments (0)
About PowerShow.com