Title: Present Status and Future Plans for the MKE Kicker Magnets
1Present Status and Future Plans for the MKE
Kicker Magnets
- Acknowledgements some slides are adapted from
previous presentations by Fritz Caspers, Enrique
Gaxiola, Tom Kroyer Jan Uythoven.
M.J. BARNES, AB/BT
2Transmission Line Kicker Magnets
- The kicker magnets installed at LSS4 LSS6 are
travelling-wave type magnets, each consisting of
7 ferrite cells - 30 year old, recuperated, equipment
- Transition piece between vacuum tank and kicker
magnet - Tank length 2174 mm
- Magnet length 1700mm.
MKE magnet in the clean room
3Cross-section of MKE Magnet(prior to 2003 at
LSS4 and 2005/2006 at LSS6)
- Ferrite C core constructed from three ferrites.
- In general, ferrite used is type 8C11 from
Ferroxcube. - Rectangular aperture for the beam.
Ferrite
Rectangular aperture
4LSS4
- LSS4 is used for extraction to CNGS/LHC
- LSS4 has 5 magnets, magnetically in series, each
powered by its own PFN and terminated in a
matched resistor - Three of the magnets have large (L) apertures
(147.7mm x 35mm) - Two of the magnets have small (S) apertures
(135mm x 32mm).
5LSS4 Parameters
CNGS LHC (Protons)
Energy 400 450 GeV/c
Deflection 0.54 0.48 mrad
Nominal PFN Voltage 50 51.2 kV
Nominal Impedance 10 10 O
Available rise-time 1.1 10 µs
Measured rise-time (1?99) 1.1 1.1 µs
Usable flattop length 10.5 7.9 µs
Flattop ripple ? 2 ? 1
E. Gaxiola et al, Upgrade And Tests Of The SPS
Fast Extraction Kicker System for LHC And CNGS,
EPAC2004.
6LSS6
- LSS6 is used for extraction to LHC
- As of 2006 LSS6 has 3 magnets, magnetically and
electrically in series, powered by a single PFN
and terminated in a short-circuit - Two of the magnets have large (L) apertures
(147.7mm x 35mm) - One magnet has small (S) aperture (135mm x
32mm).
7LSS6 Parameters
- Before 2006, LSS6 consisted of 4 series magnets
terminated in 10O. In 2005, proof of principle
tests were carried out, in lab, for a
short-circuit system - Rise and fall time increased
- Reduced PFN voltage for same deflection
- BUT voltage reversal.
LHC (protons)
Energy 450 GeV/c
Deflection 0.429 mrad
Nominal PFN Voltage 33.1 kV
Nominal Impedance 10 O
Available rise-time 8.8 µs
Measured rise-time 8 µs
Usable flattop length 7.9 µs
Flattop ripple ? 1
8Beam Induced Heating
- 2004 Need to reduce both beam impedance and
losses. - The MKE (SPS extraction) kickers LSS4 LSS6 are
heated by the beam due to their beam coupling
impedance. Ferrite heating is caused by coupling
between beam and real part of ferrite impedance. - High intensity beam can result in high power
deposition in ferrite.
9Past Developments
- Kicker magnets at LSS4 (2003) LLS6 (2005/2006)
equipped with - High thermal conductivity Aluminium-Nitride
(AlN180) plates - Water cooling
- PT100 temperature sensor.
10Measured Probe Temperature
- Design Space simulations were carried out to
determine the relationship between the highest
ferrite temperature and probe (PT100) temperature
(with water cooling). - Validated by machine measurements for 8C11
ferrite kick strength diminishes above 80C
measured, which corresponds to 125C highest
ferrite temperature, i.e. Curie temperature of
ferrite (AB-Note-2004-005 BT, section 5).
11Summary of situation at 2006
- Above about 120?C the 8C11 ferrites loose their
magnetic properties, this has been measured
during the scrubbing runs. - Note 4E2 ferrite has a Curie Temperature of
400?C. - Additional risk is structural damage above about
150?C. - For normal operation the beam is interlocked at
70 ?C measured (125?C on the ferrites) - For scrubbing runs the beam is interlocked
above 90?C measured, which is about 140?C on the
ferrites. - The water cooling system allows the magnet to be
operational with approximately double the beam
power deposition in the ferrite (AB-Note-2004-005
BT, section 5).
12Beam Coupling Impedance
- Beam coupling impedance can be reduced using
conductive stripes (serigraphy), i.e. interleaved
comb structure, directly printed onto the
ferrite blocks and having a reliable contact to
the metallic HV plates at either side - Capacitive coupling between stripes (stripes
carry beam image current).
13Longitudinal Measurements (1)
- Comparison between the two extreme cases
- MKE-L8, without any serigraphy on 8C11 ferrites
- MKE-L10, serigraphy on all seven 8C11 ferrite
cells. - Significant reduction of longitudinal impedance
from serigraphy. - Low frequency resonance directly linked to
geometry of serigraphy.
Note Impedance based on 2.2m length (1.7m
actual) hence should be increased by a factor of
1.3
L8
L8
L10
L10
14Dissipated Power
- Calculated using beam spectrum measured during
2004 SPS scrubbing run (data from J. Uythoven),
but theoretical beam coupling impedance - 272 LHC bunches in SPS at 450 GeV
- Comparison between fully shielded MKE-L10 and
MKE-L8 (no shielding at all).
Serigraphy (painted stripes) reduce calculated
power deposition by a factor of gt4, for LHC beam.
15Longitudinal Measurements (2)
- In a comprehensive measurement campaign data for
all types of MKE magnets was collected. - Conclusions
- High Curie temperature ferrite (4E2) displays
similar Real Impedance as 8C11 (Ferroxcube)
ferrite. - S-Type L-Type magnets, without serigraphy,
display similar Real Impedance.
16CNGS Power Depositions
- Calculated power deposition based on
- CNGS beam spectra measurements made by G.
Arduini and T. Bohl (4.5 s period) see
Note-2004-39 - 2.5x1013 protons per pulse
- A total cycle duration of 6 s.
- From Jan Uythovens presentation to APC, 10
December 2004 (real part of beam impedance - 2 x 210 W/m ? Thottest-equilibrium107?C
- Replace theoretical beam impedance of SPS kicker
by measured data, for MKE-L8 (see slide 13),
scaled by 2.2/1.7 - 2 x 178 W/m ? Thottest-equilibrium91?C (based
on 26?C tunnel) - Replace theoretical beam impedance of SPS kicker
by measured data, for MKE-L10 (see slide 13),
scaled by 2.2/1.7 - 2 x 25 W/m ? Thottest-equilibrium35?C (based
on 26?C tunnel) - Therefore shielding stripes on MKE-L10 kicker
reduce beam induced power deposition,
attributable to nominal CNGS beam, by a factor of
7 c.f. MKE-L8. - For 1.7x1013 protons per pulse 3 cycles per
39.6s, replace theoretical beam impedance of SPS
kicker by measured data, for MKE-L10 (see
slide 13), scaled by 2.2/1.7 - 75 W/m ? Thottest-equilibrium40?C (based on 26?C
tunnel)
17Measured Temperatures (2007)
- LHC type beam. No serigraphy (yet) at MKE4.
18Measured Temperatures (2007)
19Measured Temperatures (2007)
CNGS type beam. MKE6. Serigraphy on L10 results
in a factor of 6.4 (9/1.4) lower temperature rise
than L9 (factor of 7 expected see slide 16).
20HV Issues Pulse Shape for MKE6
Terminating the series magnets by a short
circuit the magnet peak voltage is reduced in
absolute value (33kV PFN 16.5kV magnet
voltage). However, because of the reflection from
the short circuit, there is a full negative
voltage (-16.5 kV) on the magnet. If we consider
peak to peak, the voltage is 2x16.5 33 kV. The
magnets are designed for 30kV.
21HV Breakdown in MKE6
- The MKE6 magnets were tested one by one in the
lab only S6 (adjacent to short circuit) was
therefore tested with the actual waveform shape. - After re-installation of magnets (2006-2007 shut
down), some conditioning (breakdown) problems
with magnet L10 (closest, electrically, to PFN).
But - L10 magnet is exposed to the longest duration
and dV/dt of both positive and negative voltage - Before 2008, the DC conditioning was only made
with positive polarity. During the past shut down
(2007-2008) we have also carried out conditioning
with negative DC so far it seems that such
conditioning has had good effect i.e. no HV
problems with L10 - Last year, we had little time to condition in
MKE6. Effort has been made, during 2007-2008
shutdown, to take every opportunity to do
conditioning, and progressive improvement has
been observed. - Slightly negative effect due to the stripes is
not excluded, but we have no evidence so far.
22Summary
- Aluminium Nitride plates and cooling system
allows the magnet to be operational with
approximately double the power deposition in the
ferrite - Serigraphy (painted stripes) reduces predicted
power deposition, in ferrite, by a factor of gt4,
for LHC beam this is consistent with temperature
measurements made during October 2007 scrubbing
run (slide 18). - Serigraphy (painted stripes) reduces predicted
power deposition , in ferrite, by a factor of 7,
for CNGS beam this is consistent with
temperature measurements made during October 2007
(slide 19).
23Transverse Impedance
- Information re Transverse Impedance, and
measurement techniques, can be found in - Tom Kroyers presentation Wire Measurements on
the MKE Extraction Kicker Magnets APC meeting
10/11/2006.
Shielding may increase transverse impedance at
100MHz, but reduces transverse impedance above
300MHz.
24Future Plans
- All 9 MKE magnets will be equipped (eventually)
with serigraphy - 1 (and 2/7 !) of 5, installed, L-Type magnets
equipped with serigraphy - 0 of 3, installed, S-Type magnets equipped with
serigraphy - We have 1 spare L-Type 1 spare S-Type
magnet (without serigraphy). - Spare Aluminium-Nitride plates ordered (expected
delivery end of May 2008) - 8C11 ferrite in stock (that can be prepared
serigraphed) - L-Type 7 top, 13 middle 8 lower. Therefore one
complete magnets worth - S-Type 7 top, 10 middle 7 lower (including 4
radioactive ferrites). Therefore one complete
magnets worth - Ferroxcube to manufacture and return following
L-Type 8C11 ferrites 6 top, 9 lower (date of
expected return not yet known) - Plan is to replace one S and one L magnet at each
SPS shutdown (using the normal operation year to
convert the 2 spare magnets for the next
shutdown) -- 4 shutdowns required!! - BUT potential problem of converting 2 spare
magnets during operation if problem is
encountered with an installed magnet, there may
not be an available spare - If faster deployment is needed, we need to
investigate the possibility to equip another 2
magnets during the shutdown. In which case a
shutdown of at least 3 months is necessary (work
includes dismantling, machining of radioactive
ferrite (radii), serigraphy (by another CERN
service), mounting, vacuum tests, HV test and
conditioning in lab, installation, vacuum, DC and
pulsed conditioning in SPS).
25Bibliography
- T. Bohl, CNGS Beam in the SPS Beam Spectra,
Note-2004-39 - F. Caspers Impedance Measurement of the SPS MKE
Kicker by means of the Coaxial Wire Method,
PS/RF/Note 2000-004 - F. Caspers, A Retrofit Technique for Kicker
Beam-Coupling Impedance Reduction,
CERN-AB-2004-048 - F. Caspers et al, The Fast Extraction Kicker
System in SPS LSS6, EPAC 2006 - E. Gaxiola, Upgrade and Tests of the SPS Fast
Extraction Kicker System for LHC and CNGS,
PAC2004 - E. Gaxiola et al, Performance Of The CERN SPS
Fast Extraction for the CNGS Facility, PAC2005 - E. Gaxiola et al, Experience with Kicker Beam
Coupling Reduction Techniques, PAC2005 E.
Gaxiola, SPS Extraction Kicker Performance with
Impedance Reduction Measures, http//ab-div.web.c
ern.ch/ab-div/Meetings/APC/2006/apc061110/EG-APC-1
0-11-2006.pdf - T. Kroyer, Wire Measurements on the MKE
Extraction Kicker Magnets, http//ab-div.web.cern
.ch/ab-div/Meetings/APC/2006/apc061110/TK-APC-10-1
1-2006.pdf - T. Kroyer et al, Longitudinal and Transverse
Wire Measurements for the Evaluation of Impedance
Reduction Measures on the MKE Extraction
Kickers, AB-Note-2007-028 - M. Timmins et al, SPS Extraction Kicker Magnet
Cooling Design, AB-Note-2004-005 BT (Rev.2),
TS-Note-2004-001 DEC (Rev. 2) - J. Uythoven, MKE Heating and Measured Power
Spectra CNGS BEAMS , http//ab-div.web.cern.ch/a
b-div/Meetings/APC/2004/apc041210/uythoven.pdf - J. Uythoven et al, Beam Induced Heating of the
SPS Fast Pulsed Magnets, EPAC2004