Construction Documents. Construction Phase. VA Seattle Seismic Program. Seattle Campus ... Worked with VA to develop specifications & RFQ. Proposals considered ... – PowerPoint PPT presentation

Number of Views:118
Avg rating:3.0/5.0
Slides: 31
Provided by: cash2
Category:

less

Transcript and Presenter's Notes

Title: SEISMIC REHABILITATION OF AN EXISTING BRACED FRAME HOSPITAL BUILDING BY DIRECT REPLACEMENT OF BRACES


1
SEISMIC REHABILITATION OF AN EXISTING BRACED
FRAME HOSPITAL BUILDING BY DIRECT REPLACEMENT OF
BRACES WITH BUCKLING-RESTRAINED BRACES


Presented by Cale Ash Degenkolb
Engineers Stacy Bartoletti Degenkolb Engineers

2
Presentation Topics
Seismic Evaluation
Seismic Upgrade Design Development
Construction Documents
Construction Phase
3
Presentation Topics
Seismic Evaluation
Seismic Upgrade Design Development
Construction Documents
Construction Phase
4
VA Seattle Seismic Program
NT
NHCU
Seattle Campus
CC
  • Bldg. 100
  • Diagnostic Treatment (DT)
  • Nursing Towers (NT)
  • Central Core (CC)
  • Nursing Home Care Unit (NHCU)
  • Energy Plant

DT
Energy Plant
5
Seismic Evaluation
DT Building Information
  • Designed in 1980 using VA Handbook H-08-8
  • Main hospital for campus
  • 4 stories
  • Stepped elevation
  • 18 ft. story height
  • Interstitial floors at 10 ft.

6
Seismic Evaluation
Lateral System
  • Braced Frames
  • Moment Frames

7
Seismic Evaluation
ASCE 31 Evaluation
  • Tier 2 Full-building Evaluation
  • Performance Objective
  • Immediate Occupancy

8
Seismic Evaluation
Evaluation Results Moment Frames
  • Pre-Northridge Moment Frames
  • Connections evaluated as force-controlled actions
  • Capacity limited to flange weld strength
  • Expected Performance
  • Limited damage to moment frame connections
  • Some welds may fracture
  • Repairs would not disrupt hospital functions

9
Seismic Evaluation
Evaluation Results Braced Frames
  • Expected Performance
  • Heavy damage to braced frames in design
    earthquake
  • Brace connections fracture
  • Column splices fail
  • Proposed Upgrade Scheme
  • Replace existing braces with Buckling-Restrained
    Braces
  • Reduces demand on column splices and brace
    connections

10
Presentation Topics
Seismic Evaluation
Seismic Upgrade Design Development
Construction Documents
Construction Phase
11
Seismic Upgrade
Methodology
  • Seismic upgrade designed using FEMA 356 and 2003
    IBC
  • Size braces using 2003 IBC, verify design using
    FEMA 356
  • Target Performance Level
  • Immediate Occupancy / BSE-2
  • FEMA 356 Analysis Procedure
  • Nonlinear Static

12
Seismic Upgrade
FEMA 356 Evaluation
  • BRB Supplier Selection Process
  • Manufacturer-specific properties
  • Worked with VA to develop specifications RFQ
  • Proposals considered from 3 domestic suppliers
  • Selected BRB supplier participated in design
    process

13
Seismic Upgrade
FEMA 356 Evaluation
IO, e1.4 LS, e2
  • Consider both existing and full build-out cases
  • Refine design through nonlinear static analyses
  • Modify BRB nonlinear properties based on brace
    strength

Typical BRB Nonlinear Properties
14
Nonlinear Static Evaluation Results
Existing Configuration
15
Nonlinear Static Evaluation Results
Built-Out Configuration
16
Seismic Upgrade
Final Brace Forces
  • Performance-based approach resulted in final
    brace sizes reduced by up to 20
  • Connection savings
  • Column strengthening eliminated

17
Presentation Topics
Seismic Evaluation
Seismic Upgrade Design Development
Construction Documents
Construction Phase
18
Construction Documents
Verify Existing Conditions
  • Original 1980 plans
  • Site visits
  • Structural steel shop drawings
  • Scaled elevations of (E) frames
  • Brace clear distance
  • Gusset plate geometry
  • Coordination with steel detailer

19
Construction Documents
Connection Design
  • BRB connection to existing gusset plates
  • Field welds to gussets allow field tolerances
  • Gusset strengthening new gussets required

20
Construction Documents
Interstitial Floor Resupport
  • Interstitial floor framed into braces

21
Construction Documents
Braced Frame Elevations
22
Presentation Topics
Seismic Evaluation
Seismic Upgrade Design Development
Construction Documents
Construction Phase
23
Construction Photos
24
Construction Photos
25
Construction Photos
26
Construction Photos
27
Construction Photos
28
Construction Photos
29
Construction Photos
30
SEISMIC REHABILITATION OF AN EXISTING BRACED
FRAME HOSPITAL BUILDING BY DIRECT REPLACEMENT OF
BRACES WITH BUCKLING-RESTRAINED BRACES


Presented by Cale Ash Degenkolb
Engineers Stacy Bartoletti Degenkolb Engineers
Write a Comment
User Comments (0)
About PowerShow.com