KING%20FAHAD%20UNIVERSITY%20OF%20PETROLEUM%20AND%20MINERALS%20CONSTRUCTION%20ENGINEERING%20 - PowerPoint PPT Presentation

About This Presentation
Title:

KING%20FAHAD%20UNIVERSITY%20OF%20PETROLEUM%20AND%20MINERALS%20CONSTRUCTION%20ENGINEERING%20

Description:

Most problem in construction is delay. Construction contract = contract duration ( specified period of time) ... VF = VS VD .6. VSP= could start time ... – PowerPoint PPT presentation

Number of Views:77
Avg rating:3.0/5.0
Slides: 9
Provided by: aimanh
Category:

less

Transcript and Presenter's Notes

Title: KING%20FAHAD%20UNIVERSITY%20OF%20PETROLEUM%20AND%20MINERALS%20CONSTRUCTION%20ENGINEERING%20


1
KING FAHAD UNIVERSITY OF PETROLEUM AND
MINERALSCONSTRUCTION ENGINEERING MANAGEMENT
DEPARTMENTCEM 510
  • CONSTRUCTION DELAY COMPUTATION METHOD
  • BY Jonathan Jingsheng Shi, Member , ASCE, S.O.
    Cheung and David Arditi, Member, ASCE
  • REF
  • JOURNAL OF CONSTRUCTION ENGINEERING AND
    MANAGEMENT JAN/FEB,2001 VOL. 127 NO.1
  • FEB28,2006

2
OBJECTIVEThis paper presents a method for
computing activity delays and assessing their
contribution to project delay. The method
consists of a set of equations, which can be
easily coded into a computer program that allows
speedy access to project delay information and
activity contributions.
  • BACKGROUND
  • Most problem in construction is delay
  • Construction contract contract duration (
    specified period of time) contractor must
    comply to achieve substantial completion within
    this time
  • For unexpected reasons contractor fails to
    complete the project within the contract period
  • Owner will claim liquidated damages and obtain
    contractual release extension of time
  • Delay analysis based on responsibilities delay
    excusable (compensable noncompensable ) and
    inexcusable
  • Project delay result from computing activity
    delay
  • Delay computation related to as-planned schedule
    contrasts as-built schedule
  • Traditional delay analysis method based always on
    CPM analysis on other words any delay on critical
    path delay the project completion
  • This method is not based on CPM and no need for
    updating CPM
  • Criticality of individual activities change from
    day to day due to delays accelerations which
    means if delay happen then extra effort from
    manager to up date the as-planned schedule with
    daily as-built information

3
APPROACH AS
  1. Examine the occurrence of delay
  2. Method for computing activity delays
  3. Method for computing the contribution of activity
    delays to project delay
  4. example

4
Occurrence of Construction delay
  • Activity completion delay to reasons
  • Delay in the start of the activity
  • Delay in the precedence activities
  • Delay in the start of the activity itself for
    some reason
  • Extend the duration of the activity

Delay precedence
Late design information
Delay deliveries
Succeeding Not delayed
Project Not delayed
No resources
Delay start
Succeed- ing delayed
Activity delay
Project delayed
Bad weather
Extended activity duration
Mang. decision
Less resources
Change scope
Change Site condition
5
Activity Variation
  • VSactual start time planned start time
    .....1
  • VFactual finish time planned finish
    time....2
  • VDactual duration planned duration
    ........................3
  • From CPM network following relationship
  • Actual finish timeactual start time actual
    duration ...4
  • Planned finish timeplanned start time planned
    duration.5
  • By subtract 4-5 then Eq 2 can be written
    as
  • VF VS VD ...6

6
Contribution of Activity Variation to Project
delay
  • VP actual completion time - planned completion
    time ( ve 0r ve )
  • Two factors
  • PDAC MEASURING THE PROJECT DELAY DUE TO
    ACCUMULATED ACTIVITY VARIATIONS CONTRIBUTED BY
    THIS AND ALL ITS PRECEDING ACTIVITIES
  • PDA MEASURING THE PROJECT DELAY CONTRIBUTED
    ONLY BY THIS ACTIVITY
  • Project delay is realized on the terminal
    activities ..mechanism start from terminals and
    continue backward through intermediate activities
  • Terminal activities are the last activities
    that do not have succeedings
  • Variation in the completion time of the terminals
    may contribute to project delay
  • PDAC actual finish time of the terminals -
    planned project finish time
  • PDA min ( VA , PDAC )
  • Intermediate activities those succeeding the
    terminals

j
i
7
Example Discussion
8
Conclusion
  • This paper presents a method for computing
    activity delays and assessing their contribution
    to project delay. The method consists of a set of
    equations, which can be easily coded into a
    computer program that allows speedy access to
    project delay information and activity
    contributions.
  • This method applicable to any intermediate
    construction stage for evaluating in-progress
    project delay
  • Traditional delay analysis method based always on
    CPM analysis require frequent updates of the
    as-built and as-planned schedules in order to
    keep track of the critical paths that may change
    daily. Such updating will require tremendous
    effort for site management. This method depend on
    as-planned schedule as basis of comparison for
    evaluating the variation in the project duration
    does not need to be updated.
  • This method is based on the finish-to-start
    relationship which is most common but not
    applicable to start-to-start or finish-to-finish
    relationships in current form , but equations can
    be expanded to these relationship as necessary.
Write a Comment
User Comments (0)
About PowerShow.com