Title: Project Management Part 2
1Project ManagementPart 2
Lecture 8
2PERT - The probabilistic Approach to Project
Scheduling
- Three time estimate approach
- a an optimistic time to perform the activity
- m the most likely time to perform the activity
- b a pessimistic time to perform the activity
3Assumptions for Distributionof Activity Times in
PERT
- For each activity in PERT/CPM Network
- 1. The probability density function for the
activitys completion time is a unimodal Beta
distribution - 2. Average (Mean) Completion Time
- m (a 4m b) / 6
- 3. Standard Deviation of Completion Time
- s (b - a) / 6
4Symmetric Unimodal Beta Distribution
m m
a
b
Unimodal Beta Distribution Skewed Left
Unimodal Beta Distribution Skewed Right
b
a
m
m
b
a
m
m
5Example (Mean and Standard Deviation ofActivity
Times for a Project)
D m 50 s 12
A m 10 s 1
C m 25 s 4
Finish
B m 20 s 2
E m 24 s 5
6Determining the Distribution of the Overall
Project Completion Time
- 1. For each activity j, calculate
- mj (a 4m b) / 6
- sj (b - a) / 6
- 2. Determine the critical path using the mjs as
fixed times. - 3. The overall project completion time has a
normal distribution with - Mean m S mj
- Variance s 2 S sj 2
- Standard deviation s Ö s 2
7Klone Computers Inc. Example
8- Management at Klone is interesting in the
following - The probability that the project will be
completed within 194 days - A reasonable interval estimate of the number of
days to complete the project - The probability that the project will be
completed within 180 days - The probability that the project will take longer
than 210 days - An upper limit for the number of days within
which it can be virtually sure the project will
be completed
9Solution
- The mean, variance and standard deviation for
activity A can be found by - mA (76 4(86) 120) / 6 90
- sA (120 - 76) / 6 7.33
- sA2 (7.33)2 53.73
10(No Transcript)
11Example Network
E 21
B 15
C 5
A 90
F 25
G 14
D 20
H 28
FINISH
J 45
I 30
12The Critical Path A-F-G-D-J
- Expected completion time of the project
- m mA mF mG mD mJ
- m 90 25 14 20 45 194
- Project variance
- s2 sA2 sF2 sG2 sD2 sJ2
- s2 53.78 5.44 4.00 9.00 13.44
85.66 - Standard deviation for the project
- s Ö s 2 9.26
13- X completion time of the project
- Z standard normal random variable
- Z (X m ) / s
14- 1. The probability that the project will be
completed within 194 days - P(X?194) P(Z ? 0) 0.5000
X Z
194 0
152. A reasonable interval estimate of the number
of days to complete the project 95 Interval m ?
z0.25 s z0.25 1.96 194 ? 1.96 (9.255) 194 ?
18.14 days 175 213 days
X Z
194 0
16- 3. The probability that the project will be
completed within 180 days - P(X?180)
- x 180
- Z (180 - 194) / 9.255 - 1.51
- P(X ? 180) P(Z ? -1.51) 0.5000 0.4345
- 0.0655 (6.55)
0.4345
0.5
X Z
194 0
180 -1.51
17- 4. The probability that the project will take
longer than 210 days - P(Xgt210)
- x 210
- z (210 - 194) / 9.255 1.73
- P(X gt 210) P(Z gt 1.73) 0.5000 0.4582
- 0.0418 (4.18)
0.4582
0.5
X Z
194 0
210 1.73
18- 5. An upper limit for the number of days within
which it can be virtually sure the project will
be completed - P(Z ? z) 0.9900
- P(0 ? Z ? z) 0.4900
- Z (x m ) / s
- x m zs
- x 194 2.33 (9.255) 215.56 days 216 days
0.4900
0.5
X Z
194 0
x 2.33
19The Critical Path Method
- NT Normal completion time
- NC Normal cost
- CT Crash completion time
- CC Crash cost
20CPM Linearity Assumption
- If any amount between CC is spent to complete an
activity, the percentage decrease in the
activitys completion time from its normal time
to its crash time equals the percentage increase
in cost from its normal cost to its crash cost.
21Time
Job Cost 2600 Job Time 18 days 25 of the
extra cost gives 25 of the maximum time reduction
Normal NC 2000 NT 20 days
20
16
Crashing NC 4400 NT 12 days
12
8
4
Cost x 1,000
10
15
20
25
30
35
40
45
5
22- T NT - CT the maximum possible time reduction
(crashing) of an activity - C CC - NC the maximum additional (crash)
costs required to achieve the maximum time
reduction - M C / T the marginal cost of reducing an
activitys completion time by one unit
23Tom Larkins Political Campaign
24The Project Network
A
H
C
G
F
D
E
I
B
FINISH
25(No Transcript)
26Campaign Crash Schedule
27Campaign Status Report End of Week 20
28Budget, Completion Time, and Costs for Campaign
29Budget, Completion Time, and Costs for Campaign