Title: Developing Natural Gas Infrastructure in the Americas: the Mexican case
1Developing Natural Gas Infrastructure in the
Americas the Mexican case
- NARUC Committee on Gas
- Francisco Salazar Diez de Sollano
- Chairman, CRE
- July 17, 2007
2Introduction CRE
- CRE (Comisión Reguladora de Energía) was created
in 1992 as a consulting body to the Secretary of
Energy. Its objective was to prepare the rules
that would regulate the relationship between the
States utilities and the private investors in
the power sector. - In 1995, the Congress passed a reform opening the
downstream activities in the natural gas sector.
Then, CRE was also constituted as the formal
regulator of the energy sector and was given
operational and technical autonomy. - CREs mandate is to promote the efficient
development of the activities it regulates. In
doing so, CRE looks for a balance between the
interest of the consumers and that of the
investors.
3CREs regulation powers
4Natural gas demand
- According to the Ministry of Energy(1), natural
gas demand was 6.549 bcfd in 2006 . - 48 corresponded to the oil sector 35.7 to the
power sector 14.6 to the industry (including
Pemex Petrochemicals), and 1.6 to residential
and other services. - Natural gas demand is expected to increase at an
overall annual rate of 3.9 over the next 10
years. - (1) Prospectiva del mercado de gas natural
2006-2015
5Natural gas forecast 2005-2015
3.9
2.8
Source SENER 2006 2015 Prospectiva del Mercado
de Gas Natural
6Gross NG Balance 2005-2015
9.49
9.11
8.69
8.28
7.90
7.58
7.05
6.65
6.61
6.11
5.72
7Natural gas for power plants
- Power forecasts 2005-2015
- 4.8 annual demand growth rate from 191 TWh in
2005 to 305 TWh in 2015 - 24 GW of new capacity required to meet demand
(approx. 49 of current capacity) - CFE will install 23,545 MW during the next decade
- Combined cycle power plants will grow from 33 to
51 of the total capacity by 2015 - 7.3 average annual natural gasgrowth over the
next decade (for power)
8Natural gas imports 2005-2015
Imports will peak by 2015 at 2.2 BCFD
Source SENER 2006 2015 Prospectiva del Mercado
de Gas Natural
9How to face increasing demand?
- Continue promoting private investment in
- Development of LNG terminals along both the
Pacific and the Gulf coasts - Pipeline infrastructure both to strengthen
cross-interconnections and access to new LNG
plants - Start exploiting coal bed methane reserves
- Focus Pemexs investment in areas of paramount
interest such as exploration and production of
oil and gas
10CREs regulation objective
- CREs regulation must
- Ensure technical engineering excellence through
modern standards and third-party auditing
procedures - Approve general terms of service that satisfy
users needs and reflect current practice in
industry - Approve rates that are competitive and allow fair
rates of return to investors - Lead to predictable and stable regulatory
conditions with adequate flexibility
11Permits granted by CRE
Capital
Length
Type
Licenses
Investment
(MM USD)
(km)
Transport
12,354
155
1,979
Open
1,744
11,501
20
Access
Non-Open
135
853
235
Access
Distribution
22
35,494
1,669
5
n.a.
LNG terminals
2,000
TOTAL
182
47,848
5,648
LNG total storage capacity of 1,250,000 cubic
metres
12(No Transcript)
13Developing LNG terminals
- LNG project solutions are varied
- Having a predictable and transparent regulation
gives investors and developers the flexibility to
structure their projects in a variety of ways - Terminal Developers (TD) can participate in
acquisition of LNG through different schemes - TD can sign long-term contracts with utilities
and shippers and/or assign all or a fraction of
the terminal capacity to a marketing function - Shippers can arrange for their LNG deliveries or
have the terminal/marketer do it. - CRE has resolved all LNG applications in
approximately 12 18 months
14Developing LNG Terminals
- Leading times are currently very long for LNG
projects - Construction time is typically 3 years
- There is an increasing demand of LNG terminals,
especially in North America - Costs of steel and concrete have increased
significantly - Additionally, liquefaction plants have been
delayed in several countries
15LNG regasification plants
- Six applications submitted, 5 permits granted
- Commercial operation Sep 30th, 2006 (Altamira)
- ECA (Sempra) operation in March 2008
Libertad
- Altamira
- Shell-Total
- CFE bid
- 140,000 m3 x 2
- 0.5 - 1.1 BCFD
- Baja California
- 1. ECA (Sempra)
- 160,000 m3 x 2
- 1.0 1.3 BCFD
- 2. Shell Baja
- 170,000 m3 x 2
- 1.0 1.3 BCFD
Topolobampo
Manzanillo
16Problems
- Private projects associated to private industry
and LDCs have had limited success - Large consumers are reluctant to sign long term
contracts - Pemex supply and services are preferred
- Competing fuels are priced with non-market
criteria - As a result, most transport and LNG
infrastructure is tied to CFEs need for CC
generators and Pemex requirements - Most of the new combined cycle power plants are
located near Pemex transmission system or LNG
terminals - Both companies dominate the gas market
17Towards a new transport model
- CRE is currently reviewing PEMEX SNG (national
pipeline system) rates, the methodology to
calculate them and the corresponding tariffs. - The idea is prepare SNG to be the main part of a
National Integrated Transport System (SNI) - Issues being discussed include using a postage
stamp instead of a mcf mile methodology, desired
levels of central planning and expansion of the
system, roll-in criteria, desired degree of
competition, etc. - Although SENER is responsible for energy policy
and planning, CREs opinion is central in this
issue.
18Conclusions
- Natural gas foreseen demands growth in Mexico
will require infrastructure to secure supply. - So far, CRE has developed a predictable,
transparent regulation that can accommodate
flexibility to investors. - Current infrastructure in Mexico has been mainly
linked to CFE and PEMEX through long term
contracts. - New infrastructure to allow regional growth and
active private participation in new projects
poses regulatory challenges to the CRE.