Title: Premises for LargeScale Implementation of Distributed Generation in Romania
1- Premises for Large-Scale Implementation of
Distributed Generation in Romania
Camelia Vasile, MSc Eng
2Contents
- General framework
- Structure and prospects
- Targets
- Legislation
- Promotion Mechanism
- Regulatory obstacles and necessary measures
- Research priorities
3General framework (1)
- DG has, in the long term, the potential to make a
large contribution to the EU energy supply,
achieving security of energy supply and
environmental sustainability. Main targets - Decreasing the cost of electricity and fuel
supplies to competitive levels developing highly
efficient concepts and achieving major cost
reductions in the entire production chain - Improving reliability, safety, availability,
system efficiency and durability with long
maintenance intervals of electricity supply - Transforming the conventional power transmission
and distribution grid into a sustainable, unified
and active energy service network with a large
share of DG requires new concepts and systems for
planning, control and supervision.
4General framework (2)
-
- In Romania - DG utilization is making its first
steps - - interest of investors in installing WPPs
increased considerably - - is expected that investments in DG technologies
will grow - Potential for RES - very high
- Successful projects are in place, but the
investment rate in the renewable sector is quite
low
5Structure and Prospects (1)
Structure of electricity production in 2008
6Structure and Prospects (2)
- Hydro energy - the biggest share in the total
participation of RES to the power balance - Hidroelectrica (state-owned company)
- 275 HPPs and power pumping stations summing up an
installed capacity of 6,374 MW - main output comes from large hydropower plants
-
- Power generation in HPPs in 2008 17 TWh
- Strategy for the period 2003-2025
- in 2025 70 of the hydro potential will be used
(compared to 50 today) - electricity production - 24 TWh for an installed
capacity of 9,000 MW
7Structure and Prospects (3)
- Installed capacity in wind turbines - 11 MW
- Great number of private investors interested in
installing new wind generation capacities - wind
power the only RES for which there are important
planned projects - Requests for grid connection received by the TSO
- about 7000 MW - Estimated that only 1000 1500 MW will be
integrated into the NPS in a first phase - Connection agreements for an installed capacity
of 900 MW
8Structure and Prospects (4)
- A certain increase in solar electric utilization
In the last years - High investment costs
- Not expected to have a significant contribution
in the power balance
9Targets for RES (Energy Strategy of Romania)
- RES targets (electricity produced from RES in
the gross domestic electricity consumption) -
10Existing Legislation
- Law 220/2008 establishing the promotion system
for RES electricity generation - GD 750/2008 approving state subsidies for RES
utilization - GD 90/2008 - Regulation regarding the
interconnection of generators to the power grids
of national interest - Energy Law no 13/2007 - transposes articles from
the EU Directive 2003/54/CE concerning common
rules for the internal market in electricity - GD 1535/2004 approving the National Strategy for
Renewable Energy Sources Utilization - GD 443/2003 regarding the promotion of
electricity production from renewable energy
sources transposes the EU RES-e Directive
2001/77/EC provisions
11RES Promotion Mechanism (1)
- Green certificates and mandatory quota system
- Mandatory quotas for the suppliers settled until
2020 - 8.3 for the period 2010 2012
- 16.8 for 2020
- GCs price
- Min 27 Euro/certificate
- Max 55 Euro/certificate
- Penalty system
- Penalties for non fulfilment of the quota
- 70 Euro/certificate for the non-purchased
certificates - Collected penalties are used annually for
investments in the national grid
12RES Promotion Mechanism (2)
- The electricity producers receive from the TSO
13Regulatory obstacles to the deployment of DG and
necessary measures (1)
- Responsible for RES energy promotion - a number
of institutions and state administrative
authorities (Ministry of Economy, local
authorities, ANRE, ARCE) not appointed by law to
execute economic activities (e.g. execution of
pilot projects in the RES field, implementation
of new execution projects for new capacities,
etc.) and not having a specific apparatus for
developing such activities - Established responsibilities and competencies in
the field of RES are not clear - Management of such activities can only be
achieved by dedicated structures
- Measures
- Creation of a management body within the Ministry
of Economy and Finances dedicated to the activity
of RES energy promotion and achievement of RES
strategy goals
- Obstacles
- Non-existence of a competent authority
responsible for the implementation of the
strategy for RES utilization
14Regulatory obstacles to the deployment of DG and
necessary measures (2)
- GD 219/2007 transposes the provisions of EU
directive 2004/8/EC concerning the promotion of
cogeneration based on a useful heat demand - No steps made towards the elaboration of
secondary legislation necessary for - adoption of the harmonized reference values and
of applicable correction factors - approval of bonus-type support scheme applied to
the cogeneration electricity production - analysis for the national cogeneration potential
of Romania - Exception procedure for issuing the guarantees
of origin for the electricity produced in
cogeneration of high-efficiency
- Obstacles
- Lack of secondary legislation for the promotion
of CHP
- Measures
- Elaboration of secondary legislation for the
promotion of cogeneration of high-efficiency
15Regulatory obstacles to the deployment of DG and
necessary measures (3)
- Grid operators - priority connection of all RES
or cogeneration units investments for
integration of such generators - Costs that affect the grid operators are related
to - grid strengthening and development
- back-up capacities from other power plants that
have to be kept in reserve for cases of total
generation outages of DG, such as WPP, as well as
for balancing variations in wind energy
injections - development of new activities.
- These costs submitted to the regulator for
approval and then reflected into the price of the
consumers
- Obstacles
- Regulatory uncertainties of cost recovery of
distribution and transmission companies for RES
integration into the grids
- Measures
- Development of a mechanism for determining a fair
cost allocation for DG integration
16Regulatory obstacles to the deployment of DG and
necessary measures (4)
- Project developers need to obtain an entire
package of permits and approvals from a series of
state and municipal authorities, depending on the
project specifics - The process of obtaining all approvals is very
heavy (could take up to two years) - delays for
the investment project.
- Obstacles
- Time consuming administrative procedures for
development projects - Lack of informational support for potential DG
investors
- Measures
- Establishing procedures for DG project proposals
and diminishing the response times - Improvement of the Guide for RES electricity
producer with information related to the
authorization procedure for a RES generation
capacity construction
17Research priorities (1)
- A. Assessment of the potential
- Old potential for RES and its values calculated
at country level - No updating of the RES potential maps
- No CHP potential studies
- Lack of knowledge about the protected areas on
which constructions are not allowed - problems in
obtaining the environmental permit - No centralized database regarding the areas with
RES potential or a portfolio of RES projects to
help the investors in selecting their investment
location
- Measures
- Inventory of renewable energy sources by sources
and regions and exclusion of protected areas from
the RES potential maps - CHP potential study
18Research priorities (2)
- B. Technical priorities
- The solution studies emphasized a series of
problems related to two important issues - the connection possibilities
- how the NPS grid should react when it has to deal
with a power source with random and intermittent
operation mode
- Problems signaled in relation to the grid
connection - limited possibilities of the existent networks
(distribution as well as transport) to evacuate
the power produced by the wind farms - the effects of wind farms connection to the
grids, especially regarding the voltage level and
the power quality
19Research priorities (3)
- Research on Impact of DG on the Design and
Operation of the Grid - The solution studies highlighted the following
- At MV level (20 kV)
- connecting WPP of maximum 10 MW - due to reduced
capacity of the evacuation line or due to risk of
exceeding the short circuit capacity of the
interconnection substations - difficulties in maintaining the flicker effect in
the limits set by the technical norms - problems in keeping the voltage in its admissible
limits - At HV level (110 kV)
- need of tele-transmission means (e.g. optical
fiber) - additional expenses for the connection
options of a WPP directly to an existing line - the HV grid needs to be developed - research for
its transformation from a passive network into an
active one - At transport network level (220 kV, 400 kV)
- The Romanian NPS does not have enough quick start
tertiary reserves required for wind operating
systems - Technical connection permits issued for 2650 MW
- Quick start tertiary reserves are available for
only 800 MW (analyses of the National Dispatch
Center - DEN)
20Research priorities (4)
- Research on grid elements
- Contemporary power electronic interface
- Use of last generation of power electronics and
invertors available in countries with better
experience in DG for improving the reliability
and flexibility of the distribution system - Romanian research community needs to focus on the
improvement in manufacturing, design and
technology - researches in converter topologies and control
- the use of new materials for semiconductors and
magnetic components - ICT for network management
- Limited possibilities for financing innovations
in the network - ICT implementation should be
carried out gradually, after a preliminary plan
taking into account the priority of urgent needs,
expenses and time needed for their introduction
21Research priorities (5)
- System research
- Assessment and improving the grid possibilities
to integrate DG - Studies regarding the impact of WPPs on the NPS
emphasized that the use of dimensioning criteria
applicable in the case of classical power plants
is not conclusive. For instance, the connection
solution analysis cannot be done only at peak
load - DGs like WPPs cannot be planned so that
they cannot be correctly considered in covering
the load curve - Distribution and transport grids require
strengthening investments for wide penetration of
DG - Another problem - the calculation of the
transitory stability - Wind forecast - no proper solution for this issue
e.g. a cooperation between the TSO, the
National Agency for Meteorology and wind dispatch
operators
22Research priorities (6)
- System research
- Active Design Concept for the Grid Structure
- Requests for the installation of over 12,000 MW
in WPPs up to 2012 - unknown if all this power
could be installed - Difficulties for the grid operators in planning
the development of the distribution and transport
grids - Is important that grid operators develop
active network management for integrating DG
into the grid
23Research priorities (7)
- System research
- Demand Side Management
- DSM programs - planning, implementing, and
monitoring activities of electric utilities,
designed to encourage consumers to modify their
level and pattern of electricity usage - The various opportunities for including the
consumers into the grid operation are not used in
the Romanian electric system and need to be
properly researched
- Micro-grids
- The micro-grid concept allows for local control
of distributed generation thereby reducing or
eliminating the need for central dispatch. - A high level of interest and research on the
utilization of micro-grids concept at EU level - Research is also needed to be done in Romania
towards its implementation
24Research priorities (8)
- Research on Electricity Storages
- DG technologies are intermittent, requiring
demand flexibility, backup power sources, and
very likely enough electricity storage for days
to perhaps a week - Strategically-placed storage systems can increase
the utilization of existing TD equipment and
defer/eliminate the need for costly TD additions
- In Romania the most common storage technology is
pumped hydro storage
- Research on DG Technologies
- Equipment manufacturing is done on a very
small-scale and for the new DG investments
imported equipment and systems are preferred
25Research priorities (9)
- C. DG Economics
- The economics of DG depend on complex mix of
economic factors - On one hand - economic advantages over power from
the grid - On-site production avoids TD costs
- Production can be limited to parts of the day
when grid electricity is expensive, with grid
power purchased at less costly periods - DG can be available in the case of a power system
outage to assure a more reliable supply - DG may also be better positioned to use
inexpensive fuels (ex. local biomass) - On the other hand - higher unit capital costs/kW
due to high combined capital, operation, and
maintenance costs of DG systems - Understanding of the fundamental economics of DG
is essential for policymakers to arrive at sound
decisions regarding the future of DG
26Research priorities (10)
- D. Pricing Cost allocation
- An analysis should be done towards finding
whether the feed-in-tariff would be a better
support scheme for RES investments encouraging - Research on the development of a mechanism for
proper allocation of costs to distribution and
transmission companies for DG integration to the
grids is needed
27Priorities timing
28- Conclusions
- In Romania DG utilization is in its very
beginning but it is expected that the investments
in DG technology applications will grow -
- In order to integrate DG to the Romanian power
system there is need for sustained research and
measures to overcome the obstacles of regulatory,
economic and technical nature -
- With the recent rush for wind power in Romania
additional measures are needed in order to ensure
the security and stability of the NPS in
accordance with the UCTE methodology on system
adequacy
29THANK YOU FOR YOUR ATTENTION
30Contact
- CAMELIA VASILE, MSc Eng.
- Institute for Studies and Power Engineering
(ISPE) - Energy and Environment Division
- 1-3 Lacul Tei Blvd.
- 020371 Bucuresti
- Romania
- ph. 40 21 2061331
- fax. 40 21 2101255
- email camelia.vasile_at_ispe.ro
- www.ispe.ro