Substrate-Paddle-Base - PowerPoint PPT Presentation

About This Presentation
Title:

Substrate-Paddle-Base

Description:

Peter Cooke 28 Feb - 1 March 2006 - VELO PRR. 4. Substrate Dimensions. Carbon ... Peter Cooke 28 Feb - 1 March 2006 - VELO PRR. 5. Materials Preparation TPG ... – PowerPoint PPT presentation

Number of Views:36
Avg rating:3.0/5.0
Slides: 28
Provided by: peter526
Category:

less

Transcript and Presenter's Notes

Title: Substrate-Paddle-Base


1
Substrate-Paddle-Base
  • Peter Cooke

2
Substrate-Paddle-Base
  • Substrate Production
  • Paddle Base Feet Component Production

3
LHCb Substrate Production
  • Substrate Dimensions
  • Materials and preparation
  • Lay-up
  • Inspection and Packaging
  • Recommended Curing Instructions
  • Summary

4
Substrate Dimensions
  • Carbon Fibre 177 x 123mm
  • TPG 169 x 115mm with semi-circular cut-out
    (detector area)
  • 4mm Carbon Fibre frame surrounding TPG

5
Materials Preparation TPG
  • 400um TPG board cut to 169 x 115mm
  • Semi-circular area removed
  • Abrade both sides with course emery paper
  • Cleaned and degreased with alcohol
  • Left to dry

6
TPG with cut-out
7
Preparation Carbon Fibre
  • Supplier Amber Composites UK
  • Carbon fibre Pre-preg 120 gm plain weave, epoxy
    resin impregnated
  • Cut to size 177 x 123mm
  • 2 Pieces weave direction 0 90 deg
  • 2 Pieces weave direction /- 45 deg
  • Pre-preg approximate cured thickness 0.125mm per
    layer

8
Lay-up Procedure
  • Release film applied to flat steel plate
  • 1st layer 0 90 deg on flat plate
  • 2nd layer /- 45 deg on top
  • TPG placed centrally on 2nd layer
  • 4mm strips of pre-preg surrounding TPG (and in
    cut-out) 3 layers with orientation of fibres
    balanced
  • 3rd layer /- 45 deg placed over previous
  • 4th layer 0 90 deg to complete

9
Carbon Fibre and TPG
10
Recommended Cure
  • Amber Composites
  • Fibre T300
  • Resin E722.02 45 RW
  • Increase temp. to 120 C _at_ 3 C/ min
  • Increase pressure to 90 psi
  • Hold for 1 hour
  • Cool to 60 C before releasing pressure

11
Inspection Packaging
  • Visual Inspection - surface finish
  • Inspection Micrometer/Smartscope
  • Substrates have release film applied to each face
    to protect resin
  • 10 substrates are sandwiched together between two
    6mm thick aluminium plates
  • Surrounded in foam and packed in cardboard box
  • Shipped off to Stevenage Circuits

12
(No Transcript)
13
Summary
  • Carbon Fibre remaining to produce up to 80 more
    substrates
  • 39 pieces of TPG in stock (20 on order)
  • Carbon Fibre stored in freezer _at_ -18 C
  • TPG stored in locked cupboard
  • Can produce 10 per week

14
LHCb Paddle/Base Components
15
Paddle/Base Assembly
16
Base and Feet Manufacture
  • Base Cut from solid sheet of carbon fibre and
    machined in-house.
  • Invar feet CNC Wire Eroded in-house to
    guarantee accuracy. Spigot on right foot
    tolerance 0.000 to 0.008
  • Feet numbered in pairs

17
Paddle Fabrication
  • Material Pre-preg
  • ACG VTM264/CF0300-42RW 200 gram 2 x 2 Twill
    (Stored18deg C)
  • Female mould tool CNC machined and hand finished
    in two halves.
  • Dowelled and fastened together during lay-up
  • Tool treated with PTFE release solution and
    buffed to a gloss finish

18
(No Transcript)
19
(No Transcript)
20
Paddle Lay-up
  • Carbon fibre cut to templates, 2 layers per face.
    1 _at_ 0/90 deg and 1_at_ /-45 deg
  • Apply fibre to each face, 0/90 then /-45
  • Final thickness over major area of paddle 0.5mm
  • Rear face fibre flush to tool surface
  • Front face overlapping tool face 6 2mm along
    length
  • 3 x 12mm wide strips added to each face at the
    topmost area of the tool.

21
(No Transcript)
22
Paddle Lay-up (cont)
  • Add release film and bleed ply fabric to the
    exposed fibre
  • Add a strip of breather fabric to each side
  • Make vacuum bag and fit into front side of tool
  • Place rear side of tool over dowels on the top
    and fasten into place
  • Place assembly into large vacuum bag and seal
    inner to outer bags

23
Paddle Cure
  • In autoclave
  • Apply vacuum
  • Heat to 65 deg C at 0.5 deg C/ minute
  • At 65 deg C apply 90 psi
  • Hold for 16 hours
  • Cool, release pressure and vacuum
  • De-mould the part

24
(No Transcript)
25
(No Transcript)
26
Parts Inspection
  • Visual inspection Surface finish, conformity to
    mould-tool, loose fibres, resin high spots, etc.

27
Summary
  • 17 - Paddles ready
  • We have enough carbon fibre stored in freezer to
    produce another 80 paddles
  • Carbon Fibre Bases ready Total 80
  • Invar Feet ready Total 80 sets
  • Aluminium inserts ready Total 80 sets
Write a Comment
User Comments (0)
About PowerShow.com