Evolution of Design Build Projects for the Federal Government PowerPoint PPT Presentation

presentation player overlay
1 / 43
About This Presentation
Transcript and Presenter's Notes

Title: Evolution of Design Build Projects for the Federal Government


1
Evolution of Design Build Projectsfor the
Federal Government
Lou Martinez Martinez Engineering Management
Services, Inc
  • Purpose - History of Design-Build Contracting
  • Organization -
  • Eight Example Projects Enhanced by Design
    Build
  • Project and Contract Parameters
  • Advantages Over Conventional Methods
  • Test

2
Lous Background
  • 6 years Army helicopter pilot
  • 20 years USACE
  • Saudi Arabia
  • Baltimore
  • Nuremberg DPW
  • Mobile
  • 15 years Brown Root/KBR
  • Mobile PM
  • Washington DC SVP Design Construction
  • 4 years MEMSI

3
(No Transcript)
4
Redstone Arsenal John J. Sparkman Center(first
USACE design build)
Acquisition plan 1991 Contractor selected late
1992
  • 59 Million
  • 687,000 SF

Centex Rooney Smallwood, Reynolds, Stewart
Stewart
Completed August 1994 six months ahead of schedule
5
Parameters
DESIGN BUILD IN ORDER TO MAKE TIMELY AWARD IN
PROGRAM YEAR
Lessons Learned Takes more effort to
advertise, evaluate and award Must Narrow
Bidder Field Minimize Review After
Proposal Minimize Submittal Requirements Allow
Construction Time Set by Contractor
6
1986 USAF REPORTon Design Construction
Delivery Strategies
  • Purpose - Improve Acquisition Process
    With More Timely and Cost-Effective Delivery
    Methods
  • Recommended Commercial Business Processes
  • Obtained Congressional Approval for D/B

7
(No Transcript)
8
Recommendations for Better Programming and
Construction Processes
Interviewed commercial firms
9
Sun Oil Middle Creek Abatement(Brown Root, Inc
example of Industrial use of business processes)
  • Awarded January 1992
  • 150 Million
  • 50k normal flow vs. 250k/25 year design storm
  • 40,000 cu yards contaminated soil
  • 100 year old refinery Marcus Hook PA
  • Two states DE and PA
  • EPA negotiated completion by 1994
  • Multiple geographic agencies

10
SUN OILMIDDLE CREEK ABATEMENT
  • Parameters
  • Fixed/unit price
  • Contractor designed sludge pile
  • Contractor managed temp pumping system
  • Design build in order to meet EPA schedule, and
    accomplish the above.

11
DoS Security Upgrades Program
7 August 1998 Nairobi, Kenya Dar Es Salaam,
Tanzania 224 (12 Americans) killed gt 4,000
injured
12
DoS Security Upgrades Program(awarded to KBR in
1999)
before
after
13
DoS Security Upgrades Program
  • Stand off
  • Barriers
  • Perimeter walls/fences
  • Access control (CAC)
  • WTMD
  • Explosive detection systems
  • X-ray
  • Local/over-ride control
  • Bullet Proof doors windows
  • Cameras
  • Detection systems
  • Deterrent systems

Examples of Stand Off
14
Locations Around The Globe
DoS Security Upgrades Program
6
9
12
12
More than 50 locations around the world
15
Compound Access Control
DoS Security Upgrades Program
16
Project Execution
DoS Security Upgrades Program
  • A. COST REIMBURSED PGM MANAGEMENT
  • Phase I - Scope and engineering surveys
  • Phase II Design and Estimate
  • Civil / architectural
  • technical security
  • B. Lump Sum Fixed Price Task Orders
  • Phase III Civil / architectural construction
  • Phase IV - Technical security

17
DoS Security Upgrades Program

Barrier examples
  • PARAMETERS
  • Execution Speed
  • Multiple designers
  • Construction resources tailored to site
  • Pre-purchased and stored materials
  • Scope flexibility
  • Funds control

18
Guantanamo Detainee Facilities
Photo courtesy globalsecurity.org
19
OBJECTIVE Replace this in 60 days
(hundreds more coming)
Awarded under CONCAP in February 2002
20
REPLACE CAMP X-RAY
Parameters CONCAP terms cost plus award
fee Extremely Short Schedule MULTICULTURAL
WORKFORCE (800) Pilipino, Indian, Jamaican,
British 24/7 Operations Construction on GTMO With
Barged Materials Replaced Contractor and
Workforce Design on the fly
Photo courtesy globalsecurity.org
21
Hundreds of Shipping Containers
Used everything but the oink
Photo courtesy globalsecurity.org
Photo courtesy globalsecurity.org
22
Container Modification
23
Beginning Construction
CAMP 1-404 CELLS, EXPEDITIONARY MAXIMUM
SECURITY ISSUED FEB 2002 16 MM
Photo courtesy globalsecurity.org
24
Hanging Utilities
CAMPS 2 3- 404 MORE CELLS ISSUED APRIL AND
JULY 22 MM LESS THAN 90 DAYS EACH
Photo courtesy globalsecurity.org
25
Assembled in Groups of Six and Insulated
Photo courtesy globalsecurity.org
26
Completed 36 Person Block
Photo courtesy globalsecurity.org
27
Hospital Operating Room
28
Two Final Facilities
STATE OF THE ART 20 MM EACH 10 MONTHS DESIGN
BUILD Design/build team Hensel Phelps/Shenkel
Shultz
Photo courtesy globalsecurity.org
29
Final Facilities
Photo courtesy globalsecurity.org
30
Kabul Embassy Project
31
Kabul Embassy Project
150 MM awarded 3/2003 as cost reimbursable
Chancery plus housing All materials shipped
thru Khyber Pass or flown into
Kabul Parameters Speed Cost plus converted
to lump sum Security changes to save funds
32
Kabul Embassy Project
  • Chancery

33
Kabul Embassy Project
Ribbon Cutting March 2006
34
Technical Support Facility
  • 24 MM Task Order On DOCCC (Cost Plus Award Fee
    GMP)
  • Control Center For NRO At CCAFS
  • Awarded 1 Year Behind But Finished On Time

35
TSF Parameters
  • Specialty Contracting During Design
  • 8 Large Audio Visual Panes (Touch Screen
    Computer)
  • Projection Equipment
  • Main Commo Relocated
  • Lighting
  • Demolition In Advance Of Construction
  • Less Than 5 Change Orders

36
Operational Expeditionary Logistics Facility
  • 42.3 MM / 2009
  • New storage, training, gate for SEABEES
  • Execution speed to use Katrina funds

37
Operational Expeditionary Logistics Facility
Parameters
  • Flexible scope to get as much as possible from
    the programmed amount
  • DPW building
  • Training facility inside the warehouse
  • But bridging documents too detailed

38
US Southern Command HQ
  • 640,000 SF
  • 230 MM
  • Awarded 4/2008

39
SOUTHCOM HQ PARAMETERS
  • Tried to execute new lease consolidating 10 Miami
    locations
  • Problems with developers scopes so late in the
    2008 program
  • Improved Scope
  • four stories
  • adjusted parking
  • wind tunnel adjustments
  • campus
  • px/commissary space

40
IHNC Hurricane Protection Project
USACE New Orleans HPO
41
IHNC Hurricane Protection Project
USACE New Orleans HPO
  • Acquisition Parameters
  • Technical and Management Plan
  • 5 scope for performance for
  • -interim protection at 1 year with or without
    overtopping
  • -100 year storm by 2011
  • Cost at 80 confidence
  • RESULT- 1 BB CW PROJECT FROM SCRATCH IN 5 YRS

42
REVIEW USAF STRATEGIES(Did it happen?)
  • Design Construction Practices
  • PM continuity, project packages, A/E integration
    with construction, performance specifications,
    incentives
  • Project Delivery Strategy clear definition from
    conception to delivery use spectrum of tailored
    contractual instruments
  • Design-Build Procedures single award acquires
    A/E and construction services, selection based on
    quality of intended design, cost, technical
    capability, construction management plan,
    guaranteed maximum price
  • Small business rules dont set aside projects
    over 2 MM
  • Expand Title II Services
  • Prequalification

43
  • Questions?
  • Comments?
  • Criticisms?
  • Witticisms?