Title: Evolution of Design Build Projects for the Federal Government
1Evolution of Design Build Projectsfor the
Federal Government
Lou Martinez Martinez Engineering Management
Services, Inc
- Purpose - History of Design-Build Contracting
- Organization -
- Eight Example Projects Enhanced by Design
Build - Project and Contract Parameters
- Advantages Over Conventional Methods
- Test
2Lous Background
- 6 years Army helicopter pilot
- 20 years USACE
- Saudi Arabia
- Baltimore
- Nuremberg DPW
- Mobile
- 15 years Brown Root/KBR
- Mobile PM
- Washington DC SVP Design Construction
- 4 years MEMSI
3(No Transcript)
4Redstone Arsenal John J. Sparkman Center(first
USACE design build)
Acquisition plan 1991 Contractor selected late
1992
Centex Rooney Smallwood, Reynolds, Stewart
Stewart
Completed August 1994 six months ahead of schedule
5Parameters
DESIGN BUILD IN ORDER TO MAKE TIMELY AWARD IN
PROGRAM YEAR
Lessons Learned Takes more effort to
advertise, evaluate and award Must Narrow
Bidder Field Minimize Review After
Proposal Minimize Submittal Requirements Allow
Construction Time Set by Contractor
61986 USAF REPORTon Design Construction
Delivery Strategies
- Purpose - Improve Acquisition Process
With More Timely and Cost-Effective Delivery
Methods - Recommended Commercial Business Processes
- Obtained Congressional Approval for D/B
7(No Transcript)
8Recommendations for Better Programming and
Construction Processes
Interviewed commercial firms
9Sun Oil Middle Creek Abatement(Brown Root, Inc
example of Industrial use of business processes)
- Awarded January 1992
- 150 Million
- 50k normal flow vs. 250k/25 year design storm
- 40,000 cu yards contaminated soil
- 100 year old refinery Marcus Hook PA
- Two states DE and PA
- EPA negotiated completion by 1994
- Multiple geographic agencies
10SUN OILMIDDLE CREEK ABATEMENT
- Parameters
- Fixed/unit price
- Contractor designed sludge pile
- Contractor managed temp pumping system
- Design build in order to meet EPA schedule, and
accomplish the above.
11DoS Security Upgrades Program
7 August 1998 Nairobi, Kenya Dar Es Salaam,
Tanzania 224 (12 Americans) killed gt 4,000
injured
12DoS Security Upgrades Program(awarded to KBR in
1999)
before
after
13DoS Security Upgrades Program
- Stand off
- Barriers
- Perimeter walls/fences
- Access control (CAC)
- WTMD
- Explosive detection systems
- X-ray
- Local/over-ride control
- Bullet Proof doors windows
- Cameras
- Detection systems
- Deterrent systems
Examples of Stand Off
14Locations Around The Globe
DoS Security Upgrades Program
6
9
12
12
More than 50 locations around the world
15Compound Access Control
DoS Security Upgrades Program
16Project Execution
DoS Security Upgrades Program
- A. COST REIMBURSED PGM MANAGEMENT
- Phase I - Scope and engineering surveys
- Phase II Design and Estimate
- Civil / architectural
- technical security
- B. Lump Sum Fixed Price Task Orders
- Phase III Civil / architectural construction
- Phase IV - Technical security
17DoS Security Upgrades Program
Barrier examples
- PARAMETERS
- Execution Speed
- Multiple designers
- Construction resources tailored to site
- Pre-purchased and stored materials
- Scope flexibility
- Funds control
18Guantanamo Detainee Facilities
Photo courtesy globalsecurity.org
19OBJECTIVE Replace this in 60 days
(hundreds more coming)
Awarded under CONCAP in February 2002
20 REPLACE CAMP X-RAY
Parameters CONCAP terms cost plus award
fee Extremely Short Schedule MULTICULTURAL
WORKFORCE (800) Pilipino, Indian, Jamaican,
British 24/7 Operations Construction on GTMO With
Barged Materials Replaced Contractor and
Workforce Design on the fly
Photo courtesy globalsecurity.org
21Hundreds of Shipping Containers
Used everything but the oink
Photo courtesy globalsecurity.org
Photo courtesy globalsecurity.org
22Container Modification
23Beginning Construction
CAMP 1-404 CELLS, EXPEDITIONARY MAXIMUM
SECURITY ISSUED FEB 2002 16 MM
Photo courtesy globalsecurity.org
24Hanging Utilities
CAMPS 2 3- 404 MORE CELLS ISSUED APRIL AND
JULY 22 MM LESS THAN 90 DAYS EACH
Photo courtesy globalsecurity.org
25Assembled in Groups of Six and Insulated
Photo courtesy globalsecurity.org
26Completed 36 Person Block
Photo courtesy globalsecurity.org
27Hospital Operating Room
28Two Final Facilities
STATE OF THE ART 20 MM EACH 10 MONTHS DESIGN
BUILD Design/build team Hensel Phelps/Shenkel
Shultz
Photo courtesy globalsecurity.org
29Final Facilities
Photo courtesy globalsecurity.org
30Kabul Embassy Project
31Kabul Embassy Project
150 MM awarded 3/2003 as cost reimbursable
Chancery plus housing All materials shipped
thru Khyber Pass or flown into
Kabul Parameters Speed Cost plus converted
to lump sum Security changes to save funds
32Kabul Embassy Project
33Kabul Embassy Project
Ribbon Cutting March 2006
34Technical Support Facility
- 24 MM Task Order On DOCCC (Cost Plus Award Fee
GMP) - Control Center For NRO At CCAFS
- Awarded 1 Year Behind But Finished On Time
35TSF Parameters
- Specialty Contracting During Design
- 8 Large Audio Visual Panes (Touch Screen
Computer) - Projection Equipment
- Main Commo Relocated
- Lighting
- Demolition In Advance Of Construction
- Less Than 5 Change Orders
36Operational Expeditionary Logistics Facility
- 42.3 MM / 2009
- New storage, training, gate for SEABEES
- Execution speed to use Katrina funds
37Operational Expeditionary Logistics Facility
Parameters
- Flexible scope to get as much as possible from
the programmed amount - DPW building
- Training facility inside the warehouse
- But bridging documents too detailed
38US Southern Command HQ
-
- 640,000 SF
- 230 MM
- Awarded 4/2008
39SOUTHCOM HQ PARAMETERS
- Tried to execute new lease consolidating 10 Miami
locations - Problems with developers scopes so late in the
2008 program - Improved Scope
- four stories
- adjusted parking
- wind tunnel adjustments
- campus
- px/commissary space
40IHNC Hurricane Protection Project
USACE New Orleans HPO
41IHNC Hurricane Protection Project
USACE New Orleans HPO
- Acquisition Parameters
- Technical and Management Plan
- 5 scope for performance for
- -interim protection at 1 year with or without
overtopping - -100 year storm by 2011
- Cost at 80 confidence
- RESULT- 1 BB CW PROJECT FROM SCRATCH IN 5 YRS
42REVIEW USAF STRATEGIES(Did it happen?)
- Design Construction Practices
- PM continuity, project packages, A/E integration
with construction, performance specifications,
incentives - Project Delivery Strategy clear definition from
conception to delivery use spectrum of tailored
contractual instruments - Design-Build Procedures single award acquires
A/E and construction services, selection based on
quality of intended design, cost, technical
capability, construction management plan,
guaranteed maximum price - Small business rules dont set aside projects
over 2 MM - Expand Title II Services
- Prequalification
-
43- Questions?
- Comments?
- Criticisms?
- Witticisms?