Title: SubContracting SME a challenge a uncontrollable risk a benefit How to handle
1SubContracting (SME)a challenge a
uncontrollable risk a benefit? How to handle
2Many have repeatedly and consistently commented
that the subcontracting obligation is a real
major concern and problem
3Basics
4What is not a subcontract
5Materials (delivery)
- Material purchase (supply) as such is not a
subcontract and follows different regulations
6- Workers as such
- are
- dependent on the instructions, are not free to do
how they like, hold no responsibility for the
product and are therefore not (sub)-contractors - Are not liable for the product/item
- Have a different legal status in terms of
obligations and rights (laborer laws)
7- Equipment
- are assets and follow other rules and laws such
as the financial laws
8- Conclusion
- it needs a combination of several elements to
create a subcontract - One element is always managing and decision
making (creating responsibility) for the item is
with the subcontractor
9- Subcontract
- in terms of construction means that parts /
elements of the project (product) are delivered
by other contractors (such as SMEs) employed by
the GC. - A subcontractor is responsible to produce/deliver
a (partial) product in terms of a measurable item
in technical and legal terms according a
ccontract (by defined time, quality, costs etc)
10Subcontracts
- Are identified and seen as serious risks and
none beneficial to achieve the project and the
objectives of a GC
11Subcontracts
- are
- unsuitable to deliver on time and delay and
complicate the project process (loss of ability
to instruct and take direct actions) - risky in terms of budget
- impossible to be handled in legal terms
- a threat to the GC
- politically beneficially but eliminate/restrict
profit for the GC
12Subcontractors
- Have
- no money, no material and no equipments
- Are short term companies
- and cannot be made responsible in future for
defects and cannot guarantee - Are on low professional grounds
- in technical administrative and managerial terms
13- GTZ (We) disagree to such statements
- and challenge them
- We will therefore address directly ANY
questions, problems and fears - We like to find solutions jointly and provide
answers needed
14GTZ will try to pave the way for successful
subcontractingby providing solutions tailored
to problems, addressing your concerns
15Lack of subcontractors available
16Data we needto understand and to find solutions
to fulfill the 40 rate of the contract
17Basic Cost distribution of a building by
workmanship, material, equipment and overhead etc
- Labour
- Material
- Equipment
- Site overhead
- General overhead
- Risk
- Profit
18Common used Subcontracts
- Piece workers
- Some trades
19Subcontracting by trades
20Sample Cost distribution Library by Trades
21Subcontracting by trades
- We can subcontract trades per building
- We can subcontract the complete trade for all
buildings - We can subcontract with equipment
- We can subcontract with materials
- We can subcontract with some materials
22Subcontracting by Components
For example Buildings, Blocks, floors etc....
23Subcontracting by Items
Specified items according BOQ None specified
items in the BOQ
24Subcontracting by Tasks
25Subcontracting by Tasks
Overhead Site-HQ
Direct Productive
indirect Productive
Management Tasks (sample update time
schedules) Financial Tasks (sample site
balancing) Testing, Reporting, Quality
Assurance Maintenance Temp. buildings/facilities G
uarding, transport of staff
Production of HCB Concrete production Aggregate
production (crushing) Formwork including.
erecting
Cleaning Waste removal Transporting/storing
26The subcontracts that are counted within the 40
are for
27Risks
28Typical Risks using subcontracts
- Sub is not registered correct
- Sub does not pay the taxes
- Sub did not pay materials he used in the project
- Sub did not pay his workers
- Sub did not comply with instructions
- Sub needs a VO
- Sub requests a time extension
- Subs quality is poor
- Sub items have defects
- Sub disappears
- Sub does not deliver all items
29 You have to plan how to handle this risk
- As you are aware the GC faces contractual
consequences in case a subcontractor is not paid
immediately - (as agreed in the subcontract)
30Insurance and subs?
- What is needed ?
- Should the GC insure subs and deduct the premium?
31- 2.1.4 Project planning principals apply for
subcontracting - Set up project plan (chart of organisation and
sub trades) - Set up (sub) risk assessment
- Decision on (sub) risk prevention and procedure
against (un) foreseen incidents
32Risk response Planning as part of good project
planning
33A definition of Risk(after Gill Ferrell)
- A future event (or series of events) with a
probability of occurrence and the potential for - a) loss or
- b) impact on objectives that can be either
positive or negative.
34Risk logging Cause and Effect
- Condition
- Cause
- Consequence
- Context
35Risk response Options
- Risk Avoidance
- Risk Transference
- Risk Mitigation/reduction
- Risk Deferral
- Risk Acceptance
36Risk Analysis
37Three-Point Estimates
- MO Most Optimistic (best case)
- ML Most Likely (average case)
- MP Most Pessimistic (worst case)
38Quantifying Risk
39Risk management
- Construction projects face various risks which
threaten the successful performance of the
contractor according to customer needs and
specifications. -
-
- Project planning must address these risks during
project development.
40Risk managementCommon risk types in building
construction
- Financial
- Time
- Design
- Quality
- Legal regulations
- Weather conditions
- Geo hazards
- Material supply
- Ground conditions
- Labour situation
41Principle Approach in risk management (I) The
risk management process
42Principle approach in Risk management (IV)
43Principle Approach in risk management (II)
Selected Risk types
44Principle approach in risk management (III)
Selected Risk types
45One way of Risk Management
469 Questions in need of answers
47The required list of subcontractors according the
GC contract
- Draft the form of the list the GC has to provide
after 15 days according the special contract
conditions
48Can you change the list/items of subcontractors?
49Price adjustment for subcontracts?
50How can I find a sub and know if he is suitable?
51Deductions from subs?
- Direct costs like Electricity, water, materials,
etc. - Damages caused by subs
- Liquidated damages
- Performance guarantee
- Warranties
52When is the right time to subcontract ?
53Is there a difference between Subcontractor and
SME
54Why is the calculation of tenders with
subcontracts different than without subs?
55Problems handling subcontractors
56Problems handling subcontractors
Like any client handles such problems a GC being
the client of a subcontractor the key is a
suitable subcontract.
57The Contract with a Sub
58Sample Sub-Contract Format
59How to achieve the 3 main results
- 1. Supporting General Contractors local
enterprises - In selection process!
- In negotiation process!
- In improving partnership!
6010 Good Reasons for Sub-contracting
- Concentration/specialization on own core
competencies! - Better supervision of construction process!
- Better time management of big projects
compliance with deadlines! - Building reliable partnerships in the regions!
- Increased possibilities on local markets!
- Distribution of risks!
- Less own employees (less problems)!
- Better control of price increase!
- Greater efficiency in the use of plant
machinery! - Improved reference for future big projects!
61Some more Good Reasons for Sub-contracting for a
GC
- More Resources
- Local contacts and knowledge
- Lower overhead costs
- More knowledge
- Distribution of responsibilities
62The Reason That Counts
- safe and real profit out of the project
- and on the longer run
63FAQs
Frequently Asked Questions (about
subcontracting) Problems associated with delay
of payment for SMEs which is big headache and
main reason for delay at most sites and SMEs are
also facing problem with getting reasonable
prices when they are entering an agreement for
labour cost with the main contractors But it is
experience from previous projects, that SMEs get
directly contracted by the client directly paid
by the client, hereby avoiding delays and
disputes among the GC and SMEs and also thelabour
price including their overheads and profit is
calculated by the client according to the market
situation of the individual places in advance so
that there is no problem between SMEs
contractor on site during offering of labour
price. Why is not the same adopted/implemented
for gtz??