SubContracting SME a challenge a uncontrollable risk a benefit How to handle - PowerPoint PPT Presentation

1 / 63
About This Presentation
Title:

SubContracting SME a challenge a uncontrollable risk a benefit How to handle

Description:

We will therefore address directly ANY questions, problems and fears ... (after Gill Ferrell) ... Significant elements of scope for functionality will be unavailable ... – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 64
Provided by: off67
Category:

less

Transcript and Presenter's Notes

Title: SubContracting SME a challenge a uncontrollable risk a benefit How to handle


1
SubContracting (SME)a challenge a
uncontrollable risk a benefit? How to handle
2
Many have repeatedly and consistently commented
that the subcontracting obligation is a real
major concern and problem
3
Basics
4
What is not a subcontract
5
Materials (delivery)
  • Material purchase (supply) as such is not a
    subcontract and follows different regulations

6
  • Workers as such
  • are
  • dependent on the instructions, are not free to do
    how they like, hold no responsibility for the
    product and are therefore not (sub)-contractors
  • Are not liable for the product/item
  • Have a different legal status in terms of
    obligations and rights (laborer laws)

7
  • Equipment
  • are assets and follow other rules and laws such
    as the financial laws

8
  • Conclusion
  • it needs a combination of several elements to
    create a subcontract
  • One element is always managing and decision
    making (creating responsibility) for the item is
    with the subcontractor

9
  • Subcontract
  • in terms of construction means that parts /
    elements of the project (product) are delivered
    by other contractors (such as SMEs) employed by
    the GC.
  • A subcontractor is responsible to produce/deliver
    a (partial) product in terms of a measurable item
    in technical and legal terms according a
    ccontract (by defined time, quality, costs etc)

10
Subcontracts
  • Are identified and seen as serious risks and
    none beneficial to achieve the project and the
    objectives of a GC

11
Subcontracts
  • are
  • unsuitable to deliver on time and delay and
    complicate the project process (loss of ability
    to instruct and take direct actions)
  • risky in terms of budget
  • impossible to be handled in legal terms
  • a threat to the GC
  • politically beneficially but eliminate/restrict
    profit for the GC

12
Subcontractors
  • Have
  • no money, no material and no equipments
  • Are short term companies
  • and cannot be made responsible in future for
    defects and cannot guarantee
  • Are on low professional grounds
  • in technical administrative and managerial terms

13
  • GTZ (We) disagree to such statements
  • and challenge them
  • We will therefore address directly ANY
    questions, problems and fears
  • We like to find solutions jointly and provide
    answers needed

14
GTZ will try to pave the way for successful
subcontractingby providing solutions tailored
to problems, addressing your concerns
15
Lack of subcontractors available
16
Data we needto understand and to find solutions
to fulfill the 40 rate of the contract
17
Basic Cost distribution of a building by
workmanship, material, equipment and overhead etc
  • Labour
  • Material
  • Equipment
  • Site overhead
  • General overhead
  • Risk
  • Profit

18
Common used Subcontracts
  • Piece workers
  • Some trades

19
Subcontracting by trades
20
Sample Cost distribution Library by Trades
21
Subcontracting by trades
  • We can subcontract trades per building
  • We can subcontract the complete trade for all
    buildings
  • We can subcontract with equipment
  • We can subcontract with materials
  • We can subcontract with some materials

22
Subcontracting by Components
For example Buildings, Blocks, floors etc....
23
Subcontracting by Items
Specified items according BOQ None specified
items in the BOQ
24
Subcontracting by Tasks
25
Subcontracting by Tasks
Overhead Site-HQ
Direct Productive
indirect Productive
Management Tasks (sample update time
schedules) Financial Tasks (sample site
balancing) Testing, Reporting, Quality
Assurance Maintenance Temp. buildings/facilities G
uarding, transport of staff
Production of HCB Concrete production Aggregate
production (crushing) Formwork including.
erecting
Cleaning Waste removal Transporting/storing

26
The subcontracts that are counted within the 40
are for
  • local and regional SMEs

27
Risks
28
Typical Risks using subcontracts
  • Sub is not registered correct
  • Sub does not pay the taxes
  • Sub did not pay materials he used in the project
  • Sub did not pay his workers
  • Sub did not comply with instructions
  • Sub needs a VO
  • Sub requests a time extension
  • Subs quality is poor
  • Sub items have defects
  • Sub disappears
  • Sub does not deliver all items

29

You have to plan how to handle this risk
  • As you are aware the GC faces contractual
    consequences in case a subcontractor is not paid
    immediately
  • (as agreed in the subcontract)

30
Insurance and subs?
  • What is needed ?
  • Should the GC insure subs and deduct the premium?

31
  • 2.1.4 Project planning principals apply for
    subcontracting
  • Set up project plan (chart of organisation and
    sub trades)
  • Set up (sub) risk assessment
  • Decision on (sub) risk prevention and procedure
    against (un) foreseen incidents

32
Risk response Planning as part of good project
planning
33
A definition of Risk(after Gill Ferrell)
  • A future event (or series of events) with a
    probability of occurrence and the potential for
  • a) loss or
  • b) impact on objectives that can be either
    positive or negative.

34
Risk logging Cause and Effect
  • Condition
  • Cause
  • Consequence
  • Context

35
Risk response Options
  • Risk Avoidance
  • Risk Transference
  • Risk Mitigation/reduction
  • Risk Deferral
  • Risk Acceptance

36
Risk Analysis
37
Three-Point Estimates
  • MO Most Optimistic (best case)
  • ML Most Likely (average case)
  • MP Most Pessimistic (worst case)

38
Quantifying Risk
39
Risk management
  • Construction projects face various risks which
    threaten the successful performance of the
    contractor according to customer needs and
    specifications.
  • Project planning must address these risks during
    project development.

40
Risk managementCommon risk types in building
construction
  • Financial
  • Time
  • Design
  • Quality
  • Legal regulations
  • Weather conditions
  • Geo hazards
  • Material supply
  • Ground conditions
  • Labour situation

41
Principle Approach in risk management (I) The
risk management process
42
Principle approach in Risk management (IV)
43
Principle Approach in risk management (II)
Selected Risk types
44
Principle approach in risk management (III)
Selected Risk types
45
One way of Risk Management
46
9 Questions in need of answers
47
The required list of subcontractors according the
GC contract
  • Draft the form of the list the GC has to provide
    after 15 days according the special contract
    conditions

48
Can you change the list/items of subcontractors?
49
Price adjustment for subcontracts?
50
How can I find a sub and know if he is suitable?
51
Deductions from subs?
  • Direct costs like Electricity, water, materials,
    etc.
  • Damages caused by subs
  • Liquidated damages
  • Performance guarantee
  • Warranties

52
When is the right time to subcontract ?
53
Is there a difference between Subcontractor and
SME
54
Why is the calculation of tenders with
subcontracts different than without subs?
55
Problems handling subcontractors
56
Problems handling subcontractors
Like any client handles such problems a GC being
the client of a subcontractor the key is a
suitable subcontract.
57
The Contract with a Sub
58
Sample Sub-Contract Format
59
How to achieve the 3 main results
  • 1. Supporting General Contractors local
    enterprises
  • In selection process!
  • In negotiation process!
  • In improving partnership!

60
10 Good Reasons for Sub-contracting
  • Concentration/specialization on own core
    competencies!
  • Better supervision of construction process!
  • Better time management of big projects
    compliance with deadlines!
  • Building reliable partnerships in the regions!
  • Increased possibilities on local markets!
  • Distribution of risks!
  • Less own employees (less problems)!
  • Better control of price increase!
  • Greater efficiency in the use of plant
    machinery!
  • Improved reference for future big projects!

61
Some more Good Reasons for Sub-contracting for a
GC
  • More Resources
  • Local contacts and knowledge
  • Lower overhead costs
  • More knowledge
  • Distribution of responsibilities

62
The Reason That Counts
  • safe and real profit out of the project
  • and on the longer run

63
FAQs
Frequently Asked Questions (about
subcontracting) Problems associated with delay
of payment for SMEs which is big headache and
main reason for delay at most sites and SMEs are
also facing problem with getting reasonable
prices when they are entering an agreement for
labour cost with the main contractors But it is
experience from previous projects, that SMEs get
directly contracted by the client directly paid
by the client, hereby avoiding delays and
disputes among the GC and SMEs and also thelabour
price including their overheads and profit is
calculated by the client according to the market
situation of the individual places in advance so
that there is no problem between SMEs
contractor on site during offering of labour
price. Why is not the same adopted/implemented
for gtz??
Write a Comment
User Comments (0)
About PowerShow.com