Chapter 6 Tracking Progress on Tasks - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Chapter 6 Tracking Progress on Tasks

Description:

Select the task to be updated in any task sheet view (Gantt chart etc. ... Display a task sheet view such as the Gantt Chart. Click View - Table - Work ... – PowerPoint PPT presentation

Number of Views:74
Avg rating:3.0/5.0
Slides: 17
Provided by: conest
Category:

less

Transcript and Presenter's Notes

Title: Chapter 6 Tracking Progress on Tasks


1
Chapter 6Tracking Progress on Tasks
  • What will we do in this chapter?
  • Start Execution phase of project.
  • Explore baselines, baseline a project.
  • Track progress on tasks
  • As Scheduled
  • Percentage of Completion
  • Actuals
  • Explore Variance.

2
Execution phase
  • Consists of 4 major activities
  • Tracking
  • Analyzing
  • Controlling
  • Reporting

3
Execution Phase Tracking
  • Track progress on tasks so you know when tasks
    are actually completed by their assigned
    resources.

4
Execution Phase Analyzing
  • Examine any differences between your original
    plan and how its actually progressing. Monitor
    the differences in schedule or cost to anticipate
    any potential problems.

5
Execution Phase Controlling
  • Take any necessary corrective actions to keep the
    project on track toward completion on time and
    within budget.

6
Execution Phase Reporting
  • Keep stakeholders informed. Whether youre
    providing the big picture to your project team or
    high-level progress information to executives,
    you should regularly report various aspects of
    project information.

7
Baselines general
  • A baseline is a snapshot of key scheduling and
    cost information in your project plan at a
    specific point in time, fields saved are
  • Start
  • Finish
  • Duration
  • Work
  • Cost

8
Baselines - general
  • The original project plan, adjusted to
    perfection, is the ideal balance between scope,
    schedule and cost. This plan is usually agreed
    on by stakeholders before project begins
    execution.
  • The best time to save your original baseline is
    when the plan has been developed as fully as
    possible, but before you have started tracking.

9
Baselines How to
  • To save a baseline
  • Tools -gt Tracking -gt Set Baseline
  • To delete a baseline
  • Tools -gt Tracking -gt Clear Baseline

10
Baselines - Multiple
  • It is possible to save multiple baselines. You
    may want to do this if
  • Your project is exceptionally long.
  • The execution of your project has started and a
    major change occurs, ie. Funding changes,
    corporate shift in priorities etc.

11
Baselines - Viewing
  • To view your baselines with views
  • Tracking Gantt
  • Multiple Baselines Gantt
  • Or
  • You can insert baseline values into charts using
    Insert -gt Column

12
TrackingTracking Tool Bar
13
Tracking Track Project as Scheduled
  • Use this if actual work is proceeding exactly as
    planned.
  • Tools -gt Tracking -gt Update Project
  • Select Update Work as Complete Through option
  • Enter Complete Through Date

14
Tracking Completion Percentage, Actual
Start/Finish, Actual Duration
  • Enter percent complete or actuals, MS Project
    calculates remaining values and updates schedule
    if required.
  • Select the task to be updated in any task sheet
    view (Gantt chart etc.)
  • Tools -gt Tracking -gt Update Tasks
  • Enter the percentage complete or actuals for
    the task.

15
Tracking Actual Values - Work
  • Remember resources must be assigned to tasks to
    have work values.
  • Display a task sheet view such as the Gantt
    Chart.
  • Click View -gt Table -gt Work
  • In the Actual (Work) field of task that you
    want to update, enter actual work value.

16
Variance
  • The difference between baseline and current
    scheduled information is called a variance.
  • Variance can bee seen in various charts (View -gt
    Table -gt Variance), in the project statistics, or
    it can be inserted as a column in charts.
Write a Comment
User Comments (0)
About PowerShow.com