Very Rough MI-8 Startup Plan no big problem
scenario
  • Monday 10/20-Friday 10/24 Circulate Beam in
    Booster.
  • Friday 10/24
  • lt1600 last inspection of bakes, secure MI-12A
    and MI-12B
  • 1600-1800 secure M.I. Tunnel
  • 1800-2400 interlock tests
  • Saturday 10/25
  • 0001-0600 Begin extraction testing and
    commissioning of EDWA magnets (Lackey, Prebys)
  • 0600-0900 Inspect bakes in M.I. Tunnel
  • 0900-1800 Deliver beam to MiniBooNE, measure
    optics in MiniBooNE line (Kobilarcik 1)
  • 1800-2100 Inspect bakes
  • 2100-2400 Ming-Jens MI-8 measurements
  • Sunday 10/26
  • 0001-0100 Ming-Jens MI-8 measurements (contd).
  • 0100-0600 contingency
  • 0600-0900 Inspect bakes in M.I. Tunnel
  • 0900-? More beamline tuning if necessary
  • ? Ming-Jen loads new settings.
  • 2400 Beam off.