Title: High Energy Physics in Japan from KEK point of view
1High Energy Physics in Japanfrom KEK point of
view
- On-going projects at KEK
- KEK five years road map
- J-PARC
- KEKB upgrade
- ILC Accelerator R/D
- Conclusion
- June 4, 2009_at_Fermilab Users Meeting
- Koichiro Nishikawa
- Institute for Particle and Nuclear Studies, KEK
2KEK Current Core Activities
Photon Factory
3Other Projects
SOI Pixel
4JAHEP Roadmap Report on Prospects for Particle
Physics (October, 2006)
- Communitys master plan
- Highest priority is given to ILC.
- Before the ILC experiment commences, flavor
physics at KEKB and J-PARC, and energy frontier
physics at LHC are promoted. - The above two goals should be pursued in a single
master plan.
- Action plans before the ILC approval
- ILC RD
- Completion/commissioning of J-PARC
- Considering the world competition, it is urgent
to improve neutrino intensity - Continuation of KEKB/Belle with upgrade
5Summary of KEK Roadmap
2007
2008
2009
2010
2011
2012
construction
1st results
operation
LHC
LHC upgrade
TDP1
ILC RD
TDP2
lots and lots of RDs
6Status of accelerator andparticle physics
experiments at J-PARC
7Commissioning Status
J-PARC Facility (KEK/JAEA)
Linac
South to North
JFY2007 Beams
JFY2008 Beams
JFY2009 Beams
Birds eye photo in January of 2008
8Primary proton beam line combined function SC
magnets
Slow beam extraction to Hadron Hall
fluorescence plate just in front of target
Graphite target
Target station
- Recent important milestones
- December 23, 2008
- 30 GeV beam acceleration and fast extraction
- to the beam abort dump
- MLF user run (20kW)
- January 27, 2009
- 30 GeV beam extraction to the Hadron Exp. Hall
(Slow ext.) - February 19, 2009
- Government inspection for radiation safety
(Hadron hall) - April 23, 2009
- 30 GeV beam extraction to the neutrino target
station (Fast ext.) - May 28,2009
- Government inspection for radiation safety
(Neutrino facility)
9- Beam commissioning has been accomplished on
schedule, - BUT with low intensity.
- Real challenge toward the power frontier machine
just started. - Many issues (unreliable components, design etc.)
to be solved - Beam must be provided to the users
- Power upgrade should be also accomplished
steadily.
- Three serious issues
- RFQ discharge problem identified problems in
- vacuum, material, and fabrication. Are there
more problems? - RF core long term stability problem Thermal
stress analysis/design - Stability of MR power supply and beam loss
- Clearly need major improvements for MW operation
- No problem for fast extraction with a level of
100kW operation - Need more stability for slow extraction
10Tadashi Koseki for ATAC09
Slow extraction tuning and beam loss
22.3022.35/0.5 sec
Its a Ripple extraction using SX system We
need ?further improvement of magnet power
supply ?installation of feedback system
100 msec
Steps
Two shots
11Milestone for J-PARC accelerator operation
- Neutrino
- Early achievement of 100kW run (for 107 sec, in
2010) - Work on power upgrade scenario from 100 to
750kW.(2011 ) - The above second step should be the base of the
MW-class power - frontier machine.
- Hadron
- Early realization of spill control by
- improving magnet power supplies, and
- applying feedback system.
- Early achievement of 10kW-class power by
- understanding and suppressing and/or localizing
the beam loss. - In order to realize 100kW-class slow beam
extraction, we have to develop - excellent extraction efficiency,
- more beam loss control, and
- radiation maintenance technology.
12Tokai-to-Kamioka (T2K) long baseline neutrino
oscillation experiment
- Goal
- Discover ne app.
- nm disapp. precision meas.
- Intense narrow spectrum nm beam from J-PARC MR
- Off-axis w/ 22.5deg
- Tuned at osci. max.
- SK largest, high PID performance
1600nmCC/yr/22.5kt (2.5deg)
12
13Neutrino beamline
- 5 year construction 20042009
- Construction completed on schedule!
Electromagnetic horn
Graphite target
Neutrino monitor build.
Primary proton beam line completed
UA1 magnet donated from CERN installed in
Apr-Jun, 2008 on schedule
Beam dump completed
Target station completed
Decay volume completed
14T2K beamline started operation!
After 10 shots for tuning, proton beam hit
around target center
MR intensity
Muon monitor signal
Ionization chamber
Silicon
Proton beam profile monitor along nu beamline
Scintillator
Muon monitor profile
Horn Off
OTR detector just in front of target
(fluorescence plate)
Horn 250kA
14
15Neutrino Facility Commissioning Achievements
- Stability of the extraction beam orbit from Main
Ring is confirmed
Tuned
within 0.3mm(position), 0.04mrad(direction)
w.r.t. design orbit - Functionality of the superconducting combined
function magnet is confirmed. - Beam is lead to the target center without
significant beam loss
Tuned within 3mm level accuracy w.r.t. design
orbit - Functionality of the beam monitors (beam
position, beam profile, beam intensity, beam
loss) are confirmed - Response function of various magnets are measured
- Muon signal is observed which confirm neutrino
production - The effect of pion focusing with horn magnet is
confirmed (consistent with present horn
configuration) - The information transfer from Tokai to Kamioka
on the absolute beam time information is
confirmed - J-PARC neutrino facility is approved by the
government on radiation safety - Record so far
- Power 1.13 kW operation for 30
seconds (6sec/cycle, 7.11011 pp/bunch) - Duration 0.14 kW operation for 40
minutes (6sec/cycle, 1 bunch, 1.71011ppb)
- Combined function super-conducting magnet
- Tuned within 3mm level
- Stability within 0.3mm(position),
0.04mrad(direction) - Muon signal observed
- Horn is working as expected
- Near detectors are being installed
16the Origin of Matter Dominated Universe ?
ne Appearance
T2K (2009
Discovery of Lepton CP Violation Proton Decay
Neutrino beam Intensity Improvement
Construction of Huge Detector
Tech. choice
Huge Detector RD
Liquid Ar TPC
17Rare Kaon Decay
- NA62 at CERN-SPS for
18Detector and Beamline RDfor the KL?p0nn
ExperimentBeam line is being constructedBeam
survey in 2009
A Japan/US program
- J-PARC KOTO experiment (K0 at Tokai)
- To study physics beyond SM by measuring branching
ratio of KL?p0nn - Modify KEK-E391a detector
- Upgraded CsI calorimeter
- Readout waveform digitization
- New photon veto in the beam
19COMET (m e conversion) activities
- Beam Extinction Study
- Abort line measurement
- Secondary beam line measurement
- Extinction monitoring device development
- Gating PMT for a Gas Cerenkov detector, 1MHz
switching with 106 on/off ratio
- Super-conducting solenoid
- Pion capture solenoid
- Design of high Intensity muon beam line
- AC-dipole development
- B5T
- Radiation transparent
- Technology
- Detector Solenoid Tech.
- NbTiAl conductor
- Indirect pipe cooling
- Conductor development in 2009
- Test coil construction and test in 2-3 years
- Single bunch, single shot operation of MR
- Count the number of protons in the EMPTY bucket
before the filled one
- Measure secondary particle time structure
relative to a reference signal from the MR - MR operation with empty buckets
- Bunched slow extraction
- 1st version corona-tested
- 2nd version built
- Single brick test soon
20Activities at J-PARC
Other particle physics experiments in preparation
_at_J-PARC
21KEKB Upgrade
22KEKB Upgrade
1.96 x 1034
goal 1 (ab)-1
23Oide _at_ HEPAP
24(No Transcript)
25(1.96)
26(No Transcript)
27(No Transcript)
28Budgetary Process toward Super-KEKB
JFY2009
JFY2010
JFY2011
Original Scenario
Government Review Council
Full Budget Proposal
Construction
Supreme Scenario
Full Budget by Supplement
350 M
??? 30M
Better Scenario
Segmented Supplement Budget
29ILC RD
30ILC RD
First priority project in JAHEP
- RD Items
- Precise beam handling in ATF
- Superconducting RF in STF
31Accelerator Test Facility (KEK)
Diagnostic line for the extracted low emittance
beam
ATF2 Realization of the nanobeam (beam
commissioning October 2008)
32ATF2 Construction Schedule
ATF2 beam line
January,2009 Started operation. 35nm beam
ATF2 beam line
(IHEP, KEK, SLAC)
33Superconducting Accelerator Test Facility (KEK)
34STF Development Plan
Phase 1 (2005 -2008) for quick startup of
ILC SCRF, infra-structure development subdivided
to Phase 0.5 1 cavity in each short
cryostat (cool downOct.2007Feb.2008) Phase
1.0 4 cavities in each short cryostat (2008)
Phase 1.5 replacement of cavities by improved
gradient one (2008-2009) Phase 2 (2008 - 2010)
develop ILC Main Linac RF unit start
design Apr. 2008, fabrication in 2009 and 2010,
commissioning in 2011 Phase 3 (2009 - 2013)
Industrialization of ILC Main Linac
component develop industrialization technology
in 2009 and 2010, fabrication of one more RF
unit by the developed mass-production
technology GDE S0 task (2006 - 2009) in parallel
to phase 1, 2 develop ILC performance
cavity (35MV/m, 90 yield)
- Some of the recent progresses
- Inspection/repair method for inner surface of RF
cavity - Operation of 31.5 MV/m cavity
- Completion of cavity testing facility
- Studies on Cryostat (deformation, magnetic field
shielding effects) - .
Much Closer Interplay between KEK and Industries
35Keep Producing Physics ResultsTechnology
DevelopmentsHuman Resources