INSTALLATION OF UNDERGROUND WIRING SYSTEM IN A NEW DEVELOPING TOWN! - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

INSTALLATION OF UNDERGROUND WIRING SYSTEM IN A NEW DEVELOPING TOWN!

Description:

To perk up the customary of living. Corporate Agenda. PROJECT. MANAGEMENT. To cope with the problems that occur due to the typical electricity transmission ... – PowerPoint PPT presentation

Number of Views:159
Avg rating:3.0/5.0
Slides: 18
Provided by: Insat
Category:

less

Transcript and Presenter's Notes

Title: INSTALLATION OF UNDERGROUND WIRING SYSTEM IN A NEW DEVELOPING TOWN!


1

PROJECT MANAGEMENT
!
Project Name
  • INSTALLATION OF UNDERGROUND WIRING SYSTEM IN A
    NEW DEVELOPING TOWN!

2

PROJECT MANAGEMENT
Project Members
3

PROJECT MANAGEMENT
Corporate Agenda
  • To perk up the customary of living

4

PROJECT MANAGEMENT
Background
  • To cope with the problems that occur due to the
    typical electricity transmission lines
  • Maximum Possibility of cable impairments
  • Irregular supply of electricity
  • Maximum Possibility of injuries

5

PROJECT MANAGEMENT
Project Reimbursement
  • Project will be benefited to
  • Mitigate damages to power lines structure and
    system
  • Restore power quickly
  • People are much secured.
  • To elude transport difficulties in town

6

PROJECT MANAGEMENT
Project Objectives
  • Install best underground wiring system to provide
    24/7 electricity supply
  • Provide safe and secured environment to people
  • To make the town adductive

7

PROJECT MANAGEMENT
Project will Comprise
  • Electric Cables
  • Digging
  • Sand
  • Concrete Cover
  • Acquiring Labor
  • Technical Staff

8

PROJECT MANAGEMENT
Constraints
  • Bad weather may cause problems
  • Some resistance of sand during digging

9

PROJECT MANAGEMENT
Key Assumptions
  • Project wont be interrupted by telecom, gas and
    sewerage pipes
  • Electricity supply wont be interrupted by other
    sources
  • Smooth supply of electricity to consumers

10

PROJECT MANAGEMENT
Project Team Work
  • The project manager
  • Finance manager
  • Civil contractor
  • HR manager

11

PROJECT MANAGEMENT
Activities
12

PROJECT MANAGEMENT
Activities
  1. Selection of Material
  2. Selection of digging Channels
  3. Tender Floating
  4. Tender Accepting
  5. Procurement
  6. Digging
  7. Sand laying
  8. Cable Line
  9. Putting Concrete cover
  10. Check Post Selection
  11. Digging for check post
  12. Tiles laying

13

PROJECT MANAGEMENT
  • Activity Predecessor Time(Days)
  • A --- 3
  • B A 5
  • C B 4
  • D C
    4
  • E D 2
  • F D 7
  • G F,E 3
  • H G 5
  • I H 4
  • J H 2
  • K J 5
  • L K,I 6

14

PROJECT MANAGEMENT
Network Diagram
  • E2 Dummy Activity
  • A3 B5 C4 D4 G3 H5
    I4 L6
  • F7
  • J2 K5

6
1
2
3
4
5
7
8
9
11
12
10
15
PROJECT MANAGEMENT
Critical Path
Critical Path
  • Contains only one critical path
  • A-B-C-D-F-G-H-J-K-L 44 days
  • Dates to remember
  • Starting Ist Feb,2008
  • Ending 22nd march,2008
  • Time Duration 44 days(Excluding 7 holidays)

16

PROJECT MANAGEMENT
Budget
  • Material Procurement Rs 20,000
  • Marketing Cost 5,000
  • Training Cost 4,000
  • Contractor Payment 15,000
  • Transportation Cost 3,000
  • Labor Cost 20,000
  • Other Cost 10,000
  • Total Cost 77,000

17

PROJECT MANAGEMENT
  • ?
  • Any Query