United Arab Emirates university College of Engineering Graduation Project II Design of a Control Man - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

United Arab Emirates university College of Engineering Graduation Project II Design of a Control Man

Description:

The main objective of construction project management is to control: ... Paint-using bitumen. 4.8. 4.4. Curing Footing. 4.7. 4.5. Place the shuttering. 4.6. 4.4 ... – PowerPoint PPT presentation

Number of Views:117
Avg rating:3.0/5.0
Slides: 49
Provided by: bader
Category:

less

Transcript and Presenter's Notes

Title: United Arab Emirates university College of Engineering Graduation Project II Design of a Control Man


1
United Arab Emirates universityCollege of
EngineeringGraduation Project IIDesign of a
Control Management System for Construction
Project
GRADUATION PROJECT (II)
CEM2-1
  • Presented By
  • Musallem Mohd Al-Jenaibi 980910183
  • Abdulla Rashed Al-Maqbali 980715131
  • Khaled Thani Al-Ketbi 980710110
  • Abdulla Salem AL-Dhahrei 980711331
  • Advisors Dr. Suleiman Ashur

2
Introduction
  • The main objective of construction project
    management is to control Time (T), Quality (Q),
    and Money (M).
  • A project consists of three components scope,
    budget and schedule.

3
Introduction
  • Typical villa ( Our Project) controlled by
  • Earned value technique.
  • Primavera soft ware.
  • Simphony soft ware.

4
Introduction
  • Many problems like cost overruns, time extensions
    and conflicts among all parties.
  • Unique nature of construction projects, high
    risk, highly fragmented, high competition and
    increasing challenges.
  • The construction project management is needed
    to- Utilize resources, meet project requirements
    and deadlines, improve quality and safety , etc.

5
Problems during construction
  • Hundreds of workers must come to gather to
    complete their assignments.
  • Many activities consume more than their estimated
    time and cost.
  • If one crew works finishes its work early, the
    following crew are not obliged to start earlier
    than initially planned.

6
Problems during construction
  • Frequent changes are introduced to the scope of
    work, thus causing a lot of work disruption and
    cost overrun.
  • Some trades proceed slower than desired whereas
    others proceed faster than desired
  • Dealing with suppliers and subcontractors.

7
Objectives of project control
  • Accurately follow the project plan.
  • Work breakdown structure.
  • Prepare cost estimate for all activities and
    prepare a budget for the sponsor approval.
  • Evaluate project performance depend on cost, time
    and quality.
  • Implement a control system to identify schedule
    variances and take corrective action to achieve
    project schedule targets.

8
Quality Control
  • Quality in Civil Engineering is the single factor
    that determines a good construction from any
    other construction.

9
Quality Control of Excavation
  • Excavation depend on the soil investigation.
  • Site should be clear from all organic materials.
  • Reach the accurately lines and levels shown in
    the drawing.
  • Support the lateral edges to prevent failure.

10
Quality Control of Formwork
  • Its the casing into which concrete is places.
  • Forms should be designed and constructed that
    concrete can be properly placed and thoroughly
    compacted.

11
Tolerance of Formwork
12
Quantities Take Off and Cost EstimateI- The
Work Breakdown Structure (WBS)
13
II- Quantities Take Off and Activities Duration
and cost
14
III- Creating the Dependencies
15
Time and Cost Control
  • meets the client's requirements and achieves the
    best possible cost, schedule, and quality
    performance.
  • Effective cost and schedule management are the
    cornerstone activities of each project.
  • S-Curve and Earned value techniques are used to
    control cost and time in a typical villa project.

16
Cost Distribution
S-curve for Cumulative Cost Curve on An Early
Start and Late Start
17
The Earned Value Technique
  • Earned Value is an objective measurement of how
    much work has been accomplished on a project.
  • The Earned value technique lends itself very well
    to the analysis of the cost and schedule
    performance in a project.

18
Cost and Time control
  • The Earned value analysis was provided to
    evaluate the progress of the typical villa
    project.
  • The original budget was DHS 552925 and the
    project scheduled to be completed in 123 working
    days.
  • A status report after different times were
    calculated.

19
Earned Value Measures for typical villa project
20
Earned Value Measures for typical villa project
21
Cost and Schedule Deviations
22
Cost and Schedule Performance
23
Project Performance Indices
24
Forecasting for the typical villa project at end
of second month
  • Estimate at completion (EAC)
  • ACWP (BCWS at completion BCWP / CPI)
  • EAC 147725 (552925 156925 / 1.0623)
  • DHS 552928
  • The estimated cost of the project at completion
    is DH'S 552928, which is DH'S 3 over the original
    budget of DH'S 552925.

25
Primavera Project Planner
  • P3 is the recognized standard for
    high-performance project management software
  • Helps construction manager in control finishing
    the project on time within the allocated budget.
  • Finding out what really happened, how much was
    actually accomplished, what remains to be done,
    and who will be available to do it

26
The benefits of Primavera in Construction Project
Management
  • Improved scheduling and analysis to stay on
    target.
  • Easy project planning and implementation
  • Construction-specific reports, layouts and
    filters.
  • Helps you build a project network quickly and
    graphically
  • Simplifies tracking resources and costs

27
Control large and complex projects efficiently
  • P3 is designed to handle large-scale, highly
    sophisticated and multifaceted projects
  • To organize projects up to 100,000 activities.
  • P3 provides unlimited resources and an unlimited
    number of target plans.

28
Components of the P3 window
  • The P3 window contains several elements that
    enable you to access information quickly and
    easily using either a mouse or the keyboard.
  • Primavera can present the data in two forms
  • Bar Chart
  • PERT

29
Applying P3 to graduation project (typical villa)
  • The total number of activities was 86.
  • The project starting date was September 1, 2003
    and should finish on January 24, 2004 .

30
Bar Chart
  • The bar chart shows the corresponding schedule
    with activity bars positioned along a timescale.

31
PERT
  • You can use a PERT to construct your project
    plan, adding activities and relationships in a
    logical flow.

32
Simulation
  • Simphony represents an evolution in computer
    simulation and its integration in to construction
    industry.
  • It is the result of over five years of research.
  • you create simulation model using a library of
    modeling elements.

33
Simulation
  • The purpose of the Simulation.
  • Templates of Simulation
  • Template for Tunnel simulation.
  • Template for Analysis Earthmoving Operations.
  • Template for Project Scheduling.

34
  • Template for Project Scheduling.
  • PERT
  • Activity.
  • Relation.

35
  • Simulation modeling with Simphony
  • Project Scheduling Template.
  • Deterministic time.
  • The time were scheduled in hours.
  • Simphony has limitations.

36
Modelling of activities in Simphony (PERT)
37
Capture of simulation screen
38
CDF of simulated project time (10).
39
Histogram of simulated project time (10).
40
CDF of simulated project time (100).
41
Histogram of simulated project time (100)
42
CDF of simulated project time (1000)
43
Histogram of simulated project time (1000)
44
(No Transcript)
45
(No Transcript)
46
CONCLUSIONS RECOMMENDATIONS
  • designed an excel sheets.
  • Work as team.
  • The Construction Management Project Control is in
    its infancy in the UAE.
  • Publish manual about QC/QA.

47
ACKNOWLEDGMENT
  • DR.SULEIMAN ASHUR (ADVISOR)
  • DR. ESSAM ZAINELDEN
  • ENG.MAHMOUD
  • CIVIL ENGINEERING DEPARTMENT
  • ALAIN MUNICIPALITY MOUNCEL CONSULTANTS
  • PUBLIC WORK DEPARTMENT (PWD).

48
THANK YOU FOR YOUR ATTENTION
  • QUESTION AND ANSWER SESSION