NEC Compensation Events Programme - PowerPoint PPT Presentation

1 / 29
About This Presentation
Title:

NEC Compensation Events Programme

Description:

CE's - Programme and Delay Issues. Compensation, Delay (i.e. analysis) ... 'Compensation Events' dealt with on a contemporaneous basis 'managed not audited' ... – PowerPoint PPT presentation

Number of Views:287
Avg rating:3.0/5.0
Slides: 30
Provided by: richardb92
Category:

less

Transcript and Presenter's Notes

Title: NEC Compensation Events Programme


1
NEC - Compensation Events Programme Delay
Issues
  • Richard Bayfield BSc., MSc., CEng., FICE, FCIArb

2
Original Brief
  • CEs - Programme and Delay Issues
  • Compensation, Delay (i.e. analysis)
  • Analysis examination, investigation, scrutiny
  • Synthesis creation, making, fusion.
  • NEC predicated on synthesis
  • Traditional Contracts emphasis on analysis
  • Synthesis pro-active pre-empting
  • Analysis re-active history (delay)

3
Introductory Question
  • What is the purpose of a programme?
  • What is the purpose of a programme under the NEC?

4
History of Construction in 3 Slides
5
(No Transcript)
6
Industry Context and NEC
  • Complexity - technical
  • Complexity people / organisations intrinsic
    need for improved communications
  • Fragmentation of industry
  • Different interests
  • Disputes arises from poor communication
  • NEC addresses these issues at a strategic level

7
Back to Programme who is programme for?
  • Client?
  • Contractor?
  • Project Manager?
  • Designer?
  • Some one else the delay analyst?
  • THE PROJECT

8
Programme purpose?
  • Project Management Martin Barnes 2 rules
  • 1. "It is only possible to manage the future".
  • 2. "All decisions must be directed towards
    meeting the clients' objectives".
  • Programme - As a tool to help manage the project
    / the remaining activities (the future)
  • Programme - Encourage what if scenarios
  • Programme - Pre-empting if decision for x is
    delayed what is effect?

9
Programme Management.
  • Many industries including construction have
    success stories going back decades - Not a new
    invention
  • .the traditional standard forms are weak on
    programme techniques
  • Prof Capper SCL Paper Sept 1994
  • Contract is a tool for managing risk (Prof
    Capper)
  • No real difference whether programme is under NEC
    or not (strategically)
  • Proper Programme Management adds value and
    reduces risk whatever the contract form

10
Programme Management
  • There is no reason why these techniques (critical
    path programming) should not be applied in a
    consensual manner within the contract and on a
    real-time basis in order to generate a regularly
    updated analysis of employer and contractor delay
    periods.
  • - Professor John Uff QC Are we all in the wrong
    job? SCL Paper July 2001
  • SCL Delay Disruption Protocol 2002
    www.eotprotocol.com

11
NEC Programme Clauses 3 Time
  • Cl 30 Starting Completion
  • Cl 31 The Programme requirements (31.3)
  • CL32 Revising the Programme
  • Cl 33 Possession
  • Cl 34 Instructions to stop / start
  • Cl 35 Take over
  • Cl 36 Acceleration

12
NEC Programme Philosophy Accepted Programme
  • The programme is an important document for
    administering the Contract. It enables the PM and
    Contractor to monitor progress and to assess the
    time effects of compensation events including
    changes to the completion date. - from
    Guidelines to Cl 31
  • i.e it is a methodology for management of the
    overall project - Implications?
  • Accepted Programme base document for assessing
    time and cost of CEs

13
Assessing Compensation Event (CE)
  • Cl 63.3 A delay to the Completion Date is
    assessed as the length of time that, due to the
    compensation event, planned completion is later
    than Planned Completion as shown on the accepted
    programme.

14
NEC Programme update for Compensation Event (CE)
  • Objective is anticipate the effect of the CE on
    the programme before it happens
  • Completion date is then revised via the accepted
    programme
  • Associated costs dealt with in advance as a a
    quote, not as part of an audit

15
NEC Programme update for Compensation Event (CE)
  • Forecasting prospective - quotation
  • Allows Choice (but not always)
  • What if?
  • Subjectivity
  • Synergy
  • Fair
  • Acceptable

16
HONDA NEP PROJECT
17
Case Study Major Client
  • 2 Similar Projects on same site
  • Built 10 years apart
  • 40 Financial improvement on second project
  • Positive Global comparison
  • British Construction Industry Award 2002
  • NEC philosophy and methodology project

18
Case Study Major Client
  • Compensation Events dealt with on a
    contemporaneous basis managed not audited.
  • Final Accounts resolved within 3 months of PC
  • Same methods for construction and process
    contractors
  • Transparent programme updates every week.

19
BRITISH CONSTRUCTION INDUSTRY AWARDS 2002
  • Honda's new European plant at Swindon took the
    Building Award.
  • The "one team one goal" culture of openness and
    transparency at Honda's New European Plant, and
    the company's refusal to accept the status quo,
    has been rewarded with a building cost of only
    701/sq m - a 40 improvement on the cost of the
    original plant at Swindon completed nine years
    earlier.

20
Programme Management
  • Transparency / visibility
  • Emphasis on Communications
  • Emphasis on Pre-planning
  • Emphasis on detailed Programmes
  • Weekly updates for actual progress
  • Standard software (MS Project)
  • Compliance by all trade Contractors.

21
Programme meeting using whiteboard
22
(No Transcript)
23
Whiteboard Meetings
  • Consensual Visible
  • Identify potential conflict early
  • No where to hide
  • Instant record email
  • Saves Management time
  • Synthesis not Analysis
  • Meeting Minutes see example

24
(No Transcript)
25
Overview
  • Methodology works -
  • Addresses some of the industry failings
  • BUT
  • Synthesis is harder than analysis
  • Needs strong Client commitment (more than just
    words needs resources as well!)
  • Needs a competent TEAM with adequate specialist
    support

26
(No Transcript)
27
(No Transcript)
28
(No Transcript)
29
Finally
  • Project successes due to
  • Synthesis not Analysis
  • Notes at www.richardbayfield.com
Write a Comment
User Comments (0)
About PowerShow.com