SR 240 Slipform Paving Case Study - PowerPoint PPT Presentation

1 / 43
About This Presentation
Title:

SR 240 Slipform Paving Case Study

Description:

Dowel bars are inserted using vibration and the vibration continues when the ... in the dowel bar placement. Only outside lanes had dowel bars across entire ... – PowerPoint PPT presentation

Number of Views:359
Avg rating:5.0/5.0
Slides: 44
Provided by: mikeh75
Category:
Tags: case | dowel | paving | slipform | study

less

Transcript and Presenter's Notes

Title: SR 240 Slipform Paving Case Study


1
SR 240 Slipform Paving Case Study
Alisa Cotter, Mike Hansen, and Eric McGarrah
2
Where is SR 240?
3
SR 240 is a Major Tri-Cities Route
  • 60,000 ADT
  • 110,000 ADT in 2025
  • Original Alignment of 4 HMA Lanes (inadaquate)
  • Project will replace with 8 PCC Lanes with a
    depth of 11 inches.

4
Project to Date
  • Westbound lanes were closed and reconstructed
    first.
  • Westbound lanes closed and traffic diverted to
    eastbound lanes.
  • 2 temporary lanes were constructed to maintain
    capacity.
  • Westbound lanes opened to allow the construction
    of the eastbound lanes.

5
Batching
  • Temporary batch plant located within ½ mile of
    project.
  • Plant relocated from Spokane.

6
Batching
  • Aggregate was stored on site.
  • Loaded into bins that feed the plant the
    appropriate gradation for the mix.
  • A weighing system is used to ensure the correct
    gradation.

7
Batching
  • Once aggregate is proportioned it goes into the
    horizontal drum followed by
  • Water, cement, and admixtures.
  • The horizontal drum mixes the components.
  • The mix is then transferred to the tilt drum.

8
Batching
  • The tilt drum then transfers the mix to the end
    dump trucks.

9
The Mix
  • A standard WSDOT mix was used.
  • Maximum water/cement ratio of 0.44.
  • Minimum cement content of 564 lbs/yrd3.
  • Type 1 cement.
  • 4,416 psi average 28 day compressive strength.
  • 718 psi average 14 day flexural strength.

10
The Mix
  • Pave-Air, a proprietary air entraining agent, was
    added for improved workability.
  • Masterpave, a proprietary water reducing agent,
    was added to decrease water/cement ratio.

11
Plant Production
  • Materials are constantly delivered to the site.
  • Two drums allow a second batch to be produced
    while a truck is being loaded.

12
Plant Production
  • Ten end dump trucks were used.
  • 9 yd3 per truck
  • 1.5 minutes to load.
  • 3 minutes from arrival to departure.
  • 300 - 350 yrd3/hr
  • 33 - 39 trucks/hr

13
Noted Project Plant Issues
  • WSDOT inspector noticed that the mix was 20-40
    lbs low per batch.
  • Contractor was instructed to increase cement
    content or batches would be rejected.
  • Resulting in a temporary plant shut down.
  • We dont know what caused this . . . . ?
  • Mechanical issue
  • Cement Shortage at the plant.

14
Mix Delivery
  • Short delivery time allowed the use of end dump
    trucks (2-3 min).
  • Trucks had to avoid the paving wire.
  • Turn around point was provided.
  • Trucks had to back up 500 -1000ft.

15
Mix Delivery
  • Concrete trucks had priority on and off the
    project.

16
High Productivity of Delivery and Placement
  • Unusually high productivity was achieved with
    only ten trucks because of . . .
  • Proximity of the plant.
  • Thoughtful and efficient traffic control plan.
  • Width of the paving.
  • Use of a slip from paver.

17
Set Up for Slipform Paving
  • Surveyors must determine the elevation of the HMA
    at 50 intervals to set the guide wire.
  • Number 1 tripping hazard for 1rst year engineers,
    isnt that right Alisa.

18
Set Up for Slipform Paving
  • Bundles of dowel bars and containers of curing
    compound must be laid out.

19
Set Up for Slipform Paving
  • Water is sprayed ahead of the paving to cool the
    HMA base and keep water from being sucked out of
    the mix.

20
The Slipform Paver Needs Space
  • The new alignment of this project provide a lot
    of space.
  • Typical spatial needs include
  • 2-3 feet on either side for tracks.
  • Loading dowel bars.
  • Access for laborers.
  • Finishing

21
Start-up of Slipform Paving
  • The transverse construction joint must be
    constructed.
  • 40-50 full width spot grinding was done at the
    construction joints.

22
Start-up of Slipform Paving
  • A wetter mix is usually associated with the
    initial batches making it difficult to maintain
    the pavement edge.

23
Start-up of Slipform Paving
  • The paver has not developed the head that is
    required, possibly resulting in surface voids.

24
Concrete in the Slipform Paver
  • The concrete is moved from side to side with the
    bucket on the front of the paver.

25
Concrete in the Slipform Paver
  • The concrete is then vibrated by a series of
    vibrators.

26
Dowel Bar Insertion
27
Dowel Bar Insertion
28
Dowel Bar Insertion
29
Loading of Dowel Bars
30
Possible Issue of Dowel Bar Insertion
  • Dowel bars need to be placed appropriately.
  • Dowel bars are inserted using vibration and the
    vibration continues when the inserters are pulled
    back.
  • Does this alter the dowel bars alignment?
  • Are the paint marks denoting the dowel bar
    location in the right location?

31
Mid-Slab Tie Bar Insertion

32
Side Tie Bar Insertion
33
Noted Paving Issues
  • Shims were used at the construction joint because
    the form was not as tall as the depth of the
    paving. This might result in stress point that
    could induce cracking.

34
Noted Paving Issues
  • There was 3 observed stoppages in the paving due
    to the dowel bar bundles not being in the proper
    location. Probably resulting in imperfection in
    smoothness.
  • WSDOT allowed a deviation in the dowel bar
    placement.
  • Only outside lanes had dowel bars across entire
    width.
  • Inside lanes only had dowel bars in the wheel
    path.
  • Saved the project about 56,000.
  • Will this bite them later?

35
Finishing
  • Initial finishing is done by the side forms and
    profile pan followed by a float and carpet drag
    on the paver.

36
Finishing
  • Edge finishing requires 4 laborers (2 on each
    side), one to remove the valley from invert on
    the profile pan, the other to finish.
  • The finishing quality of this edge is very
    important if there is an adjacent lane of PCC to
    be paved.

37
Transverse Tining
38
Curing
39
Noted Issues of the Curing
  • The curing compound was tested twice and failed
    twice.
  • WSDOT allowed the use at twice the application
    rate.
  • During testing the contractor found it difficult
    to apply a uniform cure in windy conditions. The
    wind was not an issue during the case study.

40
Compressive Strength Testing
  • Minimum 28 day compressive strength of 3,216
    psi.

41
Air Entraining Testing
  • Air entrainment between 3 and 7.

42
Ride Testing and Pavement Depth
  • The pavements smoothness was tested using a
    profilograph.
  • Pavement depth was determined from coring.

43
Contractor Bonus
  • The contractor received a 3 bonus for gradation,
    cylinder breaks, and air entrainment. Totaling
    107,500
  • The contractor also received 64,300 for the
    pavements ride smoothness and 86,500 for
    additional pavement thickness.
Write a Comment
User Comments (0)
About PowerShow.com