Title: Procurement Forum Training Presented by Code 210.H
1Procurement Forum Training Presented byCode
210.H
- Type of Procurement Action (TPA)
- Contract Types
2Type of Procurement Action
- Type of Procurement Actions also known as TPAs.
The purpose of the TPAs is to provide guidance in
creating milestones for procurements. - For the contract milestone spreadsheet go to 210
Procurement Operations Home Page,
(http//code210.gsfc.nasa.gov/), click on
Procurement Policy, TPA will be the last item
under Additional Links.
3Contract Milestones
Start of Proc Clock
Title/Description Requisition Date Complete Requisition Package Synopsis - Presolicitation Notice Published Draft Solicitation Released Final Solicitation Released Offers Received Evaluation Complete Competitive Range Determined Discussions Complete Final Proposal Revisions Received Source Selection Decision Negotiations Complete Award Total
Comp - gt100K - 10M 0 14 7 N/A 22 30 30 15 15 7 5 N/A 10 155
Non-Comp - gt100K - 10M 0 14 14 N/A 60 30 30 N/A N/A N/A N/A 30 30 208
Competitive - gt10M - 50M 0 21 7 30 45 45 40 20 20 10 15 N/A 15 268
Non-Comp - gt10M - 50M 0 21 14 N/A 60 45 30 N/A N/A N/A N/A 45 30 245
Competitive - gt50M 0 30 7 30 50 60 40 20 20 10 15 N/A 15 297
Non-Comp - gt50M 0 30 14 N/A 60 60 45 N/A N/A N/A N/A 45 30 284
4TYPES OF CONTRACTS (FAR PART 16)
- Firm-Fixed-Price Contract (FAR Subpart 16.2)
- Cost Reimbursement Contract (FAR Subpart 16.3)
- Other Contract Types (FAR Subpart 16.5 16.6)
5- FIRM-FIXED-PRICE CONTRACTS
6Firm-Fixed-Price Contracts (FAR 16.202)
- Firm-Fixed-Price (FFP) contracts provide for a
price that is not subject to any adjustment on
the basis of the contractors cost experience in
performing the contract. - Use FFP when work can be clearly defined.
7Firm-Fixed-Price Contracts (FAR 16.202)
- FFP contract type places upon the contractor
maximum risk and full responsibility for all
costs and resulting profit or loss. - The contractor is required to deliver the product
specified and there is a maximum limit on the
amount of money the government must pay.
8Firm-Fixed-Price Contracts (FAR 16.202)
- A FFP contract is suitable when the contracting
officer can establish fair and reasonable prices
through - Adequate price competition
- Reasonable price comparisons with prior purchases
of the same or similar supplies or services - Available cost or pricing information permits
realistic estimates of the probable costs of
performance
9Firm-Fixed-Price Contracts (FAR 16.202)
- Performance uncertainties can be identified and
reasonable estimates provided that the contractor
is willing to accept a FFP representing
assumption of the risks involved - FFP is the preferred type when cost risk is none
or minimal, or can be predicted with an
acceptable degree of certainty - Fully funded at time of award
- Incremental funding waiver requires concurrence
of the Deputy Project Manager-Resources/Deputy
Resources Manager (DPMR/DRM) and the Director
prior to concurrence by the Chief Finance Officer
(CFO) and the approval of the Procurement Officer
10Fixed-Price Incentive (FPI) Contracts (FAR 16.204)
- Fixed-Price Incentive contract is a fixed-price
type contract, but provides for profit adjustment
formula to be applied either at a pre-determined
mid-point of performance or upon completion of
performance in order to establish the final
contract price. - FPI is appropriate when both parties can
negotiate an initial target and assume an
appropriate share of the risk.
11 12 13- Cost Reimbursement (FAR 16.302)
- Cost-Plus-Fixed-Fee (FAR 16.306)
- Cost-Plus-Incentive-Fee (FAR 16.304)
- Cost-Plus-Award-Fee (FAR 16.305)
-
14Cost Reimbursement Contracts (FAR 16.302)
- These types of contracts provide for payment of
allowable incurred costs, to the extent
prescribed in the contract. Cost Reimbursement
contracts establish an estimate of total cost for
the purpose of obligating funds and establishing
a ceiling that the contractor may not exceed
(except at its own risk) without the approval of
the contracting officer. - Cost Reimbursement contracts are Suitable for use
only when uncertainties involved in contract
performance do not permit costs to be estimated
with sufficient accuracy to use any type of
fixed-price contract. (FAR 16.301-2)
15Cost Reimbursement Contracts (FAR 16.302)
- A cost-reimbursement contract may be used only
when - The contractors accounting system is adequate
for determining costs applicable to the contract
and - Appropriate Government surveillance during
performance will provide reasonable assurance
that efficient methods and effective cost
controls are used - The use of cost-reimbursement contracts is
prohibited for the acquisition of commercial
items (See FAR Parts 2 and 12).
16Cost-Plus-Fixed-Fee Contracts (FAR 16.306)
- Provides for payment to the contractor of a
negotiated fee that is fixed at the inception of
the contract. - The fixed fee does not vary with actual cost, but
may be adjusted as a result of changes in the
work to be performed under the contract. - This contract type permits contracting for
efforts that might otherwise present too great a
risk to contractors, but it provides the
contractor only a minimum financial incentive to
control costs.
17Cost-Plus-Incentive-Fee Contracts (FAR 16.304)
- A cost-plus-incentive-fee contract is appropriate
for services or development and test programs
when - A target cost and a fee adjustment formula can be
negotiated that are likely to motivate the
contractor to manage effectively.
18Cost-Plus-Award-Fee Contracts (FAR 16.305)
- Provides for a fee consisting of (1) a base
amount fixed at inception of the contract and
(2) an award amount that the contractor may earn
in whole or in part during performance. - Amount of the award fee is determined by the
Government's judgmental Performance Evaluation
Board (PEB) of the contractor's performance in
terms of the criteria stated in the contract
(Performance Evaluation Plan).
19Cost-Plus-Award-Fee Contracts (FAR 16.305)
- The cost-plus-award-fee contract is suitable for
use when- - The work to be performed is such that it is
neither feasible nor effective to devise
predetermined objective incentive targets
applicable to cost, technical performance, or
schedule - The likelihood of meeting acquisition objectives
will be enhanced by using a contract that
effectively motivates the contractor toward
exceptional performance and provides the
Government with the flexibility to evaluate both
actual performance and the conditions under which
it was achieved
20Cost-Plus-Award-Fee Contracts (FAR 16.305)
- Any additional administrative effort and cost
required to monitor and evaluate performance are
justified by the expected benefits and - Must be approved at Procurement Officer level.
21Profit (FAR 15.404-4)
- The contractor Officer shall not negotiate a
price or fee that exceeds the following
statutory limitations, imposed by 10 U.S.C.
2306(d) and 41 U.S.C. 254(b) - (A) For experimental, developmental, or research
work performed under a CPFF contract, the fee
shall not exceed 15 percent of the contracts
estimated cost, excluding fee.
22Profit (FAR 15.404-4)
- (B) For architect-engineer services for public
works or utilities, the contract price or the
estimated cost or fee for production and delivery
of designs, plans, drawings, and specifications
the fee shall not exceed 6 percent of the
estimated cost of construction of public work or
utility, excluding fee. - (C) For other CPFF contracts, the fee shall not
exceed 10 percent of the contracts estimated
cost, excluding fee.
23 24 25- Award Term
- Indefinite-Quantity (FAR 16.504)
- Indefinite-Delivery (Sub Part 16.605)
- Definite-Quantity (FAR 16.502)
- Time and Materials (FAR 16.601)
-
26Award Term Contracts
- Provides for a term consisting of an award term
fixed at inception of the contract. - The award term is determined by the Government's
judgmental evaluation of the contractor's
performance in terms of the criteria stated in
the contract. The number of evaluation criteria
and the requirements.
27- Indefinite-Quantity limit government obligation
to minimum quantity specified in the contract. - Requirements may permit faster deliveries when
production lead time is involved. - Indefinite-Delivery may provide appropriate cost
or pricing arrangement under FAR Part 16. Cost or
pricing arrangements that provide for an
estimated quantity of supplies or services must
comply with FAR Part 16.
28- Definite-Quantity may be used to determine in
advance that a definite quantity of supplies or
services are required during contract period.
Supplies or Services are regularly available
after a short lead time. -
- Requirements provide for filling all actual
purchase requirements of designated Government
activities for supplies or services during a
specified contract period with deliveries or
performance scheduled by placing orders with
contractor.
29- Time and Materials are used only when it is not
possible to estimate accurately the extent or
duration of the work or to anticipate costs with
any reasonable degree of confidence. - Labor Hour used when materials are not involved.
- Requires Determination and Findings (FAR Subpart
1.7), reviewed by Legal and approved by Associate
Division Chief.
30