Title: Slurry Pipeline Design, Testing and Practice
 1Slurry Pipeline Design, Testing and Practice
- Presented by 
 - Graeme Addie and Lee Whitlock 
 - GIW Industries, Inc. 
 - Bob Hagler 
 - Hagler Systems 
 
  2Slurry Pipeline Design
- FIRST NEED TO KNOW 
 - CONCENTRATION FIXED OR CAN BE VARIED 
 - IS PIPELINE EXISTING DIAMETER CAN IT BE VARIED 
 - IS SLURRY SETTLING OR NON-SETTLNIG TYPE 
 - HOW MUCH CAN 
 -  SLURRY SIZE 
 -  TYPE 
 -  CONCENTRATION, ETC. 
 -  VARY/ CHANGE
 
  3Solids Transport Ratefor Different Pipe 
Diameters, Velocities and Concentrations 
 4Demarcation Between Settling and Non-Settling 
 5Slurry System Characteristics 
 6When the solids are less than 80 micron, the 
slurry is usually non-settling 
 7For Non-Settling Slurry
Design flow can theoretically be very low but 
energy dictates need be higher capital cost 
also Also, if laminar, any large particles may 
settle 
 8Non-Settling Slurry Analysis
Rabinowitsch and Mooney have shown that the rate 
of strain of a fluid particle adjacent to the 
pipe wall can be expressed as
(11)
for all laminar flows in a pipe. In eq. 11
(12)
The importance of the Rabinowitsch and Mooney 
proof is that of establishing the scaling law
(13)
for all steady uniform laminar flows in a pipe. 
In other words, both T 0 and 8V/D can be 
determined from experiment with the result that 
the experimentally determined friction, eq. 13, 
can be applied to other pipe sizes and/or 
velocities provided that the same non-Newtonian 
fluid is involved in both the test are the 
design. Here, the shear stress distribution is 
linear varying from a maximum at the boundary to 
zero at the centerline of the pipe, that is,
(3)
In which dp/dx  the pressure gradient along the 
axis of a horizontal pipe. 
 9Where We Can Only Get a Small Sample, We Can Use
-  Rotating Viscometer 
 -  Extrusion Rheometer
 
  10Extrusion Rheometer 
 11Non-settling slurries have a zero flow wall shear 
stress and a laminar and turbulent region.
t
(PSI) 
 12Non-settling slurries arevery concentration 
dependent
1.45 Red Mud Alcan 1.13 Phosphate Slimes 
 13Settling slurries of 100 micron to 5 mm size 
solids,have a minimum head loss and a deposit 
velocity
Settling Slurries 
 14The deposit velocity can be calculated 
 15Pipeline Deposit Velocity 
 16Settling Slurry Modeling Approach
- Wilson and Clift used the concept of a 
stratification ratio R and the threshold of 
turbulent suspension to show that the total 
excess friction pressure gradient (im - if) is  - where the stratification ratio 
 - and 
 -  A' and B are properties of the slurry 
 -  Smd  specific gravity of the delivered mixture 
 -  if  pipe friction due to carrier liquid only.
 
  17Stratification in Settling Slurries
To estimate the variation of R with pipe size and 
mixture velocity, we return to the work of Wilson 
(5). Wilson and Watt proposed that, below a 
particular mixture velocity termed the threshold 
of turbulent suspension, Vs, the solids are fully 
stratified. If the mixture velocity is increased 
above Vs, then part of the solids pass into 
pseudohomogeneous suspension. The value of Vs is 
estimated as where Vt and d are the terminal 
velocity and diameter of a conveyed particle, and 
?w is the (Moody) friction factor for flow of the 
carrier liquid alone (i.e. 2gDiw/V2m). For 
mixture velocities below Vs, flow is fully 
stratified and R  1. For Vm gt Vs, R can be 
estimated where values of m close to 1.7 have 
been determined (6). For particles which are 
sufficiently fine to ensure Vs lt Vm over the 
whole.
(9)
(10) 
 18Settling Slurry Transport Mechanisms
Sliding
Lifted 
 19Analysis of Settling Slurry Test Data
Behaviour of masonry-sand slurry (d50  0.42 
mm) In 203 mm and 440 mm pipe, after Clift et al. 
(1982) 
 20Settling Slurry Pipe Friction Approach 
 21Pipe Friction Constant From Pipe Tests 
 22Wilson Book Method
The equation for the approximating power law is 
readily obtained in terms of V50, giving the 
relative solids effect as
The coefficient 0.22 represents the value of the 
relative solids effect at the point where Vm 
equals V50, as mentioned previously. The power M 
is about 1.7 for slurries with a narrow particle 
grading (Clift et al., 1982)
Based on data obtained for various slurries 
tested at the GIW Hydraulic Laboratory, the 
resulting expression is
Prepared by CRA GIW Industries, Inc.
22 
 23GIW has Developed Different Models for Predicting 
Head Loss
Definition sketch for limit of stationary deposit 
zone. 
 24The GIW Models are Some of the Best 
Available.In a Long Pipeline with Difficult 
Slurry, it is Best to do Tests. 
 25GIW Slurry Test Loops3, 4, 6, 8, 12, 18 
and 20 
 26Observing Deposit Velocity at Glass Pipe Section 
 27US Army Corps. of EngineersSlurry Tests
- Tests Run in 4 Loop 
 - Used Three Different Sand Sizes 
 - 650 micron 
 - 1250 micron 
 - 2250 mircon 
 - 4 Concentrations of each Sand 
 -  (5, 10, 20, and 30 Cv) 
 - 5 Concentrations Clay for Each 
 -  (0, 2, 4, 5, and 6 Cv) 
 - Total Number of Tests - 60
 
Prepared by CRA GIW Industries, Inc.
27 
 28US Army Corps. Of Engineers Sand Results
Prepared by CRA GIW Industries, Inc.
28 
 29Argyle DiamondSimulated Slurry Pipe Testin 250 
and 300 mm Loop
Prepared by CRA GIW Industries, Inc.
29 
 30Plugged PipelineWhile Running at CV49
Prepared by CRA GIW Industries, Inc.
30 
 31Energy vs. Transport Rate for a 250 mm Pipe
Prepared by CRA GIW Industries, Inc.
31 
 32Schematic of Hibernia Oil Platform
Prepared by CRA GIW Industries, Inc.
32 
 33Hibernia Slurry Tests
- Phase 1 Determine the head loss characteristics 
of pumping magnetite ore in various pipelines. 
Results to be used to design distributor 
system.Average Solids S.G.  4.392Average 
Particle Size  25 mmA. Tests in combo 254 / 
305 mm loop at 0, 4, 8, and 16 by volume. 
 Flow rates up to 550 L/sec.B. Tests in combo 
406 / 457 / 508 mm loop at  0, 6, 8, and 10 
by volume. Flow rates up to 1250 L/sec  - Phase 2 Test Full Scale Mock-up of Actual 
Distributor at concentrations of 0, 4, 8, and 
12 by volume.  Flow rates up to 1800 L/sec.  
Prepared by CRA GIW Industries, Inc.
33 
 34Hibernia Distributor Slurry Test
Prepared by CRA GIW Industries, Inc.
34 
 35Hibernia Slurry Tests
Prepared by CRA GIW Industries, Inc.
35 
 36Syncrude Coarse RockReady for Loading in 450 m 
Loop
Sliding
Lifted 
 37Tar Sands Slurry Pipe Friction
Frictional headlosses for tar sand slurries at 
40C, as determined in two laboratories
Delivered concentration for coarse rock in water, 
Cr  0.066, D  490 mm 
 38Dallas White Rock Lake
- 20 Mile Transportation of Sediment 
 - Slurry Analysis Performed by GIW for Terra-Mar, 
Consulting Engineers  - GIW Extrusion Rheometer tests performed to 
predict pipeline friction  - Silt NOT Sand 
 - Double Velocity required for Sand 
 - 3.25 times Friction for Sand 
 - 3.25 x 2  6.5 times the power 
 - Results  (3) Pumps rather than (9) Pumps 
 - Results  5,000 HP rather than 27,000 HP 
 - Huge Project Savings
 
  39Dallas Process Concept 
 40Flow Properties of White-Rock-Lake-Sediment 
Slurries
For Terra-Mar Consulting Engineers Determined 
at GIW Hydraulic Laboratory
Four tests were performed in the GIW Hydraulic 
Laboratory for the Terra-Mar, Consulting 
Engineers. These four test were carried out in 
the .43 ID Extrusion Rheometer and are 
designated and differentiated as follows 
 410.43 ID Extrusion Rheometer Test
tau0  fn(8V/D) Test 4-97 Sm  1.30 
 42Scaled Test Results
-dp/dx  fn(V) Terra-Mar ID  19in. 
 43Application of GIW Test Data 
 44Hydraulic Gradeline 24 inch 20 Mile 
SystemDredge, Unmanned Booster, and Instruments 
 45Radio Link to Dredge Dallas White Rock Lake 
 46Main Control Radio Link to Dredge, Phone Line 
Link to Remote Booster 
 47Remote Booster  6 miles  Dallas White Rock Lake 
 48System Make Up Water Dallas White Rock Lake 
 49Automatic Flow Control Dallas White Rock Lake 
 50Dredge SG Approx 1.1 Dallas White Rock Lake 
 51Four Corners Mine Transportation Analysis 
 52Long Distance Pipeline Pumps are Usually Not This 
LargeCentrifugal Pumps are Usually Limited to 
6 in Series in One Location
Prepared by CRA GIW Industries, Inc.
52 
 53In Florida, Up to 11 Pumps in Series May be 
Located Along a 21 Pipeline, 8.5 Miles Long 
 54Phosphate Pump and Pipe Tests in the Field 
 55Florida Phosphate Matrix Transport Costs
Existing Matrix Train 17, with 19 ID Pipe, 
Except 10 WBC 46 (49)s  LSA 62 Pit Pump Costs 
at Different Concentrations (and TPH), 45,200 
Feet (Same Motors, V.S. Pumps _at_ Max Speed, 300 
Micron D50) (Assumes 1" Suction Liner Wear, 2" 
Casing Belly Wear)
 All costs are figured at 6000 hours unless 
specified otherwise 
 56Kaolin Hydro-transport Pipeline Design
Kaolin Product 37 miles of 12 
pipeline d50  8 µm 98-99 lt 50 µm Some 
200 µm quartz Cw  24  36 Closed Test 
Loop Setup 400 feet long 12 steel pipeline 
loop Observation section in inclinable 
pipe Fully instrumented to measure both 
 pipeline and pump characteristics. 
Prepared by CRA GIW Industries, Inc.
56 
 573 Pumps in Series Tachonite Tails Pump System
Prepared by CRA GIW Industries, Inc.
57 
 58Power Failure Example
3.5 miles
3.5 miles
Pumps located in two pumping stations (3 in 
series) with sumps
Prepared by CRA GIW Industries, Inc.
58 
 59Piping Arrangements and Considerations
The simplest solution is often the best solution.
Prepared by CRA GIW Industries, Inc.
59 
 60Startup on Part Full Line (or filling)
Pump comes up to speed and then operates at point 
where H-Q curve of pump intersects the system 
resistance for the amount of line filled.
- Unless throttle or controlled by reduced speed, 
operation will result in  -  Increased Power 
 -  Possible Cavitation 
 - If Pump H-Q curve is flat, increases will be 
larger 
Prepared by CRA GIW Industries, Inc.
60 
 61Startup (Sequencing) of Multiple Pumps in a Line
- After some time (steady flow) all pumps located 
at pit end of line.  -  Shortly after starting all pumps located at pit 
end.  - After some time (steady flow) pumps located 
(spaced) along line.  - Shortly after starting pumps spaced along line. 
 - Starting booster before pit pump.
 
Prepared by CRA GIW Industries, Inc.
61 
 62Water Hammer
-  Occurs when rapid change happens 
 -  May be initiated by 
 -  startup 
 -  shutdown 
 -  rapidly closing valve 
 -  water column closure 
 -  Blocked suction 
 -  Disturbance coming from the change 
 -  is in the form of waves traveling outwards
 
Individual waves pass up and down at constant 
velocity, neither being attenuated or undergoing 
shape change by each other Waves are reflected 
in full or part at each change of section. Net 
pressure at a section is sum of pressure 
heights Maximums occur at wave crossover points 
or initiation or reflection locations.
Prepared by CRA GIW Industries, Inc.
62 
 63Water Hammer Example
When cavitation occurs Vapor column created can 
be pulled up line by inertia after pump 
collapses. As line slows, pump will pick up 
sending a second column after the 
first. Subsequent closure of two columns will 
result in transient.
A closure may be likened to a rapidly closing 
value The transient in this case is Which can 
be simplified to any air will cushion
Prepared by CRA GIW Industries, Inc.
63 
 64Conclusions
- It is Possible to Use Centrifugal Pumps to 
Transport Solids in a Pipeline up to 30 Miles and 
More.  - It is Important to Categorize Slurries Accurately 
in Order to Identify the Most Energy Efficient, 
Lowest Wear Operating Velocity and Concentration.  - Test Lab Pipeline Tests are Necessary in Most 
Cases to Determine Pipe Friction and Pump 
Performance