Tamalpais Union High School District Measure A Bond Modernization Program - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Tamalpais Union High School District Measure A Bond Modernization Program

Description:

Tam 2 Gus Gym/locker rooms, Palmer Hall. Tam 3 Hoetger, Phoenix, Wood Hall, ... Drake dry rot - under investigation. Summer moves - on schedule ... – PowerPoint PPT presentation

Number of Views:58
Avg rating:3.0/5.0
Slides: 17
Provided by: vannech
Category:

less

Transcript and Presenter's Notes

Title: Tamalpais Union High School District Measure A Bond Modernization Program


1
Tamalpais Union High School DistrictMeasure A
Bond Modernization Program
  • Mid-Program Review
  • June 10, 2003

2
Agenda
  • Increment Refresher
  • Program Schedule - Design
  • Program Schedule - Construction
  • Projected Program Variances ()
  • Design Issues
  • Construction Issues
  • Miscellaneous Fiscal Items
  • Other Critical Activities

3
Increment Refresher
  • Tam 2 Gus Gym/locker rooms, Palmer Hall
  • Tam 3 Hoetger, Phoenix, Wood Hall, Woodshop,
    Ceramics, Music, Woodruff
  • Tam 4 Baker Hall (Student Center), Theater,
    Keyser Hall, Benefield, Weight Room, Ruby Scott
    Gym

4
Increment Refresher (cont'd)
  • Drake 2 Building 500
  • Drake 3 Main campus, incl. Devonshire
    and Theater
  • Drake 4 Gym/locker rooms, student center and
    eating area

5
Increment Refresher (cont'd)
  • Redwood 2 Main campus
  • Redwood 3 West parking, miscellaneous
  • San Andreas Entire campus
  • Corp Yard Conversion of MCAL office to MO,
    food service

6
Increment Refresher (cont'd)
  • Tam F-1 Baseball, softball, soccer
  • Tam F-2 Football, track
  • Drake F-1 All Drake fields
  • Redwood F-1 Moody Field (varsity baseball)
  • Redwood F-2 Football, track
  • Redwood F-3 Softball

7
Program Schedule - Design
  • Not yet started
  • Redwood 3
  • Redwood Fields 3
  • To DSA by Fall 2003
  • Corp Yard
  • Tam 4
  • San Andreas
  • Drake 4
  • Tam Fields 2
  • Drake Fields
  • Redwood Fields 2

8
Program Schedule - Design (cont'd)
  • In DSA now
  • Tam 3
  • DSA approved
  • Tam Fields 1
  • Advertised
  • Drake 3
  • Redwood Fields 1

9
Program Schedule - Construction
  • Drake 2 Now - August 2003
  • Tam 2 Now - October 2003
  • Redwood 2 Now - July 2005
  • Redwood F-1 July 2003 - January 2004
  • Drake 3 July 2003 - October 2005
  • Corp Yard August 2003 - December 2003
  • Tam 3 October 2003 - December 2004
  • Tam F-1, F-2 April 2004 - November 2004
  • Redwood F-2 April 2004 - November 2004
  • Drake Fields April 2004 - November 2004
  • Drake 4 April 2004 - August 2005
  • Tam 4 June 2004 - December 2005
  • San Andreas June 2004 - August 2004
  • Redwood 3 June 2005 - August 2005
  • Redwood F-3 June 2005 - November 2005

10
Projected Program Variances
  • 2,828,100 Construction
  • - 1,663,500 Non-construction
  • 4,039,400 Program reserves
  • 6,130,600 Unallocated State funds
  • 11,334,600 Remaining available funds

11
Design Issues
  • Tamalpais Increment 4 (QKA)
  • Theater design, schedule
  • Keyser science labs, classrooms in Baker Hall
  • Drake Increment 4 (DLM)
  • Approval of concepts, estimates

12
Design Issues (cont'd)
  • Redwood Increment 3 (QKA)
  • Availability of funding for extra projects
  • San Andreas (QKA)
  • Size, placement of second new modular
  • Football / Track Field Projects (Carducci)
  • Specification for artificial turf
  • Cost estimates
  • Redwood bleachers

13
Construction Issues
  • Drake Increment 2
  • On schedule, within budget
  • Drake Increment 3
  • Bid date delayed by late DSA approval
  • Portables on basketball courts

14
Construction Issues (cont'd)
  • Redwood Increment 2
  • Moving from summer construction areas
  • Redwood Moody Field
  • Bid alternates for artificial turf, dugouts,
    drainage
  • Tam Increment 2
  • Scheduling for science portable
  • Tam Fields Increment 1
  • Delayed by lease-leaseback process

15
Miscellaneous Fiscal Items
  • Interest income - on track
  • Relocation costs - need to watch
  • Labor compliance program - started
  • Donations - encouraged
  • Hazardous materials abatement - growing
  • Legal costs - within budget
  • Field conditions - need more investigation
  • Pools - on hold

16
Other Critical Activities
  • Drake dry rot - under investigation
  • Summer moves - on schedule
  • FY financial close / next year's budget - by June
    30
  • Contracts and contract modifications - ongoing
  • Labor compliance program startup - done
  • Colors - to Board June 24