Title: System z Linux Proof Of Concept Project Management Best Practices
1System z Linux Proof Of Concept Project
Management Best Practices September 8, 2009
Marianne Eggett System z Linux Practice
Manager Marianne.eggett_at_mainline.com
2Agenda
- Mainlines System z Linux Life Cycle
- Planning for the POC
- Project Methodology Overview
- Dos and Donts
3Through Out the Life Cycle Mainline is there
Proving
Planning
- System z Linux POC Projects
- Systems Assurance
- Architecting Solutions
- Installation Services
- IBM Specialty Engine Loaner
- Program
- Business Cases
- Sizing Servers for IFLs
- Value of Z Linux Presentations
- Account Planning
- Proposal Development
- Scoping POC
- Linux LOTS
- zVM Linux Healthcheck
Production
4Linux Team
- The Team
- Planning New Workload Sales Team
- Marianne Eggett Central, West
- Andy Greco NE, Mid Atlantic, SE
- Proving Installation Team
- Project Managers
- zVM and Linux Technical Consultants
- WebSphere, DB2 UDB, other expertise
- Production 24x7 SuSE LOTS Support Line
- Supporting zVM SuSE Linux
- Supporting IBM and many non-IBM middleware
Software products
5Best Fit For Server Consolidations
- DB2 Connect Ideal 1st Application
- Oracle Generates excellent TCOs
- WebSphere AS, MQSeries Portal
- WebSphere HATS HOD
- CICS Gateways, IMS Connect
- Lotus Domino eMail and Applications
- Tivoli TSM Server
- DB2 UDB
- Communication Controller for Linux (3745
replacement) - Network Infrastructure FTP, NFS, DNS, etc.
- ISV products WebFocus, Attachmate
6MIS Customer References
- State of Idaho Domino, Apache appl
- Emigrant Savings WebSphere
- University of Maryland Oracle
- Thomas Jefferson Un. Hospital TSM
- Indianapolis Power Light WebSphere Hats
- Boston University DB2 UDB, Oracle
- John Hopkins University WebSphere
- Brocade Development Environment
7Linux Partners
- Novell Business Partnership
- Mainline is Novells largest remarketer of
System z SuSE Linux - Red Hat Business Partnership
- IBM
- zVM and PPA Software
- IBM Software Excel Support Line
- Velocity Software for zVM Linux performance
tuning
8Managing the Linux Proof of Concept
9Planning
Proving Managing the Linux POC
Project Initiation
Project Definition
- Value Proposition
- Learning the value of System z Linux
- Server Consolidation
- Sizings
- Business Case Development
- POC Initiative
- Scoping POC
- POC IFL Sizings
- Real memory sizing
- Scope Document
Installation Set Up
Testing
Closing
10Value Proposition
- IBM
- Scorpion Study
- Environmental Studies
- Application Assessments
- zRace
Proving
- Mainline
- IFL Capacity sizings
- Business Case
- zRace with IBM Techline
Production
11Planning
Proving Managing the Linux POC
Project Initiation
Project Definition
- Value Proposition
- Learning the value of System z Linux
- Server Consolidation
- Sizings
- Business Case Development
- POC Initiative
- Scoping POC
- POC IFL Sizings
- Real memory sizing
- Scope Document
- Infrastructure Planning
- Hardware
- Software
- Network
- Security
- Disk
- Backup Recovery
- Project Planning
- Scope Document
- Project Plan
- Team Roster
- Systems Assurance
- Statement of Work Consulting Services
- Status Report
- Phone Support
- IBM Loaner Program
- POR date
- Success Criteria
- Configs
Installation Set Up
Testing
Closing
12Project Definition
- Choosing Scope is Critical
- Significant enough
- Not overwhelming
- Resource Commitment
- Senior Management Commitment
- Success Criteria
- System assurances are valuable
13Planning
Proving Managing the Linux POC
Project Initiation
Project Definition
- Value Proposition
- Learning the value of System z Linux
- Server Consolidation
- Sizings
- Business Case Development
- POC Initiative
- Scoping POC
- POC IFL Sizings
- Real memory sizing
- Scope Document
- Infrastructure Planning
- Hardware
- Software
- Network
- Security
- Disk
- Backup Recovery
- Project Planning
- Scope Document
- Project Plan
- Team Roster
- Systems Assurance
- SOW Consulting Svc
- Status Report
- Phone Support
- IBM Loaner Program
- POR date
- Success Criteria
- Configs
Installation Set Up
- IBM loaner Eq.
- zVM Linux install
- Other SW install
- Network
- Security
- Disk
- DB loads
- Application set up
- Other Distributed Servers
- Weekly Status Meeting
- Status Report
Testing
Closing
14Installation and Set up
- Week day vs. Weekend changes
- IBM CE
- Real Memory
- Networks
- Consultants on site for skills transfer
- Back up environment
- Clones
- Weekly status meeting
15Planning
Proving Managing the Linux POC
Project Initiation
Project Definition
- Value Proposition
- Learning the value of System z Linux
- Server Consolidation
- Sizings
- Business Case Development
- POC Initiative
- Scoping POC
- POC IFL Sizings
- Real memory sizing
- Scope Document
- Infrastructure Planning
- Hardware
- Software
- Network
- Security
- Disk
- Backup Recovery
- Project Planning
- Scope Document
- Project Plan
- Team Roster
- Systems Assurance
- SOW Consulting Svc
- Status Report
- Phone Support
- IBM Loaner Program
- POR date
- Success Criteria
- Configs
Installation Set Up
- IBM loaner Eq.
- zVM Linux install
- Other SW install
- Network
- Security
- Disk
- DB loads
- Application set up
- Other Distributed Servers
- Weekly Status Meeting
- Status Report
Testing
- Test Plan
- Unit
- Volume/Performance
- Weekly Status Mtg
- Status Report
- Issues Management
- Escalation Process
- Resource Management
- In house
- Mainline
- IBM
- Linux vendor
- ISVs
Closing
16Testing
- Test Plan
- Outline tests
- Document performance targets when compared to
current production system - Keep track of each runs changes
- Keep track of each runs results
- Learning curve
- Ask for help early
- Problems
- Ask for help early
- IBM and BP resources
- Open problems with software vendors too, i.e.
Oracle - Weekly Status meetings
- Schedule meeting out 12 weeks
17Planning
Proving Managing the Linux POC
Project Initiation
Project Definition
- Value Proposition
- Learning the value of System z Linux
- Server Consolidation
- Sizings
- Business Case Development
- POC Initiative
- Scoping POC
- POC IFL Sizings
- Real memory sizing
- Scope Document
- Infrastructure Planning
- Hardware
- Software
- Network
- Security
- Disk
- Backup Recovery
- Project Planning
- Scope Document
- Project Plan
- Team Roster
- Systems Assurance
- SOW Consulting Svc
- Status Report
- Phone Support
- IBM Loaner Program
- POR date
- Success Criteria
- Configs
Installation Set Up
- IBM loaner Eq.
- zVM Linux install
- Other SW install
- Network
- Security
- Disk
- DB loads
- Application set up
- Other Distributed Servers
- Weekly Status Meeting
- Status Report
Testing
- Test Plan
- Unit
- Volume/Performance
- Weekly Status Mtg
- Status Report
- Issues Management
- Escalation Process
- Resource Management
- In house
- Mainline
- IBM
- Linux vendor
- ISVs
Closing
- Success Criteria Acceptance
- Loaner Purchase or removed
- Production Implementation Planning
- Purchasing
- Technical Services
- Vendor 24x7 Support
18Closing
- Document results against Success Criteria
- Review results with project team to gain
everyones concurrence - Identified lessons learned
19Proving Managing the Linux POC
Project Initiation
3-5 weeks
Project Definition
- Value Proposition
- Learning the value of System z Linux
- Server Consolidation
- Sizings
- Business Case Development
- POC Initiative
- Scoping POC
- POC IFL Sizings
- Real memory sizing
- Scope Document
1-3 weeks
- Infrastructure Planning
- Hardware
- Software
- Network
- Security
- Disk
- Backup Recovery
- Project Planning
- Scope Document
- Project Plan
- Team Roster
- Systems Assurance
- SOW Consulting Svc
- Status Report
- Phone Support
- IBM Loaner Program
- POR date
- Success Criteria
- Configs
Installation Set Up
2-20 weeks
- IBM loaner Eq.
- zVM Linux install
- Other SW install
- Network
- Security
- Disk
- DB loads
- Application set up
- Other Distributed Servers
- Weekly Status Meeting
- Status Report
Testing
1-3 weeks
- Test Plan
- Unit
- Volume/Performance
- Weekly Status Mtg
- Status Report
- Issues Management
- Escalation Process
- Resource Management
- In house
- Mainline
- IBM
- Linux vendor
- ISVs
Closing
- Customer Final Report
- Success Criteria Acceptance
- IFL Purchased or removed
- Production Implementation Planning
- Purchasing
- Technical Services
- Vendor 24x7 Support
20Managing the Linux POC
Hardware Solution Coordination
zVM and Linux POC Project Management Deliverables
- These are PMO standard templates to manage Linux
POCs - POC Scope Document
- POC Success Criteria
- POC Project Plan
- POC Team Roster
- POC Status Report
21Beware of the Benchmark POC
Final Comments
- Stay away from performance benchmark tests that
drive the IFL to 100 to determine maximum
transactions compared to Intel/Power platforms. - System z Linux sweet spot is as a multi-tasker.
22Ideal POC Scope
- Focus the POC scope on
- Learning the environment
- Functional test or Production comparative test
- Follow up on the Business Case
23Planning
Proving Managing the Linux POC
Project Initiation
Project Definition
- Value Proposition
- Learning the value of System z Linux
- Server Consolidation
- Sizings
- Business Case Development
- POC Initiative
- Scoping POC
- POC IFL Sizings
- Real memory sizing
- Scope Document
- Infrastructure Planning
- Hardware
- Software
- Network
- Security
- Disk
- Backup Recovery
- Project Planning
- Scope Document
- Project Plan
- Team Roster
- Systems Assurance
- SOW Consulting Svc
- Status Report
- Phone Support
- IBM Loaner Program
- POR date
- Success Criteria
- Configs
Installation Set Up
- IBM loaner Eq.
- zVM Linux install
- Other SW install
- Network
- Security
- Disk
- DB loads
- Application set up
- Other Distributed Servers
- Weekly Status Meeting
- Status Report
Testing
- Test Plan
- Unit
- Volume/Performance
- Weekly Status Mtg
- Status Report
- Issues Management
- Escalation Process
- Resource Management
- In house
- Mainline
- IBM
- Linux vendor
- ISVs
Closing
- POC Final Report
- Success Criteria Acceptance
- IFL Purchased or removed
- Production Implementation Planning
- Purchasing
- Technical Services
- Vendor 24x7 Support