Secure System Scheduling with High Wind Penetrations PowerPoint PPT Presentation

presentation player overlay
1 / 12
About This Presentation
Transcript and Presenter's Notes

Title: Secure System Scheduling with High Wind Penetrations


1
Secure System Scheduling with High Wind
Penetrations
  • J. Kennedy
  • March 2009

2
Contents
  • Background to the Irish Power system
  • Problems scheduling the System
  • Spinning and standing reserve on the system
  • Wilmar scheduling model
  • Adjustment of reserve requirements
  • Fast start balancing plant
  • Conclusions
  • Future Research

3
Background (Growth of Wind Generation)
  • Currently (2008 data)
  • 10 wind energy penetration in Ireland
  • 2 wind energy penetration in the UK
  • Projections for 2020 indicate
  • 42 wind energy penetration likely in Ireland
  • 13 wind energy penetration likely in the UK 1
  • Instantaneous power penetration could be much
    greater
  • Achieving projected growth figures will
  • Significantly reduced imported natural gas in the
    UK Ireland
  • Reduce Carbon emissions, inline with government
    targets

4
Background (Challenges of Large Scale Wind)
  • Balancing problems due to wind
  • Increased uncertainty (limitations to wind
    forecasts accuracy)
  • Variability, increased cycling of thermal plant
    2
  • Increased part loading of thermal plant
  • Balancing options

5
High wind penetrations
30 wind penetration
Light load on Sunday morning
Strong wind
6
Wilmar Scheduling Model
  • Developed by Risø for Denmark, Finland, Germany,
    Norway and Sweden
  • Realistic forecasting mode
  • Modified to include mixed Integer variables for
    use in Irish system
  • Used extensively in the All Island Grid Study
    report
  • Deterministic mode - assumes a perfect forecast
  • Stochastic mode assumes a realistic forecast
    error
  • Incorporates Day ahead, and intraday
    scheduling Unit ramp rates
  • Min/Max unit generation Min unit up and down
    times
  • Temperature dependent start-up costs
    Realistic unit reserves
  • Time variable fuel costs Carbon tax
    Stochastic optimisation
  • Validated against Plexos in the All Island Grid
    Study

7
Reserve classification
Spinning
Non-spinning?
Non-spinning
8
Assumptions for 2020
  • As per AIGS
  • 1000 MW of asynchronous interconnection
  • 100 MW interconnection available for tertiary
    reserve
  • 6000 MW of installed wind (portfolio 5)
  • Tertiary reserve (90 seconds to 5 minutes)
    covers
  • 100 of largest scheduled unit additional
    tertiary reserve due to wind
  • Replacement reserve (5 minutes onwards) covers
  • 90th percentile of total forecast error

9
Assumptions for 2020
  • Tertiary reserve (90 seconds to 5 minutes)
    covers
  • 100 of largest scheduled unit additional
    tertiary reserve due to wind

Provide from off-line plant?
10
Operational costs and reserve
Deterministic mode
11
Fast start off-line plant for TR1
  • Additional tertiary reserve due to wind supplied
    from off-line plant
  • For 6000 MW wind, 131 MW of extraTR1 required
    easily achieved
  • Tertiary reserve cost reduced by 22,or 3.6 M
  • 146 less start-ups per year with modified TR1
  • 213 less start-ups per year on plant larger than
    110 MW

12
Conclusions
  • Allow offline plant to participate in Tertiary
    reserve band one
  • Sufficient fast start generation already
    available for high wind penetration scenarios
  • Reducing TR1 from online plant, reduces cycling
    of thermal plant, a major worry of new AIGS
  • Existing peaking plant more profitable for
    owners

13
What if simulations
  • With and without additional tertiary reserve due
    to wind
  • Examine distribution of
  • Power changes on each unit
  • Number of problem periods (low reserve) per year

14
What if simulations
  • With and without interconnection to GB
  • With and without replacement reserve
  • With and without nominal tertiary spinning
    reserve
  • With and without additional tertiary reserve due
    to wind
  • With and without Turlough Hill pumped storage
    plant
  • Examine periods of peak wind penetration
  • with and without reduced tertiary reserve
  • Examine distribution of
  • Power changes on each unit
  • Number of problem periods (low reserve) per year

15
Forecast vs. Fuel saver (summary)
  • Forecast mode with diesel delivers significant
    savings over fuel saver
  • 150 MW max gen-set capacity required for up to
    600 MW wind (25 of wind)
  • Even with perfect forecasting net demand is more
    variable more flexible plant required
  • Capacity factor of plant increased in forecast
    mode

With diesel
Fig. 4.31
Write a Comment
User Comments (0)
About PowerShow.com