Development Plan of the Slovenian Transmission Grid Inside the UCTE Interconnection PowerPoint PPT Presentation

presentation player overlay
1 / 14
About This Presentation
Transcript and Presenter's Notes

Title: Development Plan of the Slovenian Transmission Grid Inside the UCTE Interconnection


1
Development Plan of the Slovenian Transmission
Grid Inside the UCTE Interconnection
Smart Grids Workshop, September 25th, Slovenia
2
Current operation state of the Slovenian power
system
  • Relatively strong transmission network, 2000 MW
    of peak load and sufficient production capacities
    inside system for domestic demand covering
  • In-expensive use of the Slovenian transmission
    network by EU energy market players leads to
    un-secure operation conditions of the Slovenian
    power system and the whole UCTE network.
  • Extensive energy power flow from north-east to
    west is concentrated on the Slovenia-Italy border
    and secure power system operation is endangered

3
UCTE Energy Balance is Concentrated on the
Slovenia-Italy Border
-7000 MW
4
Total Power Flow on Slovenia-Italy Border During
2001
MW 1200 900 600 300 0 -300
TTC
NTC
Power flow
January February March April May
June July August Sept. October
Novem. Decem.
5
Total Power Flow on Slovenia-Italy Border During
2005
NTC
6
Dynamic simulation results, case 1 SLO-I
tie-lines outage at 1000 MW
7
Dynamic simulation results, case 2 SLO-I
tie-lines outage at 1700 MW
NTC
8
Possible UCTE splitting due to the large distance
power transfer
9
Actual and Administrative Slovenia-Italy
Tie-lines Capacity Contrast
  • Thermal capacity of the existing two high-voltage
    lines between Slovenia and Italy, installed on
    the corridor from Divaca substation, is more than
    2000 MW.
  • Secure capacity of the existing corridor is due
    to the whole UCTE network limitation (mostly
    because of the un-complete Austrian network)
    about 1200 MW to max.1500 MW, depending on power
    flow control possibilities.
  • The actual power flow on Slovenia-Italy border is
    moving around the maximal technical capacity of
    the tie-lines.
  • The existing administrative level for network
    trading is just cca. 400 MW and is not in
    accordance with the actual power flows and
    technical limits.

10
The reason for discrepancy between actual power
flow and administrative NTC level money game
  • Average auction price for the Slovenian-Italy
    cross-border capacity use is pretty high (12
    Euro/MWh) due to existence of the non-expensive
    power sources in the north-east area.
  • Slovenia is loosing about 25 million Euro/year
    for its network use due to the too low
    administrative NTC level on Slovenia-Italy border
    this money is collected on other EU borders.
  • Merely a cost of the Slovenian transmission
    network active power losses are climbed to 20
    millions Euro/year and almost a half of that
    losses are caused by the transit power flows.
  • ELES should cover the costs (losses, maintenance,
    re-dispatching) and risks of energy trading power
    flows by income from domestic energy users.

11
Possible Technical Solutions
  • Strengthening the transmission network by
    constructing new high-voltage lines, and
  • installing devices for active power flow control
    on the certain transmission lines (phase-shifting
    transformers, PST)

12
PST Inside Divaca Substation
  • ELES already started investment process for 400
    kV and 1200 MVA PST construction inside Divaca
    substation in order to
  • control power flows across its network under
    secure technical level assuring thus reliable
    operation of a huge part of the UCTE network,
  • control power flow on Slovenia-Italy border close
    to the existed maximal technical limit (1500 MW)
    if the NTC height will follow this technical
    possibilities,
  • enable a safe and non-cost re-closure of the
    Slovenia-Italy tie-lines by help of the wide
    range voltage-angle control of the installed PST.

13
Steps of ELES investment plan on the Slovenian
transmission network
14
Conclusion
  • ELES steps of its transmission network
    investments will assure
  • reliable supply of domestic electric energy
    consumers,
  • secure operation of the whole UCTE
    interconnection, not dependent of unpredictable
    EU market processes,
  • more fair distribution of market affected costs
    and incomes inside EU TSO partners
Write a Comment
User Comments (0)
About PowerShow.com