Title: Development Plan of the Slovenian Transmission Grid Inside the UCTE Interconnection
1Development Plan of the Slovenian Transmission
Grid Inside the UCTE Interconnection
Smart Grids Workshop, September 25th, Slovenia
2Current operation state of the Slovenian power
system
- Relatively strong transmission network, 2000 MW
of peak load and sufficient production capacities
inside system for domestic demand covering - In-expensive use of the Slovenian transmission
network by EU energy market players leads to
un-secure operation conditions of the Slovenian
power system and the whole UCTE network. - Extensive energy power flow from north-east to
west is concentrated on the Slovenia-Italy border
and secure power system operation is endangered
3UCTE Energy Balance is Concentrated on the
Slovenia-Italy Border
-7000 MW
4Total Power Flow on Slovenia-Italy Border During
2001
MW 1200 900 600 300 0 -300
TTC
NTC
Power flow
January February March April May
June July August Sept. October
Novem. Decem.
5Total Power Flow on Slovenia-Italy Border During
2005
NTC
6Dynamic simulation results, case 1 SLO-I
tie-lines outage at 1000 MW
7Dynamic simulation results, case 2 SLO-I
tie-lines outage at 1700 MW
NTC
8Possible UCTE splitting due to the large distance
power transfer
9Actual and Administrative Slovenia-Italy
Tie-lines Capacity Contrast
- Thermal capacity of the existing two high-voltage
lines between Slovenia and Italy, installed on
the corridor from Divaca substation, is more than
2000 MW. - Secure capacity of the existing corridor is due
to the whole UCTE network limitation (mostly
because of the un-complete Austrian network)
about 1200 MW to max.1500 MW, depending on power
flow control possibilities. - The actual power flow on Slovenia-Italy border is
moving around the maximal technical capacity of
the tie-lines. - The existing administrative level for network
trading is just cca. 400 MW and is not in
accordance with the actual power flows and
technical limits.
10The reason for discrepancy between actual power
flow and administrative NTC level money game
- Average auction price for the Slovenian-Italy
cross-border capacity use is pretty high (12
Euro/MWh) due to existence of the non-expensive
power sources in the north-east area. - Slovenia is loosing about 25 million Euro/year
for its network use due to the too low
administrative NTC level on Slovenia-Italy border
this money is collected on other EU borders. - Merely a cost of the Slovenian transmission
network active power losses are climbed to 20
millions Euro/year and almost a half of that
losses are caused by the transit power flows. - ELES should cover the costs (losses, maintenance,
re-dispatching) and risks of energy trading power
flows by income from domestic energy users.
11Possible Technical Solutions
- Strengthening the transmission network by
constructing new high-voltage lines, and - installing devices for active power flow control
on the certain transmission lines (phase-shifting
transformers, PST)
12PST Inside Divaca Substation
- ELES already started investment process for 400
kV and 1200 MVA PST construction inside Divaca
substation in order to - control power flows across its network under
secure technical level assuring thus reliable
operation of a huge part of the UCTE network, - control power flow on Slovenia-Italy border close
to the existed maximal technical limit (1500 MW)
if the NTC height will follow this technical
possibilities, - enable a safe and non-cost re-closure of the
Slovenia-Italy tie-lines by help of the wide
range voltage-angle control of the installed PST.
13Steps of ELES investment plan on the Slovenian
transmission network
14Conclusion
- ELES steps of its transmission network
investments will assure - reliable supply of domestic electric energy
consumers, - secure operation of the whole UCTE
interconnection, not dependent of unpredictable
EU market processes, - more fair distribution of market affected costs
and incomes inside EU TSO partners