Title: An Integrated Program for GBT Focal Plane Array Development
1An Integrated Program for GBT Focal Plane Array
Development
- Steven White
- Based on discussions with
- Rick Fisher, John Ford, Matt Morgan, Roger
Norrod, Kamaljeet Saini, Amy Shelton, Richard
Prestage, John Webber, and others
2Summary
- A pathfinder focal plane array (FPA) frontend is
the necessary first step in an integrated
development program. - K-band is the appropriate frequency, for reasons
which will be outlined. - We have the necessary resources and expertise (,
more importantly appropriate staff effort) ready
and eager to go. - We need to start now to demonstrate results
within 2 years (production use in 3 years).
3Integrated FPA Development Program
- The Science Case is the primary driver for
frequency selection and detailed specifications. - Development Program Components
- Frontend (EM Components, Cryogenics, HEMT Amp,
Calibration, Downconversion) - Digitization and IF Transmission
- Spectrometer
- Software
- Scientific desires must be tempered by technical
realities and costs of each component . - True measure of a successful program for the GBT
- Competitive instrumentation installed on short
time scales and in production use by external
observers.
4Instrument Development Realities
- GBT Spectrometer
- 5 year development time with an additional 5
year integration time. - Finally debugged August 2007
- Ka-band Receiver
- Extensive refurbishments required for each of
three successive observing seasons - HARP/ACSIS FPA program on JCMT
- HARP 16 pixel 345GHz frontend
- ACSIS 16 x 2 x 1GHz spectrometer backend
- Similar specifications and logistical challenges
to our proposed system - 10 year development time
- IF distribution became critical path item
- Commissioning FE/IF/BE simultaneously is
enormously complicated! - Solution
- Select challenging but realistic component
deliverables. - Develop on 1-2 year timescales.
5Development Path 1st Step
- Frequency Selection
- ? lt K-band physically too large for Gregorian
focus (needs beam-forming array at prime focus). - ? Q, W-band existing IF capacity inadequate
upgrade path unknown. - ? Q, W-band telescope performance still under
development (should be delivered on 2-3 year
timescales, but not a given). - ? W-band significant detector and other RD
development required. - Where is GBT Unique?
6K-Band Advantages
- A scientifically exciting but technically
realistic focal plane array. - Can do production science with existing IF system
and spectrometer. - Parallel and collaborative spectrometer
developments possible but not critical. - Realize cost savings and enhanced performance for
future expansion of instrument.
7K-Band Advantages
- Develop on 1-2 year timescales
- Integrate each new component into the production
system to allow immediate, productive astronomy. - Technical staff available for two years and ready
to begin. - Frontend minimal RD effort required.
- Current capability to demonstrate a prototype
within one year. - Concurrent software development with a usable
instrument within 2 years.
8K-band FPA Deliverables
- Frontend
- Cryogenic Package
- Modular Downconverter
- Modular Noise Calibration
- Mechanical Packaging
- Software
- Package for Engineering and MC
- Package for data analysis
9Future FPA Developments
- Significantly enhanced spectrometer with this new
array and existing IF system. - New digital I.F. distribution system.
- Expanded focal plane array (perhaps at a
different frequency) - Phased, expandable software development to match
hardware capabilities.
10Spectrometer
- We have a new approach CICADA program
- Configurable Instrument Collaboration for Agile
Data Acquistion - Collaboration between GB, CDL, UC Berkeley CASPER
group, WVU, University of Cincinnati, others - Initial production instrument pulsar backend
(Scotts Dream Machine") - Design of a 2GHz bandwidth spectrometer already
identified as a deliverable for FY2008 - Construction could commence in FY2009 given
resources - Excellent candidate for external funding
- Correct technology area (innovative hardware /
networking / computing) - University collaborations
- gt prototype backends are under development
new Spectrometer development should start in
Fy2009
11IF System
- Current analog IF system limits expansion.
- Analog modulators costly with increased
complexity due to stability requirements. - Downconversion scheme limits bandwidth
- Digitization at antenna with filtering/compression
schemes probable solution for IF transmission. - Commerical technology advancements in digital
transmission reduces cost and increases
performance. - Development in this area is extremely active,
driven by SKA and SKA-pathfinder initiatives
12Software
- Similar systems do exist at other telescopes.
- Challenge in software is to transfer approach or
actual implementation to your specific telescope. - We will certainly leverage work done elsewhere,
and collaborate with other groups. - Using existing GBT Spectrometer makes problem
much more tractable (many GBT-specifics already
solved). - gt Software development is an integral part of
FPA program addressed early in the project.
13 Development Path Summary
- Processing software issues well understood
- Backend current system can accommodate a modest
array (at K-band), issues and upgrade path well
understood. - I.F. system current system can accommodate
modest array, upgrades premature at this time - Frontend Proposed K-band.
- A pathfinder focal plane array (FPA) frontend is
the necessary first step in an integrated
development program.
14K-band FPA Summary
- K-band is the appropriate frequency.
- We have the necessary resources and expertise (,
more importantly appropriate staff effort) ready
and eager to go. - We need to start now to demonstrate results
within 2 years (production use in 3 years)
15Backup Slides
Backend Data Transmission System Telescope
Performance Weather
16Backend Strawman Design
- Strawman Specifications
- 3 GHz analog bandwidth
- 6 GS/s
- 8 bit ADC, 6 bit ENOB
- 183 KHz resolution_at_ 3 GHz bandwidth (16K
channels) - 80 millisecond minimum integration time
- 200 MB/s aggregate data rate to disk for 122 IF
channels
17Backend Strawman Design
- Technology Approach
- Off the shelf ADC chips
- FPGA DSP hardware
- Off the shelf Data Collection Computer Systems
- Optional locations
- Receiver room
- Equipment room
18Backend Strawman Design
- Cost
- 20K/pixel sampler and DSP costs(2 channels)
- 2.44M for 61 pixels, scales linearly with
pixels - 30K Data collection and storage computers
- 70K data transmission to disks (all DSP at front
end) - 6 FTE-years effort (3 people, 2 years)
- Total 3.3 million.
19Data Transmission Systems
- EVLA and ALMA Data Transmission Systems are not
appropriate - GBT needs 4 bit samplers
- EVLA 3 bits
- ALMA 2 bits
- ALMA and EVLA multiplexing too complex and
expensive for GBT - gt Advantages in allowing technology to develop.
20Telescope Performance
21Azimuth Track Replacement Project
- Field work completed on Monday 3rd September to
specification, on schedule and within budget - Now in the process of developing new pointing
model initial results extremely promising.
Local tilt (pitch) of the antenna as measured by
inclinometers mounted on the elevation axle. Both
large and small scale track effects are
significantly reduced.
Very first observation after outage complete.
Measured pointing offsets (3, 1.5) in (az,el).
2214GHz half-power track
23Surface Performance
- OOF technique can easily measure large-scale
wavefront errors with accuracy 100µm - Large scale gravitational errors corrected via
OOF look-up table - Benign night-time rms
- 350µm
- Efficiencies
- 43 GHz ?S 0.67 ?A 0.47
- 90 GHz ?S 0.2 ?A 0.15
- Now dominated by panel-panel errors (night-time),
thermal gradients (day-time)
24Summary Current Performance
25Weather
26(excellent)
Atmospheric Absorption and Emission
(mediocre)
- lowers the SNR ? exp(-?) / Tsys
Slide Courtesy Jim Condon
27Observing Limits (accept/reject)
- Atmospheric efficiency
- Atmospheric stability
- Absolute hour angle
- Zenith angle lt 85 deg
- Tracking flux error lt 10
Atmospheric efficiency
Slide Courtesy Jim Condon
28Stringency ? 1 / (fraction of time OK)
- Stringency measures the difficulty of
scheduling an observation on the GBT. It depends
strongly on the observing frequency ? and also on
the source elevation at transit.
Slide Courtesy Jim Condon