Chenab Railway Bridge - PowerPoint PPT Presentation

About This Presentation
Title:

Chenab Railway Bridge

Description:

A brief Presentation on World Tallest Railway bridge, Chanb Railway bridge, an Marvel of India – PowerPoint PPT presentation

Number of Views:95
Slides: 13
Provided by: Nbag877
Tags:

less

Transcript and Presenter's Notes

Title: Chenab Railway Bridge


1
A PRESENTATION BY NILANJAN BAG
2
  • CONTENT
  • BASIC INFORMATION
  • IMPORTANT FACTS
  • DESIGN OF BRIDGE
  • GEOLOGY
  • CONSTRUCTION
  • STEEL AND CONCRETE DETAILS
  • CONCLUSION

3
  • BASIC INFORMATIONS
  • SITUATED IN REASI DISTRICT OF JAMMU KASHMIR
  • DESIGN ARCH BRIDGE
  • MATERIAL USED STEEL CONCRETE
  • TOTAL LENGTH 1315 METER
  • ARCH LENGTH 480
  • LONGEST SPAN 467 METER
  • ARCH SPAN 467 METER
  • NUMBER OF SPANS 17
  • HEIGHT 359 METER RIVER BED TO FORMATION

4
  • IMPORTANT FACTS
  • OFFICIAL PROJECT NAME DESIGN CONSTRUCTION OF
    SPECIAL BRIDGE ACROSS THE RIVER CHENAB AT 50/800
    ON THE KATRA-LAOLE SECTION OF THE UDHAMPUR
    SRINAGAR BARAMULLA RAIL LINK PROJECT
  • THE CLIENT KONKAN RAILWAY CORPORATION LTD,
    INDIA
  • THE CONSTRUCTER AFCONS INFRASTRUCTURE LTD,
    INDIA
  • ARCHITECT WSP IN FINLAND WITH SUBCONSULTANT
    LEONHARDT, ANDRA UND PARTNER, GERMANY
  • BRIDGE DECK CARRIES TWO RAILWAY TRACKS AND DRDO
    MAKES IT WORLD FIRST BLAST-PROOF RAILWAY BRIDGE
  • ITS HEIGHT, ALMOST 29 METER MORE THAN EIFFEL
    TOWER (330 METER), MAKES IT THE WORLD HIGHEST
    RAILWAY BRIDGE AND TOTAL COST IS AROUND 1486
    CRORE AFTER COMPLETION

5
- AS MANY AS 3200 PEOPLE WORKED ON CONSTRUCTION
OF THIS CHALLENGING ICONIC BRIDGE TO MAKE IT ONE
OF A MARVEL OF INDIA
6
  • DESIGN OF BRIDGE
  • THE DESIGN SPEED OF RAILWAY OS SET TO BE 100 KM/H
  • WIND LOAD CORRESPONDS TO MAXIMUM WIND PRESSURE OF
    1500 PASCAL AND WIND SPEED UP TO 266 KMPH
  • THE BRIDGE IS DESIGNED TO WITHSTAND EARTHQUAKE
    FORCES OF THE HIGHEST INTENSITY ZONE-V MAGNETUDE
    8
  • THE DESIGN LIFE OF THE BRIDGE SHOULD BE 120 YEARS
  • FATIGUE ASSESMENT HAS TO BE DONE AS PER BS5400
    PART 10
  • THE SUPERSTRUCTURE IS A PLATE GIRDER WITH A
    CLOSED DECK, WHERE RAILS ARE CONNECTED
  • THE CLOSED DECK KEEPS THE RAINWATER OUT AND
    PROVIDES MOSTLY DRY ENVIRONMENT BELOW THE DECK

7
  • GEOLOGY
  • THE CHENAB BRIDGE IS LOCATED IN THE TRICKIEST
    SECTION OF THE JAMMUUDHAMPURSRINAGARBARAMULLA
    RAIL ROUTE, WHERE THE TYPICAL GEOLOGY CONSISTS OF
    YOUNG HIMALAYAN ROCK
  • THE SITE COMPRISES OF SHIWALIKS AND PRETERTIARY
    ROCKS AND THE MAIN SUB-TYPE OF ROCKS COMPRISES OF
    DOLOMITE AND LIMESTONE
  • SOME OF PIER LOCATIONS COMPRISE QUARTZITE AND
    SHALE ROCKS AND THERE IS NO SIGNIFICANT SHEAR
    ZONES OR CAVITIES IN BOTH THE ABUTMENTS
  • TOP LAYERS OF THE ROCKS AT ABUTMENTS ARE HIGHLY
    FRACTURED AND REPRESENT A BLOCKY MASS
  • HOWEVER, THE BOTTOM LAYERS OF ROCKS ARE STABLE
    AND STRONG ENOUGH FOR A GOOD FOUNDATION

8
  • CONSTRUCTION
  • FIRSTLY, THE FOUNDATION AND SLOPE STABILIZATION
    WORKS ARE STARTED AND A TOTAL OF 18 PIERS WERE
    CONSTRUCTED
  • AFTER ERECTION OF THE MAIN PIERS BY CABLE CRANE ,
    THE DECK IS LAUNCHED UP THE AXES OF SUPPORT S40
    AND S50
  • THE DERRICK CRANE IS PLACED ON TOP OF THE DECK TO
    LOWER THE ARCH SEGMENTS FROM DECK LEVEL TO THE
    ERECTION FRONT OF THE ARCH
  • THE ERECTION PROCESS OF THE DECK AND THE ARCH
    PROCEEDS SIMULTANEOUSLY UP TO A MAXIMUM CANTILEVR
    LENGTH OF 48 METER
  • WHEN THE NEXT ARCH PIER SUPPORT WOULD BE REACHED,
    TEMPORARY CABLES SET UP TO SUPPORT CONSTRUCTED
    ARCH

9
  • STRUCTURAL PLAN OF THE CHENAB BRIDGE
  • USE OF DERRICK AND CABLE CRANE IN ARCH
    CONSTRUCTION

10
  • AFTER THAT, THE NEW ARCH PIER IS CONSTRUCTED
    USING CABLE CRANES ON THE FREE END AND THIS
    PROCESS IS CONTINUED UNTILL THE LAST PIER OF ARCH
    IS CONSTRUCTED
  • THE SUPERSTRUCTURE AND THE ARCH WILL BRIEFLY FORM
    A TRUSS GIRDER, CANTILEVERING OUT FROM ARCH
    ABUTMENT
  • THE FINAL SEGMENT OF THE ARCH IS CONSTRUCTED
    USING A CABLE CRANE AND TWO HALVES OF THE ARCH IS
    ADJUSTED USING HYDRAULIC JACKS BEFORE THE FINAL
    CONNECTION
  • FINALLY, THE TEMPORARY CABLES ARE REMOVED AND THE
    FINAL CONNECTIONS WILL BE MADE

11
  • STEEL CONCRETE DETAILS
  • TEKLA SOFTWARE IS EMPLOYED FOR DETAILING USING
    STRUCTURAL STEEL SUITABLE FOR -20C TO 40C
  • CONSTRUCTION OF THE BRIDGE REQUIRED 25000 TON OF
    STEEL 4000 TON OF REINFORCED STEEL AND TO
    ENHANCE SAFETY SECURITY, THE BRIDGE IS MADE OF
    63MM-THICK SPECIAL BLAST-PROOF STEEL
  • TOTAL OF 46000m3 CONCRETE WAS REQUIRED AND THE
    MAIN CHORD MEMBERS WERE FILLED WITH SELF
    COMPACTING CONCRETE FOR ENHANCING OVERALL
    STIFFNESS AND ROBUSTNESS
  • BOTH ENDS OF THE BRIDGE HAS BEEN CONNECTED WITH
    THE HELP OF HIGH STRENGTH FRICTION GRIP (HSFG)
    BOLTS AND IT IS MARKED AS GOLDEN JOINT
  • EIGHT MILLION CUBIC METRES OF EXCAVATION WAS DONE
    AND THE BRIDGE WILL BE PAINTED WITH A SPECIAL
    CORROSION-RESISTANT PAINT, WHICH LASTS FOR 15
    YEARS

12
  • CONCLUSION
  • THE BRIDGE WAS CONSTRUCTED IN ONE OF THE MOST
    COMPLICATED AND ISOLATED TERRAINS. ONE OF THE
    BIGGEST CHALLENGES INVOLVED WAS CONSTRUCTION OF
    BRIDGE WITHOUT OBSTRUCTING THE FLOW OF CHENAB
    RIVER.
  • THE PROJECT WAS APPROVED IN
    DECEMBER 2003 AND AFTER 18 YEARS THE BRIDGE WAS
    COMPLETED AND INAUGURATED ON 13TH AUGUST 2022.
    LAYING OF RAILWAY TRACKS WAS STARTED IN FEBRUARY
    2023 AND THE BRIDGE ALONG WITH THE ENTIRE ROUTE
    IS EXPECTED TO BECOME OPERATIONAL BY THE JANUARY
    2024.
  • THE BRIDGE WILL SURELY BOOST THE REGIONS
    INDUSTRIAL AND AGRICULTURAL SECTORS BY ALLOWING
    ALLWEATHER CONNECTIVITY BETWEEN THE VALLY AND
    REST OF INDIA.

REFERENCE 1. theconstructor.org
2. seminarsonly.com
3. wsp.com
Write a Comment
User Comments (0)
About PowerShow.com