OptiSurface - Optimum Surface Landforming PowerPoint PPT Presentation

presentation player overlay
About This Presentation
Transcript and Presenter's Notes

Title: OptiSurface - Optimum Surface Landforming


1
By
Graeme Cox BEng (Ag) PhD
Dave Cox Farmer
2
Evolution of Landforming
  • We have been landforming since agriculture began

3
Evolution of Landforming
  • 1900s Dumpy Stakes
  • 1970s Laserplane
  • 1990s Multiplane
  • 2000s OptiSurface

Patent Pending
4
Evolution of Landforming
  • 1900s Dumpy Stakes
  • 1970s Laserplane
  • 1990s Multiplane
  • 2000s OptiSurface

Patent Pending
5
Evolution of Landforming
  • 1900s Dumpy Stakes
  • 1970s Laserplane
  • 1990s Multiplane
  • 2000s OptiSurface

Patent Pending
6
Evolution of Landforming
  • 1900s Dumpy Stakes
  • 1970s Laserplane
  • 1990s Multiplane
  • 2000s OptiSurface

Patent Pending
7
Benefits of Landforming
  • Higher Yields, Quality and Profit through
  • Minimised water logging
  • Improve infiltration uniformity
  • Sooner trafficability
  • Improved crop establishment
  • Improved uniformity of crop maturity
  • Reduced weed problems

8
OptiSurface Landforming
provides all of the benefits of traditional
laser landforming only
  • MUCH BETTER!!
  • Much cheaper (up to 80)
  • Much less topsoil removal
  • Much faster

9
Case Study C7
  • Block C7 Area 92 Ha
  • Location DAVCO Farming, Burdekin
  • Row Cropping (sugar cane)
  • Lateral Move Irrigation

10
Existing Topography
Note vertical scale exaggerated x 100
C7
11
Plane of Best Fit
C7
12
Plane of Best Fit - Cut\Fill Map
C7
Cut 791m3/ha Cost 1,190/ha Max Cut 0.350m
13
OptiSurface Design Constraints
Minimum Downslope 1
900
0.111
Maximum Downslope 1
300
0.333
Max. Downslope change 1
4000
0.025
Minimum Cross-slope 1
-200
-0.500
Maximum Cross-slope 1
200
0.500
Max. Cross-slope change 1
1000
0.100
14
OptiSurface Design
C7
15
OptiSurface - Cut\Fill Map
C7
Cut 180m3/ha Cost 270/ha Max Cut 0.270m
16
Long Section Plot
Long section plot
Downslope 0.111 to 0.333
C7
17
Long Section Plot
Downslope 0.050 to 1.000
C7
18
OptiSurface - Downslope Map
C7
19
Runoff Velocity Map
FLOW DIRECTION
C7
Rainfall 75mm/hr Max Velocity 0.44m/s
20
Runoff Depth Map
FLOW DIRECTION
C7
Rainfall 75mm/hr Infiltration0mm Max Depth
0.170m
21
OptiSurface - Downslope Map
C7
22
Design Surface Options
  • OptiSurface 1D
  • Row drainage in one direction only
  • OptiSurface 2D
  • Row drainage in two directions
  • OptiSurface 4D
  • Can drain in any direction as long as it leaves
    the field

23
Case Study C8 Existing
LS2
LS1
C8
24
OptiSurface 2D Design
LS2
LS1
C8
25
Long Section 1
C8
26
OptiSurface 4D Design
C8
27
OptiSurface 4D Existing
C8
28
Contact Us
  • Contact us for a FREE Design
  • Phone 61 7 4782 7575 (international)
  • (07) 47827575 (Australia)
  • Email support_at_optisurface.com
  • Visit www.optisurface.com