Title: Necsa presentation to Portfolio Committee on Minerals and Energy
1Necsa presentation to Portfolio Committee on
Minerals and Energy
- 25 May 2005
- Presented by
- Dr. van Zyl de Villiers
2Contents
- Instrument calibration facility
- HSE management processes
- Performance w.r.t. radiation exposure
- Requests for medical information
3Necsa calibration facilityfor radiometric
instruments
4Sequence of events
- Earthlife Africa (ELA) inspected site on 23 April
2005 without knowledge to Necsa - 26 April 0900 Necsa informed by NNR of ELAs
intention to hold press release at a secret
nuclear waste dump - ELA, press and NNR representative arrived at site
at about 1200 - Appeared in news since that afternoon.
- Earthlife claimed dose rate levels of between 20
30 µSv/h on site - Necsa provided NNR with preliminary statement
based on information then available
5Sequence of events (cont.)
- During evening of 26 April NNR requested Necsa to
verify measurements taken by ELA - Measured levels ranging from natural background
to a maximum of 27 µSv/h (Thorium slab 1) - 27 April NNR visited site
- Requested that site be secured gate locked
immediately and full-time security guard placed
on site - NNR issued letter to Necsa requesting some
actions, e.g. signposting, securing area,
reporting as a nuclear occurrence and a detailed
report - to be complied with by 29 April
6Sequence of events (cont.)
- DME requested summary report evening of 27 April
and extended report by 800 on 28 April - Meeting between DME, Necsa and NNR held at DME
offices at 1100 on 28 April - Decision to investigate existence of other
similar sites and to talk to media - Necsa Corporate Communication had numerous
telephonic and TV interviews 28 29 April
7Background on the calibration site
- Upsurge in uranium exploration during 1970s
created need for standardization and calibration
of radiometric field instruments - Facility built 1972 and upgraded 1979
- 11 flat-circular concrete slabs (2 meters in
diameter and 300mm thick) and 2 borehole type
facilities containing known amounts of uranium,
thorium and potassium
8Background (cont.)
- Used for calibration of field spectrometers for
quantitative in-situ determination of U, Th and
K as well as for accurate calibration of well
logging equipment - Naturally occurring ores incorporated
homogeneously and immobilized into concrete
matrices - Radioactive material not processed but in form as
it occurs in nature (to simulate typical ore
bodies)
9Background (cont.)
- Facility extensively used by many organizations
and companies, but diminished since late 1980s - Situated on Necsa property
- Borders minor gravel road about 600m from main
road - Site was chosen due to low natural background
levels and to allow easy access for external users
10Status of Site
- Identified as zone with elevated radiation levels
on Necsa site included in list of current
operating and shut-down nuclear facilities
submitted to NNR - Passively safe
- Inadvertent exposure controlled by locked gate
and cattle fence locked steel covers over slabs - Security inspection on 15 April 2005 found lock
and signposting in order
11Radiological risk
- Prevailing dose rates between background levels
and maximum contact dose rate of 27 µSv/h - Levels above background only detectable 3 m from
uranium and thorium pads with highest levels - Maximum ambient dose rate 1 µSv/h in area, i.e.
250 hours to be spent in area before reaching
public dose limit of 250 µSv/a - Because of remoteness and infrequent use credible
exposure scenarios will present much lower
exposures to individuals, which will not result
in any detrimental health effects
12Corrective actions
- Immediate replacement of lock on gate
- Replacement of proper signposting
- Erection of proper security fence (full-time
security until completion of fence) - Inspection of site by Necsa security staff during
each shift - Establish need for further use of site within 6
months rehabilitate if no need is identified
13 - Overview of Necsas HSE management processes
14ACTS STANDARDS (SANS) IAEA/ICRP PERMITS/
LICENCE NECSA POLICIES AND HSE MANAGEMENT
PRINCIPLES
LEGISLATION AND SOUND MANAGEMENT PRINCIPLES
HSE SYSTEM
150 DOCUMENTS 10 CHAPTERS
15HSE SYSTEM
150 SYSTEM DOCUMENTS
HSE CHANGE MANAGEMENT PROCESS INCL PROJECT
APPROVAL
PREMISES AND HOUSEKEEPING
BEHAVIOURAL BASED SAFETY (BBS) PROCESS
MECHANICAL, ELECTRICAL AND PERSONAL PROTECTION/
SAFEGUARING
RADIATION PROTECTION PROGRAMME
10 CHAPTERS
FIRE PREVENTION AND PROTECTION AND EMERGENCY
PLANNING
HAZARDOUS CHEMICAL SUBSTANCE CONTROL PROGRAMME
COMPLIANCE ASSURANCE PROCESS
ENVIRONMENTAL MANAGEMENT
SAFETY ORGANIZATION
16EXTERNAL AND INTERNAL INSPECTIONS AND AUDITS
- HSED AUDITORS INTERNAL AUDITS
- HSED ISO 9000 2000 CERTIFIED
- EXTERNAL AUDITS
- NOSA
- NATIONAL NUCLEAR REGULATOR
- SABS
- CONSULTANTS
- APPROVED INSPECTION AUTHORITIES
17 - Necsas performance regarding worker radiation
exposure
18Terminology
- The strength of a radioactive source is called
its - activity, which is measured in becquerels (Bq).
- A becquerel is one disintegration per second.
- The measure of the biological effect of radiation
on a human is called dose and is measured in
sievert (Sv). - (1 Sv 1000 mSv 1 000 000 µSv)
19Public dose limit and constraints(µSv/a
microsieverts per annum)
50 µSv/a ALARA margin
2400 µSv/a (Average dose from background)
50 µSv/a Air pathway
Average actual Necsa public dose (0.8 of nat.
background)
International recommended public dose limit
150 µSv/a Water pathway
Necsa public dose limit
1000 µSv/a
250 µSv/a
20 µSv/a
20Worker dose limits (mSv/a millisieverts per
annum)
International recommended worker dose limit
20 mSv/a (averaged over 5y Not more that 50
mSv/a)
Average Necsa radiation worker dose
lt 1mSv/a
21(No Transcript)
22(No Transcript)
23(No Transcript)
24 - Requests for medical information
25Requests for medical records
- No claims received i.t.o.
- NNR Act (47 of 1999)
- COID Act (130 of 1993)
- Only requests for information i.t.o.
- Promotion of Access to Information Act (2 of
2000)
26Requests for medical records (cont.)
- Number of requests received via Earthlife Africa
173 - - Number of files submitted to ELA 22 (only
medical files as per initial information
requested) - - Number of requestors that were registered as
radiation workers 63 (36) - - Number of individuals that could to date not be
identified as former Necsa employees 33 (19)
27INITIAL REQUEST FOR INFORMATION
28LATEST REQUEST FOR INFORMATION
29Challenges
- Promotion of Access to Information Act (Act 2 of
2000) was promulgated in 2000. Records requested
are for periods before 2000 (e.g. 1970 1984). - Information is available but not readily
retrievable because it is held in different
systems at Necsa, e.g. - Medical information
- Dosimetry and biological monitoring results
- Facilities surveillance data
- Human resources information
- Incident reports
30Challenges (cont.)
- Personal information is sometimes inadequate to
uniquely identify the individuals. - Legal requirements for retention periods of
records differ, e.g. - Workers compensation 3 years
- Medical history 40 years
- Incident reports 3 years
- Human resources 7 years
31Necsa actions
- The Necsa Board of Directors is setting up an
independent task team to investigate allegations
by ELA and former employees. - A task team has been established to compile the
medical records of current and previous employees
(ca. 25 000) to combine all medical related
information. - Modification of the database of medical exposures
to identify record items available and not
available (for previous employees). Records not
available for current staff will be established
where possible (e.g. where a baseline medical was
not performed) (June 2005).
32Necsa actions (cont.)
- A system will be developed and implemented to
identify individuals not fully participating in
the health care programme (June 2005). - Health Hazard Identification and Risk Assessments
(HIRA) will be reviewed for all facilities (July
2006). - Workplace and medical surveillance programmes
(including dosimetry and biological monitoring)
will be adapted, where necessary, in accordance
with the HIRA (September 2006).
33Case study An investigation into the health of
US nuclear workers
- Investigation of 53,000 US nuclear industry
workers from 15 nuclear utilities between 1979
and 1997. - Mortality rates of these workers 60 lower than
comparable US mortality rates for general
population similar in terms of age and gender. - Ascribed to the healthy worker effect
34Thank you very much!