Title: Regional Transmission Expansion Plan Massachusetts Electric Restructuring Roundtable October 28, 200
1Regional Transmission Expansion
PlanMassachusetts Electric Restructuring
RoundtableOctober 28, 2004
- Jimmy Cross
- Vice President System Planning
- ISO New England
2About ISO New England
- Private, not-for-profit corporation created in
1997 to oversee New Englands deregulated
electric power system - Regulated by the Federal Energy Regulatory
Commission (FERC) - Independent of companies doing business in the
market - Independent board of directors, with no financial
stake in regional energy firms - Approximately 400 employees headquartered in
Holyoke, MA
3Planning Process
- ISO Role in Restructured Electric Industry
- Provide independent assessment of bulk power
system needs - FERC granted ISO sole authority to lead planning
effort (2000) - Stakeholder input from Transmission Expansion
Advisory Committee - Regional Transmission Expansion Plan for 2004
- The most comprehensive planning effort to date to
ensure system reliability and promote market
efficiency - RTEP04 constitutes a regional system plan
- Objectives
- Identify system needs
- Provide information to the marketplace to attract
generation, merchant transmission, and
demand-response solutions - Identify regulated transmission solutions as a
backstop for reliability
4Planning Process
New Generation
Retirements/Deactivations
Planning is Ongoing
Transmission Projects
Load Forecast
Demand-Side Management
Demand Response Program
5Reliability Concern in Load Pockets
- Areas with limited import capability and local
generation - Southwest Connecticut
- Connecticut
- Boston
- Northwest Vermont
- Timely completion of 345 kV transmission upgrades
to these areas is essential to address
reliability concerns and to allow needed
development of new resources. - Even with new 345 kV transmission, only a limited
time for re-powering or developing new resources
will exist. - Market incentives are needed to promote
development of new resources.
6System-Wide Resource Reliability
- Present capacity surplus will be short-lived.
- New England supply outlook shifts from tight to
deficit conditions in two to four years. - Some generation units needed for system
reliability are at risk. - Potential retirements/deactivations include units
in critical load pockets.
7System-Wide Resource Reliability, cont.
- New England is heavily dependent on gas-fired
generation. - The 9,500 MW of capacity added since 1999 is
largely gas-fired. - Approx. 11,500 MW of capacity is now capable of
burning gas as a primary fuel. - Poses major concerns for unit availability during
winter periods. - Region is vulnerable to price fluctuation,
delivery constraints and competing demands for
natural gas. - Cold Snap initiatives are underway to improve
unit availability, and thus system reliability,
during winter season.
8New Englands Capacity Situation Todays surplus
capacity situation will be short-lived
9Transmission Projects
- Progress in Several Areas Since RTEP03
- Projects placed in service since RTEP03 25
- Total New RTEP04 projects 39
- Total RTEP04 projects needed for reliability
246 - Major 345 kV Projects (Estimated costs)
- Southwest Connecticut Reliability Project (890M)
- Southern New England Reinforcement Project
(125M) - NSTAR 345kV Transmission Reliability Project
(217M) - Northwest Vermont Reliability Project (156.3M)
- Northeast Reliability Interconnect Project
(90.4M) - Subtotal approximately 1.5 billion
- Remaining RTEP04 Projects approximately 0.6
billion - 2004 Transmission System Project Plan Grand
Total 2.1 billion - Additional equipment or expense may be required
for underground design.
10Market Information
- New England needs a capacity market that
appropriately values the location of resources. - RTEP04 provides historical market information and
economic assessments of the system in the future. - Congestion component of energy pricing has been
low.
11Conclusions
- Reliability is at risk in Southwestern
Connecticut, the State of Connecticut, Northwest
Vermont and Boston. - Problems in these areas could adversely impact
the regional bulk power system. - Resource reliability could become a major
system-wide issue for New England in two to four
years. - Timely completion of transmission projects is
critical. - Delays exacerbate reliability problems.
- Implementation of actions identified in RTEP04
and enhancements to the market design are needed
to address New Englands reliability concerns.
12Questions?
13Backup material
14Connecticut Capacity Situation
15Southwest Connecticut Capacity Situation
16Post-Contingency ViolationsCurrent System
Thermal Overloads