TRT Barrel assembly - PowerPoint PPT Presentation

About This Presentation
Title:

TRT Barrel assembly

Description:

Active gas fittings, custom made for each module: connection & leak test ... Parts, procedures, and drawings are in good shape ... – PowerPoint PPT presentation

Number of Views:92
Avg rating:3.0/5.0
Slides: 19
Provided by: atlasP
Category:
Tags: trt | assembly | barrel

less

Transcript and Presenter's Notes

Title: TRT Barrel assembly


1
  • TRT Barrel assembly
  • status schedule
  • Feb. 9, 2005

2
All modules installed!
Feb. 3, 2005
3
Snap shot
  • Feb. 8 snap shot
  • Type 1
  • All modules installed tested
  • All electronics installed
  • 20 modules cooling tube installed
  • Type 2
  • All modules installed tested
  • 18 side A electronics installed
  • Type 3
  • All modules installed
  • 28 modules with protection boards and tested

Feb. 06, 2005
4
Module installation time line
30 module mounting days
5
Module placement
  • Final dead wire distribution
  • Type 1
  • 123.5 1.17
  • Type 2
  • 1210.73
  • Type 3
  • 572.52.26

6
Final dead wire distribution
  • Whole barrel
  • 817 1.55

7
  • Mechanical Assembly Processes

8
Module preparation (done, except for spares)
  • Capacitor installation (1-2 days/module)
  • Insert capacitors
  • Check capacitor connectivity
  • Check HV traces
  • HV test caps wires
  • Seal capacitors
  • Pre-insertion prep.
  • (6 modules/day/2 person)
  • Check ground wire
  • Check cooling sleeve
  • Check mounting holes
  • Active gas fittings, custom made for each module
    connection leak test
  • Glue purging gas gasket
  • Tape HV kapton for protection
  • Glue thermal sensors as needed (4 modules each
    type)

9
Module installation tests (4 last modules)
  • Procedures tests
  • Fold HV kapton and cover with protection plates
  • Insert module fix one corner
  • Set module z position to middle of BSS
  • Fix module 2nd corner attach set screws
  • Check purging gas flow
  • Type 1 1.5 L/min lt 10 loss
  • Type 12 1.5 L/min lt 15 loss
  • Type 123 0.5 L/min lt 20 loss
  • Unfold HV kapton check HV traces
  • Attach glue active gas fittings
  • Plug seal unused active gas inlets.
  • Leak test active gas volume (1mB/B/min)
  • Install protection boards
  • HV test with Ar-CO2
  • Check active gas path for obstruction (flow rate
    test)

10
Cooling lines installation (on going)
  • After the electronics have been
  • Installed
  • Continuity check
  • Noise check
  • The cooling lines are
  • inserted through both corners of the module
  • 90 bend forced on one end
  • Attachment to cooling plate at each end.
  • (T1 20 modules)
  • Cooling flow measurement is made.
  • (T1- 20 modules)

11
Module repairs modifications
  • Module repair
  • Wire removal (2 bad wires some retroactive
    decisions from acceptance group)
  • HV trace broken, shares from neighboring line (1)
  • Cooling sleeve replacement (4)
  • Three wires removed from BSS. (2 drawing excess
    current, 1 shorted).
  • Two modules (T1) show a connection between 2
    signal wires (double joints) at one end. Left for
    now.
  • Components modification
  • Peek tubes for module cooling reduced from
    0.123-0.127 ? 0.116-0.120 (done)
  • Fuse box brackets dimension change
  • Fuse box screws changed from Nylon to Ultem
  • CO2 flushing tube redesigned with corrigated
    PEEK.
  • De-magnetized stainless steel screws for active
    gas inlet plugs (started from type 2 modules)

12
Remaining mechanical work
  • Finish testing the last 4 type 3 modules (1week)
  • Continue to install module cooling tubes as
    electronics are installed
  • Install outer cylinder
  • After all modules are tested ( March, 1week)
  • Before manifold can be installed
  • Install services after electronics are installed
  • Cooling manifold (contract, deliver April)
  • Active gas manifold (drawing/review this week)
  • Purging gas manifold (parts)
  • Install fuse boxes
  • Need to solve fuse problem and resume production
  • 3 possible windows for installation (in
    descending preferences)
  • Before TRT/SCT system test Oct.
  • Before going in the pit Feb. 06
  • In the pit, same time as harness or before (?)
  • MTF migration Data base structure defined,
    entering data.

13
Electronics installation
  • Type 1
  • Completed Jan. 24, 2005
  • Type 2
  • Side A (2B) 18 modules installed
  • 22 boards in repair process, 10 finished
  • Side C (2F) started stuffing at ACAMAS. Should
    have pre-series at CERN end of Feb.
  • Type 3
  • Side A (3B) Pre-series at CERN and tested.
    Feedback to ACAMAS. No known issue.
  • Side C (3F) All bare board received. Need to
    start pre-series.

14
Electronics schedule
  • 3B will be the next to arrive (followed by 2F and
    3F) and available for installation April 11.
  • After that we will be saturated with boards.
  • Installation is the slowest part.
  • 3 weeks per side for type 2
  • 1 month per side for type 3
  • Will need to run more than one shift to finish
    installation in June.

15
Services Manifolds
16
Sector Tests
17
Current Integration Schedule
18
Summary
  • All modules installed!
  • Electronics installation is well under way.
  • All type 1 installed
  • gt1/4 type 2 installed.
  • Parts, procedures, and drawings are in good shape
  • Manifolds could cause delays and need to be
    carefully followed.
  • Active Roof Boards remain the critical path and
    need to be carefully followed
  • Fuse problem need to be solved
Write a Comment
User Comments (0)
About PowerShow.com