Section 1 Overview and SC Status - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Section 1 Overview and SC Status

Description:

MOC SIMs Days 1 and 2 (twice) RCS Leak Test. Photo/Closeouts. Red Tags. 5/18. 5/28 ... Number Closed out = 1020 (96% closure rate) Open Work Orders = 44 (TBR on ... – PowerPoint PPT presentation

Number of Views:38
Avg rating:3.0/5.0
Slides: 16
Provided by: mikecullys
Category:

less

Transcript and Presenter's Notes

Title: Section 1 Overview and SC Status


1
Section 1 Overview Spacecraft Status
. . . Mike Cully Swales Aerospace, Inc.
2
Overview Agenda
  • Scope of Review
  • Test Objectives
  • Spacecraft Status
  • Summary of WOA Problem Reports
  • TV Staffing

3
Scope Of EO-1 Second T/V TRR
  • Demonstrate Readiness of all Subsystems to start
    T/V
  • Status of flight hardware and software
  • Short description of any changes since the last
    thermal vac test
  • Status of open problem reports
  • Trending plans
  • Work required before pump down
  • Status of critical limits in the ASIST database
  • Review of any critical procedure steps
  • Provide Red Team members an intermediate report
    card on EO-1 status
  • To obtain review team concurrence to begin EO-1
    Second T/V

4
Test Objectives
  • Further demonstrate EO-1 Subsystems in Thermal
    Vacuum following significant de-integration
    activities (LVPC Fuse plugs, ACDS, GPS PCU, IRU,
    WARP, AST)
  • Verify post T/V Flight Software Changes at
    operating temperature extremes
  • Increase confidence in hardware/software
    integration by substantially increasing Power on
    time for WARP FSW
  • Perform CPTs at hot and cold plateaus
  • Perform Instrument Turn on Simulation
  • Further characterize ALI Outgassing and validate
    on-orbit procedure
  • Further develop MOC team capability for normal
    operations
  • Verify modifications to heater circuits at system
    level (verification performed at panel level)
  • Perform Spectral Registration Comparison for
    Hyperion LEISA/AC (secondary objective)

5
Major Configuration Changes for T/V2
  • Change to smaller chamber (225) required custom
    designed base plate and new GSE framing for Cryo
    panels and Heater panels
  • Static load test performed of new base plate
  • Fit check performed of frame during chamber
    certification
  • Thermal balance not required. Therefore GSE MLI
    to separate bays not required
  • Minimal changes to cabling with exception to
    extensions for GPS, WARP monitor cable (frequency
    shift anomaly) and new Hyperion/AC Spectral
    Registration Comparison cables. Solar Array HOPS
    GSE cables replaced as result of Fusing changes
  • Use of Hyperion Heater Control GSE to allow
    better control of test heaters

6
(No Transcript)
7
Spacecraft Status
  • Completed Post WARP integration CPT on May 26th
  • CPT went extremely well with minimal issues (AST
    was simulated)
  • Completed Launch simulation Day 1 and Day 2 on
    June 6th
  • Chamber Certification Completed on June 12th
  • Spacecraft on Table, Wednesday June 14th
    (dependant on SADA Cable repair)
  • EGSE to be setup around chamber 225 two days in
    advance of S/C on Table
  • SRC Materials received and in bakeout
  • S/C Roll in projected 6/20/00 (dependant on SADA
    Cable repair)
  • Start compress following completion of Functional
    (12 hours) CPT0 (4 hours)

8
Pre-T/V II Activities
9
(No Transcript)
10
This page intentionally left blank
11
WOA Status
  • Spacecraft IT WOA Statistics
  • Total number generated as 3/24/98 through 6/9/00
    1064
  • Total number from 3/28/00 (RTR) 112
  • Number Closed out 1020 (96 closure rate)
  • Open Work Orders 44 (TBR on 6/09/00)
  • Work In Process 4
  • Open PRs 16 (6/9/00)
  • Future Work 1
  • In Close Out Process 23

12
Problem Report Status
  • Total number generated from 5/1/98 through 6/9/00
    1619
  • Total number from 3/28/00 (RTR) 47 (closed
    32)
  • Number closed out ITD 1596 (98.6 closure
    rate)
  • Number open 23 (TBR on 6/9/00)
  • Work In Process 10
  • Test verification required 2
  • In Closure Process 8
  • Red Book Items 3
  • WOA 572 One Time Event observed Red Low Limits
    for bus chassis believed to be associated with
    SAS cable problem (GSE)
  • WOA 770-20-3 One Time Event Chassis Current
    during EMC Testing
  • WOA 837-20-1 One Time Event LVPC Current Red Limit

13
Open Problem Reports
14
Solar Array Cable Damage
  • Background
  • During final panel closeout inspections on June 6
    a hair line mark (centered around three o'clock)
    was noticed on the 92 wire bundle that comes out
    of the SADA.
  • The hair line mark was further inspected and
    determined to be a cut of the insulation for
    seven wires. The geometry of the cut indicated a
    razor or sharp object. It must be noted that
    this cut was very difficult to see. The location
    of the cut is approximately 0.75 inches off the
    face of the SADA interface which is approximately
    at the start of the bend radius for the cable
    bundle as it is folded up against the Solar Array
    Yoke. This obviously high stress area.
  • Under higher magnification it was determined that
    at least three wires had copper showing. In
    addition oxidation has occurred indicating the
    damage was done some time ago.

15
Solar Array Cable Damage
  • Background Continued
  • All seven wires were verified as
    followsgtConnector Pin Description -
    FunctiongtCable Wrap J2 7 Inboard S/A panel
    structural groundgtCable Wrap J2 37 Circuit 11
    (outboard panel fixed string)gtCable Wrap J2 19
    Circuit 4- (Outboard panel, shuntable)gtCable
    Wrap J2 38 Guard (ground wire shield for
    CSS)gtCable Wrap J2 14 GuardgtCable Wrap J2 42
    GuardgtCable Wrap J2 27 Coarse Sun Sensor 2
  • There is currently 5 spare wires in this cable
    system
Write a Comment
User Comments (0)
About PowerShow.com