Title: BlueOX Energy Management
1Blue-OX Energy Management
- TJ Chancellor
- Paul Cole
- Sara Habib
- Mira Kim
- Claudio Ramos
- Vicente Rosas
2Benzene Hydrogenation Process
3Project 3 Benzene Hydrogenation Process
- Purpose - provide an economic analysis for the
benzene hydrogenation process. - Objectives -
- Estimate the total fixed capital investment
- Estimate the annual product cost.
- Estimate the annual cash flow for the life of the
project. - Report profitability based on ROI, discounted
cash flow, (NPW), and POT. - NPW if products were sold at half or three times
the price of cyclohexane.
4Process Flow Diagram
5Results
6Annual Cash Flow
7Annual Total Product Cost
8Profitability
9Recommendations
- If market value of cyclohexane falls below
2.32/gallon the process should be discontinued.
10Hydrogenation Process Fluid Flow Economics
11Purpose
- Perform sensitivity analysis for the
quantification of risk - Determine the minimum price difference between
the product and raw material - Select material types for different piping
section - Determine pressure drops through the pipe network
in order to determine if more pumps are needed - Perform safety analysis for the suggested pipes
- Suggest insulation material and thickness
- Estimate the Fixed Capital Investment
12Results
13FindingsOptimized Pipe Network Insulation Total
Cost
14FindingsOptimized Pipe Network Insulation Total
Cost Percentage less than the Non-optimized
15Results
- For Non-optimized pipes the minimum price is
1.44 - For the Optimized pipes network the minimum price
drop 4 cents to 1.40 - Pressure Drop around the entire network was found
negligible
16Pressure Drops for Each Stream
17Recommendations
- By using the nominal diameter suggested the
company will save about 200,000 in the capital
investment for the pipes - Blue Ox determine that 2 inches thick rock wool
insulation is the economical optimum - Based on the simulation and calculation the
pressure drop is negligible throughout the pipe
network thus no new pump or compressor is
necessary at this time
18Heat and Material Balances and Pump Analysis
19Heat and Material Balances and Pump Analysis
- Objectives
- solve heat and material balances for the process
from Project 3 - select an appropriate material for the reactor
- determine the work needed at the pump for the
pumping section of the process - suggest a pump type
- create NPSHA vs. flow rate diagram
- system head vs. flow rate diagram
- estimate the Fixed Capital Investment for the
pumping section.
20Results
Heat Balance
21- Material
- Stainless Steel
- Reactor contains Hydrogen at high T and P
- Resistant to corrosion
- Ensures reactor safety longevity
- Pump
- Work Needed 5.06 kW
- Pressure Drop 38 psia
- Discharge Pressure 593 psia
- Type regenerative pump (turbine pump )
22NPSHA and System Head vs. Flow Rate
23Fixed Capital Investment for the pumping section
24Heat Transport Equipment
25Objectives
- Design heat exchanger E1 by hand (using Excel)
and by simulation (using Pro/II). - Choose materials for construction of the heat
exchangers. - Generate T-Q diagrams for each of the heat
exchangers. - Design a distillation column for the process.
26Hand Design
- Double pass heat exchanger.
- Nominal Tube Size ½ inch
- Tube Length 16 feet
- Total Area 2117 ft2
- Fluid Flow Rate 4.73 m3/s
- Tube Side Pressure Drop 1.71 psi
27Simulator Design
- Front End Stationary Head Channel and Removable
Cover - Shell Type Double Pass with Longitudinal Baffle
- Rear End Head U-Tube Bundle
- Shell Inside Diameter 8 inches
- Tubes per Shell 24
- Area 588ft2
28(No Transcript)
29(No Transcript)
30(No Transcript)
31Heat Exchanger Materials
- 304 Stainless Steel was chosen as the material
for construction. - Stainless steel was chosen because of the
corrosive properties of methane and benzene.
32Economics
- Price of a single heat exchanger 12,155
- Purchased Equipment (3 heat exchangers) 36,465
- Fixed Capital Investment 190,530
33Distillation Column
- 28 Trays. 2 feet between trays. 5 feet for the
top and bottom trays. - Column Height 66 feet
- Tray Diameter 93 inches
- Condenser
- Reboiler
- Reflux Ratio 24