B Factory DD Strategy Overview
  • S. Kahn
  • Director, PPA

2
B Factory DD planning status
  • BABAR DD and PEP-II DD are very different
    projects at very different stages of planning and
    maturity
  • BABAR DD has been in preparation for more than a
    year and is relatively mature
  • Funding is in place or planned for project
    execution FY08-FY12
  • Project team is identified, preparatory work has
    begun in IR-2, and first major DD steps are
    about to get underway
  • BABAR DD consists of many one-time dismantling
    steps, with unique tooling and unique in-house
    expertise required
  • Necessitates early dismantling to take advantage
    of existing knowledge base before this disappears
  • Re-use case for components is uncertain, but
    temporary storage of these components while
    issues are resolved is also straightforward

3
B Factory DD planning status
  • Planning for PEP-II DD is just getting underway
    in FY09 at minimal budget levels
  • Project team is not yet identified and limited
    funding exists for project planning in PPA budget
    projections for FY10-FY11
  • Once PEP-II is brought to a minimal maintenance
    state, valuable components can be safely stored
    in the present location
  • No immediate demand for tunnels before PEP-X
    Project
  • Re-use cases do not require components before
    2013
  • Dismantling is largely an industrial operation,
    probably best executed with an outside contractor
  • Large number of repeated operations, with
    existing and routine procedures for handling
    accelerator components
  • In-house knowledge continues to reside within
    Accelerator Systems and ETS Divisions
  • Storing components on-site in light of the metals
    suspension requires significant planning and
    preparation
  • We are defining PEP-II DD scope as technical
    components, leaving buildings and tunnels intact
    including utilities, lighting and cable ways

4
Baseline plan for PEP-II DD
  • FY09-FY10 PPA manages initial planning effort
    while re-use cases are resolved
  • Develop refined budget and planning baseline,
    including offsite engineering participation in
    DD effort, packing and transportation costs,
    contractor costs for removal of components, and
    costs for new building as an on-site storage
    solution
  • Negotiate with potential recipients of PEP-II
    components for re-use to understand required
    interfaces and schedules, and shared funding
    scenarios
  • Manage development of possible protocol for
    exemptions to metals suspension in connection
    with BABAR DD project, with evaluation of
    implications for PEP-II component disposal
    scenario
  • Evaluate project options with CD-1 review at the
    end of FY2010
  • Will have firmer understanding of re-use needs,
    cost implications, and on-site space requirements
    for new storage building

5
Baseline plan for PEP-II DD
  • FY11-FY12 Develop project team and detailed
    project execution planning
  • If there is significant re-use of components for
    HEP-related projects, continue PPA management of
    project development
  • If there is no significant re-use planned, turn
    over management of the PEP-II DD project to ETS
    or equivalent lab technical services division
  • Plan for CD-2 review at the end of FY11 and CD-3
    in FY12
  • Begin construction of storage building in FY12
  • FY13-FY14
  • Execute PEP-II DD project under PPA (re-use
    scenario) or lab-operations (no re-use scenario)
    management
  • Complete storage building in FY13
  • Use contractor to remove components from tunnel,
    dispose radioactive waste store suspension
    material in on-site building

6
B Factory MMS/DD budget
In a SuperB Project-X re-use scenario, and
assuming exemption from the metals suspension,
BABAR PEP-II DD would be reduced by 15.5M
7
Structure of review talks
  • PEP-II introduction, MMS status, and initial
    estimates for DD scenarios Mike Sullivan, John
    Seeman
  • BABAR introduction, MMS status, DD planning,
    materials handling, schedule and budget Bill
    Wisniewski, Jim Krebs
  • Review of re-use requests David MacFarlane,
    Umberto Dosselli (INFN) and Jim Kerby (Fermilab)
  • BABAR safety planning Craig Ferguson, Frank
    ONeill
  • BABAR materials disposition issues and metals
    suspension planning Sayed Rokni, Joachim
    Vollaire, Amanda Sabourov, Olga Ligeti