ACINA Legal Seminar UPDATE ON 800 MHZ PUBLIC SAFETY SPECTRUM REBANDING PROCESS - PowerPoint PPT Presentation

1 / 8
About This Presentation
Title:

ACINA Legal Seminar UPDATE ON 800 MHZ PUBLIC SAFETY SPECTRUM REBANDING PROCESS

Description:

Wave 3: Southeast: NC, SC, GA, FL, AL, MS, LA. Wave 4: ... Wave 3 scheduled for June 2008: ... you're not alone, but if in Waves 1-3, you should be well along. ... – PowerPoint PPT presentation

Number of Views:35
Avg rating:3.0/5.0
Slides: 9
Provided by: willet
Category:

less

Transcript and Presenter's Notes

Title: ACINA Legal Seminar UPDATE ON 800 MHZ PUBLIC SAFETY SPECTRUM REBANDING PROCESS


1
ACI-NA Legal Seminar UPDATE ON 800 MHZ
PUBLIC SAFETY SPECTRUM REBANDING PROCESS
  • Kansas City, MissouriSeptember 30, 2007
  • Matthew C. Ames
  • Miller Van Eaton

2
Introduction
  • FCC set up rebanding process to deal with
    interference between private users primarily
    Nextel (now Sprint) and public safety licensees.
  • Example of problem Anne Arundel County, Maryland
    FCC rejected self-help.
  • Nextel required to pay for cost of moving public
    safety licensees to new frequencies no cap on
    liability, but Nextel put up 2.5 B letter of
    credit and received additional 10 MHz of
    spectrum.
  • If Nextel spends less than 4.8 B, less value of
    new spectrum and cost of reconfiguration, balance
    goes into U.S Treasury.

3
Process
  • Entire process originally scheduled to be
    completed 36 months from June 2005.
  • Process is overseen by Transition Administrator
    Bearing Point, Baseline Telecom and Squire
    Sanders Dempsey.
  • TA established four waves regions of country
    to complete process on staggered schedule.
  • Wave 1 Northeast and West Coast, except for
    Canadian, Mexican borders.
  • Wave 2 Central US, including less-populated
    border areas.
  • Wave 3 Southeast NC, SC, GA, FL, AL, MS, LA
  • Wave 4 Border regions.

4
Process (contd)
  • Each wave has two stages. Stage 1 move
    occupants of lower band. Stage 2 move holders
    of NPSPAC frequencies.
  • Affected licensees negotiate with Sprint/Nextel
    on terms of agreements. Licensees entitled to
    compensation for planning, and for
    reconfiguration itself.
  • Can negotiate two separate agreements Planning
    Funding Agreement and Frequency Reconfiguration
    Agreement or a single agreement depending on
    needs and circumstances.

5
Timing
  • Wave 1 supposed to be done by end of 2007 this
    is not likely to happen.
  • Wave 2 scheduled to be done by April 2008
    clearly behind schedule.
  • Wave 3 scheduled for June 2008 also lagging.
  • Wave 4 depends on reaching treaties with Mexico
    and Canada, and that negotiation process is
    lagging.
  • September 12, 2007, Public Notice Order extended
    certain dates.

6
Negotiations
  • TA must approve PFAs and RFAs, based on
    compensation for reasonable, prudent, and
    necessary expenses to achieve comparability.
    Sprint not required to pay for any system
    upgrades, although in practice some are required.
  • Licensee can ask Sprint to pay outside vendors
    directly, or opt to receive funds itself for
    distribution to vendors. Most choose first
    option.
  • TA established 3-month voluntary negotiation
    period, followed by 3-month mandatory
    negotiation period. If cant reach agreement
    within specified time, parties go to mediation.

7
Negotiations (contd)
  • Mediation conducted by TA. If parties dont
    reach settlement, mediator issues recommended
    resolution. If parties still dont agree, matter
    goes to FCC, where recommended resolution carries
    great weight.
  • Process slowed by tough negotiating by Sprint
    company refused to disclose information about
    costs and forced confidentiality on licensees
    that reached agreements, and at the same time
    forced licensees to prove what is reasonable,
    prudent and necessary. TA supported this, but
    FCC finally expressly allowed information
    sharing.
  • TA has tended to side with Sprint trying to
    force resolution and keep costs down.

8
Conclusion
  • If youre late youre not alone, but if in Waves
    1-3, you should be well along.
  • More time will likely be needed recent orders
    suggest FCC is figuring this out.
  • FCC order directed that licensees be kept whole
    should not accept less than that, although
    dynamics of process make that hard.
Write a Comment
User Comments (0)
About PowerShow.com