Title: Cost Benefit Analysis of the Three Gorges Dam
1Cost Benefit Analysis of the Three Gorges Dam
- Risako Morimoto and Chris Hope
2Methodology
- Goals
- Calculate present value of costs and benefits
- Examine uncertainty.
- Method
- Quantify each effect (e.g. kwhrs of electricity).
- Value each effect (e.g. determine its price)
- Sum discounted benefits minus costs
3Direct Costs
- Construction costs of the power station and
transmission facilities - Operation and maintenance cost
- Lost land from inundation (reservoir)
4Indirect Costs
- Resettlement costs (including compensation and
development costs) - Lost archaeological sites
- Possible accident costs (during construction,
operation and maintenance)
5Environmental Costs
- Aesthetic loss due to reduction in water flow
- Sedimentation- lower power generation
- Decline in fish catch downstream
- Downstream pollution caused by dam construction
6Benefits
- Power generation
- Economic growth (avoided economic losses from
power shortages) - Avoided damages from air pollution (from coal)
- Flood control
- Navigation improvement
7Uncertainty
- Key Parameters Electricity generated, economic
growth per kwhr, decay of electricity from
sedimentation, loss of archeological sites, etc - Allow parameters to vary and explore sensitivity
8Electricity
- What is capacity (GC) of dam?
- What is the electricity price (EO)?
- How will sedimentation reduce electricity over
time (A)?
9Data
10Analysis
- Use best guess of parameters and calculates
annual costs and benefits. - Examines many different assumptions about
parameters and calculate a distribution of NPV. - Discounts values back to current using 5
discount rate
11Calculate Flood Benefits
- Calculate frequency of flooding before dam
- Calculate economic damage and health effects of
each flood - Calculate expected flooding damage per year
- If dam eliminates flooding, then benefit is
damages avoided
12Expected Results
13Uncertainty Results
- The 5th percentile, mean, and the 95th percentile
of the cumulative NPV with a 5 discount rate
95th Percentile run
Mean run
5th Percentile run
14Results
- The final NPV values are 114, 424, and 1321
billion Yuan for the 5th percentile, mean and
95th percentile runs. - The cumulative NPV is initially negative due to
the large upfront construction and resettlement
costs. As electricity starts to flow, NPV
improves. Electricity at end of project matters
less than in early stages. - If climate change reduces electricity at end, it
would have only a small effect on NPV.
15Discussion
- Measures direct costs and benefits well
- Incorporates uncertainty
- Does not measure damages associated with coal-
undervalues electricity price - Assumes growth limited by electricity- probably
not true-over values electricity