Title: Setup Reduction -- Creating More Production Time Dr. Richard A. Wysk rwysk@psu.edu http://www.engr.psu.edu/cim March 20, 2003
1Setup Reduction -- Creating More
Production TimeDr. Richard A.
Wyskrwysk_at_psu.eduhttp//www.engr.psu.edu/cimMa
rch 20, 2003
2Make it better!Make it faster!Make it cheaper!
Lets spend a few minutes and talk about how we
might make things better, faster and/or cheaper.
3HIGH
FLEXIBILITY
TRANSFER LINE
PRODUCTION CAPACITY
SPECIAL SYSTEM
FLEXIBLE MANUFACTURING SYSTEM
VOLUME
MANUFACTURING Cells
STD. AND GEN. MACHINERY
LOW
HIGH
VARIETY
4Readings
- Singo Shingeo, A Revolution in Manufacturing-The
SMED-Single Minute Exchange of Dies-System,
Productivity Press, 1981. - Chapter 18 of Computer Aided Manufacturing, Wang,
H.P., Chang, T.C. and Wysk, R. A., 3rd Edition
(2004 expected) http//www.engr.psu.edu/cim/active
/ie450ho1.pdf
5Objectives
- To be able to identify internal and external
process elements - To be able to apply methods improvements
techniques to manufacturing - To calculate/measure the various Production Time
Elements - To be able to apply the techniques of set-up
reduction
6ExerciseReadiness Assessment Test A.K.A. RAT
- Complete the RAT for this module before you meet
to discuss this for class. - What set up reduction activities did you
select as having value added to you for personal
benefit?
7How long does it take to produce something?
- It is not unusual for the processing time to be a
very small part of the time required to make a
component. - Order materials
- Accumulate parts
- Setup machine
8JIT -- Speed is everything!
- Some Just in time models
- Buying bread
- Buying milk
- Buying take-out
9Exercise
- What are the most important factors that
contribute to the production time (average time
required to produce a single unit/product)?
10In Industry
- Between .05 and 5 of the time Value is being
added to a product
11What are the Value added activities at PSU Inc.?
- Receiving -gt
- Material handling -gt
- Machining -gt
- Assembling -gt
- Packaging
12Are we really adding value
- What percent of the time are the machines
producing good product? - What percent of the time are the moving and
setting up?
13Producing a product
- Production time (per lot)
-
- setup time (per lot) manufacturing time (per
lot)
14Producing a product
- Manufacturing time (per piece)
-
- material handling and locating time (per piece)
manufacturing time (per piece)
15Product time (per piece)
Total production time S (set up time
load/unload time processing time
idle time tool change
time) initial set up time
16the time required for setup for an operation
(load fixture,
retrieve tooling , etc.)
L/UL
17Production time per piece
- The cost associated with new tooling is also a
key consideration - for the designer.
- For low and medium volume products, the cost
associated with - tooling and setup can dominate the total product
cost.
18- The product cost can be expressed as
-
- Production cost per piece, Cp
19where
Cmo is the cost of machine and operator/hour Ct i
s the perishable tooling cost np/t is the number
of pieces that can be produced per
tool Csetup is the setup resource cost for the
part (fixture, jig, steady-rest,
etc) nbt is the total number of parts to be
produced
20Simple CNC Example
- New batch of parts arrives
- Change over tools for the batch
- Set offsets for new tools
- Load NC program
- Validate
- Run parts
- Load part onto machine
- Cycle start and wait
- Unload and visually inspect (adjust if necessary)
Setup time per lot
Material handling and loading time per piece
21Graphically it looks like
TOTAL TIME TO PRODUCE A LOT OF PRODUCT
SETTING UP THE MACHINE
RUNNING THE MACHINE AND OFF-LINE MEASUREMENT
This can be gt 30 of the TOTAL TIME TO
PRODUCE A LOT
22A look at SETUP
SETTING UP THE MACHINE
Setup consists of activities that must be
performed on the machine (these are called
Internal Elements), and elements that can be
performed off-line or while the machine is
producing a product (these are called External
Elements)
23Rapid Tool Change-over Setup consists of
- Internal Elements - Elements that must be
performed on the machine itself - External Elements - Elements that can be
performed off-line
24A look at SETUP (contd)
SETTING UP THE MACHINE
Internal Elements
External Elements
These External Elements can be completed while
the machine is producing good product. For
instance, we can clean a die set after the
machine comes up. We can preassemble
components for a setup.
25A look at SETUP (contd)
SETTING UP THE MACHINE
Internal Elements
External Elements
RUNNING THE MACHINE
If the External Elements are performed while the
machine is producing good parts then we can
reduce the TOTAL PRODUCTION TIME by starting
production earlier.
26Premise for SMED
Idle time waiting for materials or other resources
Set up time where machine is down while
operators prepares for next activity
Processing time - adding value to raw materials
27Graphically it looks like
TOTAL TIME TO PRODUCE A LOT OF PRODUCT
SAVINGS
SETTING UP THE MACHINE
RUNNING THE MACHINE AND OFF-LINE MEASUREMENT
Production Time gained
28Premise for SMED
Methods improvements
Idle time waiting for materials or other resources
Set up time where machine is down while
operators prepares for next activity
Processing time - adding value to raw materials
29Exercise (5 minutes)
- As an individual, describe a process that you
know well (from work, food preparation, office
activities) - Identify the internal and external elements for
setup or work changeover.
30Methods Improvement
- Standard ways to improve setup efficiency
- Power tools
- Collets and quick-change fixtures
- 2nd set of fixtures and tools
- Setup layout
- Setup accumulation
31Examples of Improved Methods
32Make the tool part of the screw device -- you
dont need a tool, and this will save time in
disassembling and reassembling the tooling and
fixturing!
33Reduce the amount of turns required in order to
activate the screw.
34Reduce the amount of screw turns and eliminate
the tool!
35(No Transcript)
36(No Transcript)
37(No Transcript)
38Areas with potential benefit
- Screws and screw fasteners
- Tedious manual activities
- Power tools can be appropriate
- Connectors
- Others????
39Currently changeover is done with these tools
40Currently changeover is done with these tools
41How about power tooling?
42How about cordless power tooling?
43Exercise
- As an individual, describe what methods,
improvements, you could make to the setup/change
over activity for the Case production system or
some other system that you are familiar with?
44SMED is employee driven
- Train Area supervisors and operators
- Some implementation with outside consultant
- Most implementation within your company
45Questions?