Title: Innovative Contracting
1Innovative Contracting
- UDOT
- Director of Construction and Materials
- Kris Peterson
2Innovative Contracting Works to Improve the
Process
- Reduce impact to public
- Reduce overall project time
- Limits Schedule Growth
- Reduce overall project cost
- Limits Cost Growth
3Types of Innovative Contracting
- Contract Manager / General Contractor (CMGC or
CM_at_Risk) - Design-Build
- A B Bidding
- Lane Rental
- Warranties
- Incentives
- Performance-based
4Timeline Comparison
Design Phase
Construct Phase
5CMGC Roles
Why Innovative Contracting
6CMGC Benefits
Lessons Learned
UDOT Controls Design UDOT Selects Innovation
7Other CMGC Benefits / Risks
Why Innovative Contracting
- Benefits
- Reduces design time and design errors
- Improves constructability
- Identifies and reduces risk
- Early procurement
- Lower cost
- Risks
- Sole source contract
- Bid price needs to be 10 of EE or below
- Negotiation skills
8Reduce Risk to Reduce Cost Increase Profit
Contractor Risk
Owner Risk
Risk
DBB
DB
CMGC
9Selection Strategy
Why Innovative Contracting
- Select complex projects
- That benefit from contractor input
- With third-party risk
- That need innovation
- Need early procurement
- Select projects with a budget emphasis
- Take time for design
10CMGC Requires Approval
- Experimental Process - SEP 14
- 12 Federal Projects per year
- 12 State Projects per year
- Justification required
- Project Development approves
- FHWA must also approve federal projects
11Contracting Process
- Develop RPF
- Selection Criteria
- Price components
- Advertise
- Selection team
- Complex participants
- Region participants
- AGC and ACEC representatives
- Select Award
12Processing Time
13Price Benefits
- Brings cost accountability to the table
- Brings cost competition to the table
- Brings cost innovation to the table
- Provides validation of good price for public trust
14Price in CMGC RFP
Where are we going?
- Price
- Continue to use the average target
- Most realist cost
- Approach to Price
- Emphasize during pre-proposal
- Change the format
15(No Transcript)
16Utah CMGC Projects (State)
Where are we going?
17Utah CMGC Projects (Federal)
Where are we going?
18Design Build
Plan
UDOT
Design
Contractor
19Design-build
- Benefits
- Faster Design/Construction
- Smaller cost growth
- Smaller schedule growth
- Innovation (Contractor controlled)
- Risks
- Design-build is built for speed
- Contractor owns the design
20Design Build Advertising Process
- Letter of Intent (Interest) LOI
- RFQ
- RFP
- Low-Bid
- Best-Value
21Checklists
- Located on the 2008 Standards / Checklists website
http//www.udot.utah.gov/Inside UDOT/Project
Development/Standards and Specifications /2008
Standards/2008 Project Checklists
22Selection Committee
23Reduce Time on Project
- AB Bidding
- Contractors bid the time to complete the project
and a dollar amount for work items - Award to lowest combinations of time and cost
- Lane-Rental
- Minimize the time lanes are closed
- Contractors are charged a fee for closing lanes
and shoulders - Focus on time the public is affected
24A B Bidding
- Benefits
- Improved coordination between prime and
sub-contractors - Reduced construction time minimizes impacts to
users - Contractors are required to put together a well
conceived schedule - Drawbacks
- Contract changes are magnified too many changes
nullify the advantages of AB - Acceleration techniques may require more
resources for contract administration - More hours and over-time budget required from
Region staff - Negotiations for additional work are more
intense since time is a bigger issue
25AB Candidates
- Good
- Interstate Projects
- Mill and Overlays
- Projects with Detours
- Bridge Painting
- Intersection upgrades
- New Construction/Reconstruction
- Bad
- Third-party delays
- Rehabilitations
26Lane Rental
- Benefits
- Better coordination of prime and sub-contractors
- Minimized impact to traveling public
- Better public perception due to fewer
un-utilized lane closures - Drawbacks
- Extra effort by staff to monitor lane rental
- Negotiating lane rental adjustments can be
difficult with contract changes - Potential added costs to the project
27Lane Rental Candidates
- Good
- Mill and Overlay (2-lane roads with flagging ops.
or intersection impacts) - Safety projects (guardrail/signing/striping/bridge
painting) - Bad
- New construction
- Long-term projects
28Warranties
- Guarantee all or portions of a construction
project - Free of defects in material
- Workmanship
- Time Period
- Correct deficiencies during warranty period
29Warranty Pros and Cons
- Benefits
- Quality and durability guaranteed
- Longer acceptance time
- Less inspection needed
- Drawbacks
- Owner must ensure warranty
- Warranty may not be collectable
- Staffing to monitor warranty
30Incentives - Disincentives
- Paid for early completions
- Penalized for late completions
31I D Pros and Cons
- Benefits
- Reduced construction time
- May lower contract admin costs
- PI benefits
- Control of project acceleration
- Drawbacks
- May require additional funding
- Contract changes may lead to disputes
32Pay-for-Performance
- Pay is dependent upon final outcome
- Measured against performance criteria
- Set by contract
- Pay withheld for poor performance
- Corrective action required
33PFP Pros and Cons
- Benefits
- Eliminates blame
- Shifts risk to contractor
- Higher quality
- Drawbacks
- Time to measure performance
- Long project close-out
- Monitoring is time- consuming
- Contractor may have to finance a portion
34Innovative Web Site
- www.dot.state.mn.us/const/tools/docments/Guideline
s.pdf - Dec 2005