Public Assistance Training - PowerPoint PPT Presentation

1 / 68
About This Presentation
Title:

Public Assistance Training

Description:

Gather list of damages for Kickoff meeting with FEMA & State. The FEMA Public Assistance Coordinator (PAC) should attend the Briefing to cover ... – PowerPoint PPT presentation

Number of Views:223
Avg rating:3.0/5.0
Slides: 69
Provided by: darrell7
Category:

less

Transcript and Presenter's Notes

Title: Public Assistance Training


1
Public Assistance Training
Presented by Florida Division of Emergency
Management FEMA
2
Introduction
  • Steve Brice
  • State Public Assistance DPAO State Wide
  • 407-268-8899
  • Fannie Spivey
  • FEMA Lead PNP Closeout Specialist
  • 407-473-8194
  • Charles Dugger
  • FEMA Infrastructure Branch Deputy Director , QC
  • 407-268-8789

3
GOALS
  • To learn how to become eligible for FEMA public
    assistance
  • To learn how to acquire all eligible funding with
    proper Documentation and Record Keeping

4
The Public Assistance Process
Disaster
Event
State
Funding
PDA
Applicant
Declaration
Validation
of
Small
Projects
Applicant
Briefing
Complete
Submission
Project
of
Kickoff
Worksheets
Request
Meeting
5
PDA / DECLARATION
Disaster
Event
State
Funding
PDA
Applicant
Declaration
Validation
of
Small
Projects
Applicant
Briefing
Complete
Submission
Project
of
Kickoff
Worksheets
Request
Meeting
6
Preliminary Damage Assessment (PDA)
  • Local governments determine disaster is beyond
    capabilities, State determines beyond State
    capabilities and request Federal assistance
  • FEMA, State, and local governments conduct a
    joint PDA
  • Governor will review information gathered
  • Governor requests assistance from the President

7
Preliminary Damage Assessment (PDA)
  • 2 Departments
  • Individual Assistance (IA)
  • Public Assistance (PA)
  • These 2 departments are focused on gathering
    different damage costs
  • Combined later to get declaration

8
Preliminary Damage Assessment (PDA)
  • Key process to gather damage estimates
  • Estimate used to trigger Presidential Disaster
    Declaration
  • Your trigger to start Record Keeping and
    Documentation.

9
DISASTER DECLARED
  • Hurricane Budget Deficit

10
PROJECT WORKSHEETS
Disaster
Event
State
Funding
Declaration
Applicant
PDA
Validation
of
Small
Projects
Applicant
Briefing
Complete
Submission
Project
of
Kickoff
Worksheets
Request
Meeting
11
Purpose of a Applicant Briefing Meeting
  • The Applicant Briefing is given by The State
  • Informs Applicant of the need to submit the
    Request for Public Assistance
    (30 days after the declaration)
  • Gives a detailed review of the PA Program
  • Covers State specific guidelines
  • Gather list of damages for Kickoff meeting with
    FEMA State
  • The FEMA Public Assistance Coordinator (PAC)
    should attend the Briefing to cover any
    questions on eligibility

Response, Recovery, Rebuilding
12
APPLICANT BRIEFING
  • BE THERE
  • BE IN THE K NOW!

13
REQUEST FOR PUBLIC ASSISTANCERPA
  • WWW.FLORIDAPA.ORG
  • MUST SUBMIT WITHIN 30 DAYS OF DECLARATION TO
    START APPLICATION PROCESS!

14
(No Transcript)
15
(No Transcript)
16
Purpose of a Kickoff Meeting
  • Gives a detailed review of the PA Program
  • Establish a partnership among the FEMA ( PAC),
    the State PAC, and the Applicant
  • Address eligibility and documentation
    requirements most pertinent to The Applicant
  • The PAC also discusses any Special
    Considerations issues unique to The Applicant and
    assigns a Project Officer (PO)

17
HOW CAN WE ASSURE ALL DAMAGES ARE CAPTURED?
  • Understanding that others need to know what you
    know about the projects damages. How is this
    done?
  • COMMUNICATION-COMMUNICATION-COMMUNICATION
  • A list of disaster related damages and pictures
    are very beneficial for identifying all damages.
  • You know your community better than we do, so we
    look to you to show us what needs repaired.

18
(No Transcript)
19
Project Worksheet (PW)
  • Used to document
  • Damages
  • Scope of work
  • Estimates eligible cost
  • Minimum PW is 1,000
  • Applicants participation is vital

20
Cost Share
  • Federal share at least 75
  • Non-Federal share can be
  • State
  • Applicant
  • State-Applicant
  • combination

21
Small Project or Large Project
  • Annually updated 59,700 is the fiscal year
    2007 threshold amount

22
Types of Eligible Work
  • 1. Emergency Work
  • (Categories A B)
  • 2. Permanent Work
  • (Categories C - G)

23
Work Categories
  • A Debris Removal
  • B Protective Measures
  • C Road System
  • D Water Control Facilities
  • E Buildings And Equipment
  • F Public Utility Systems
  • G Other (Park and Recreational)

24
Eligible Work Criteria
  • Required as a result of declared disaster
  • Located in designated disaster area
  • Legal responsibility of eligible applicant
  • No other Federal agency has specific authority

25
72 Hour Period
  • Choose a 3-day period to receive 100
    reimbursement
  • Identify greatest expenses for emergency work
  • For some disasters, no 72 hr period

26
  • DOCUMENTATION
  • DOCUMENTATION
  • DOCUMENTATION

27
Record KeepingVital To Full Reimbursement
  • Document costs by PW for approved work
  • FEMA has forms that assist in organizing and
    summarizing
  • Original documentation required
    for closeout and audit
  • Keep records for 5 years after closeout
    letter from FEMA

28
Documentation
  • Force Account Labor
  • Force Account Equipment
  • Force Account Materials
  • Contracts
  • Mutual Aid Agreements
  • Insurance policies
  • Pay policies
  • Invoices / cancelled checks

29
Labor Costs
  • Force Account Labor
  • Work done by your employees
  • Emergency work only overtime is eligible for
  • Permanent Employees
  • Reassigned Employees
  • Seasonal Employees
  • Permanent work both regular and overtime are
    eligible for all employees.
  • Overtime may be credited in actual wages or in
    compensatory time off.

30
Labor Costs
  • Timesheets
  • Hints
  • Encourage employees to be detailed
  • Correct Dates
  • List Overtime Regular time hours
  • Work Performed
  • Implement a code for the storm work
  • Pay Policy
  • Fringe Benefits

31
Equipment Costs
  • Force Account Equipment used by your employees.
  • Examples
  • Vehicles
  • Trailers
  • Heavy equipment
  • Chain saws

32
Equipment Costs
  • Need equipment logs
  • Things to look for
  • Equipment hours must match labor hours.
  • One person, one piece of equipment
  • No duplication of projects

33
Material Costs
  • Force Account Materials
  • Purchased
  • Taken from stock
  • Must be reasonable amount and cost
  • Keep all invoices and receipts
  • Make sure there is a date

34
Contracts
  • Must be a reasonable cost
  • Generally must be competitively bid
  • Comply with Federal, State, and local procurement
    standards

35
Procurement Standards
  • Small purchase procedures
  • less than 100,000
  • Several quotes from different sources
  • Sealed Bids
  • publicly advertised
  • contract awarded to lowest bidder
  • Competitive proposals
  • based on contractor qualifications
  • preferred for architectural and engineering
    services
  • Non-competitive proposals
  • Generally ineligible

36
4 Types of Contracts
  • Lump Sum
  • within a prescribed boundary
  • clearly defined scope of work
  • a total price
  • Unit Price
  • item-by-item basis with cost determined per unit
  • Cost plus fixed fee
  • Lump Sum or Unit Price contract with a fixed
    contractor fee added to the price
  • Time and Materials
  • FEMA will generally accept within 70 hours
    immediately after the disaster
  • Generally should be avoided.

37
Mutual Aid Agreements
  • Keep mutual aid agreements up to date
  • Collect mutual aid agreement

38
Record Keeping
  • Insurance policies
  • Schedule of values
  • Statement of loss
  • Pay policies
  • Overtime
  • Fringe benefits
  • Timesheets
  • Invoices / cancelled checks

39
MY PW IS SIGNED, NOW WHAT?
40
PROJECT WORKSHEET REVIEW PROCESS
  • My project worksheet is written, when will I
    receive my funds?

41
InitialInsuranceHistoricalEnvironmentalDebr
isSBAStateFloodplainMitigationMisc.
(Airports, etc.)FinalMillion Dollars
  • PW MUST GO TO
  • FEDERAL STATE REVIEW


Response, Recovery, Rebuilding
42
Small Projects Reimbursements
  • Less than 59,700
  • Paid when obligated
  • Subject to closeout

43
Small Project or Large Project
  • Annually updated 59,700 is the fiscal year
    2007 threshold amount

44
Large Projects Reimbursements
  • Must submit Requests for Reimbursement as work is
    completed
  • along with Summary of Documentation
  • Should be paid within 3 weeks of request
  • Submit requests at www.floridapa.org

45
(No Transcript)
46
(No Transcript)
47
Payment Process
  • 1. Financial Specialist Review
  • 2. Financial Supervisor - Verification
  • 3. Program Manager - Approval
  • 4. Governors Authorized Representative
    -Approval
  • 5. Finance and Accounting - Processing
  • 6. Finance and Accounting Acceptance
  • 7. Payment Mail Check or Electronic Funds
    Transfer
  • 8. Review Flairs for check issue date or funds
    transfer

48
Key Points
  • Submit a Request for Public Assistance
  • Sign and return Disaster Relief Funding Agreement
  • Bring insurance policies to kickoff meeting
  • Bring key personnel to Kickoff Meeting
  • Complete all project worksheets with FEMA/State
  • For all Large Projects, submit RFR/SOD
  • Contact your State FEMA PACs for any specific
    questions

49
WORK IS COMPLETE, NOW WHAT?
  • LARGE PROJECT CLOSEOUT

50
What is A Large Project Closeout?
  • Certify
  • that all recovery work is completed
  • that all eligible costs have been reimbursed
  • Ensure that applicant has received all
    funding available under the law.

51
WHO PERFORMS CLOSEOUT
52
Closeout Team
  • PA
  • Planners
  • Closeout Specialist
  • Debris Specialists
  • Applicants

53
Closeout Process
Project Completion
Request RFI
Closeout Team Assigned
Initial Meeting
Review Expenses
Final SOD
20 Plus Validation
Site Inspection
Generate JCT
Applicant Signature
Submit for Review
Forward to Grants Management
54
Final SOD
  • Applicant submits actual eligible dollars spent

55
Overrun VS Under-run
56
Closeout PW
  • FEMA Completes Report

57
Final InspectionSignoff Comments
  • State PAC Completes Report

58
Supporting Documentation
Supporting Documentation (e. g. time sheets,
equipment logs, contracts, invoices, etc.)
Summary of Documentation SOD Supplemental
Worksheet
Project Worksheet 999cv1
Final Inspection Signoff
59
Critical Issues In Closeout
  • Project Deadlines
  • Cost Overruns
  • Project Thresholds
  • Reasonable Costs

60
Project Deadlines
  • Emergency Work 6 months
  • Additional 6 month extension from the state
  • Permanent Work 18 months
  • Additional 30 month extension from the state
  • State may impose lesser deadlines
  • State may request additional time from FEMA

61
Cost Overruns
  • Three categories
  • Variations in unit prices
  • Change in the scope of eligible work
  • Delays in timely starts or completion
  • Applicant must request additional funding through
    the state for FEMA review

62
Reasonable Costs
  • Does not exceed that which would be incurred by a
    prudent person under the circumstances prevailing
    at the time the decision was made to incur the
    cost.
  • Historical documentation for similar work
  • Average costs for similar work in the area
  • Published unit costs from national cost
    estimating databases
  • FEMA cost codes

63
Project Closeout
  • FEMA Letter
  • Voucher Analysis Report Delivered to State

64
COMMON PITFALLS
  • UNIDENTIFIED DAMAGES OR PWS
  • MY SCOPE OF WORK CHANGED, WHAT HAPPENS?
  • TURNOVER WITH APPLICANT, STATE, FEMA
  • CAN I USE PW MONIES FOR OTHER PROJECTS?
    (ALTERNATE/IMPROVED)
  • MY PW WAS REDUCED DURING REVIEW PROCESS, WHY?
    (INSURANCE, INELIGIBLE, ETC)
  • I NEED TO PERFORM WORK NOT IN PW SCOPE OF WORK,
    CAN I DO THIS?
  • MY INSURANCE COMPANY GAVE MORE/LESS THAN PW
    AMOUNT, HOW DO WE RESOLVE?
  • MY PROJECT IS MORE THAN MY PW, WHAT HAPPENS?

65
FEMA ContactsFlorida Long Term Recovery Office
  • Scott Morris
  • Director
  • 407-268-8560
  • Martin Altman
  • Infrastructure Branch Director
  • 407-268-8920
  • Martin.Altman_at_dhs.gov
  • Roger Jones
  • Infrastructure Branch Deputy Director
  • 407-268-8904
  • Roger.Jones_at_dhs.gov

66
RESOURCES
  • www.floridapa.org
  • www.floridadisaster.org
  • www.fema.gov

67
Contacts
  • Gary Freerksen
  • State Public Assistance Officer
  • Orlando office number (407)
    268-8899gary.freerksen_at_dca.state.fl.us
  • Bill Owens
  • Lead Deputy PAO Long Term Recovery
  • Orlando office number (407) 268-8899
  • william.owens_at_dca.state.fl.us
  • Stephen Brice
  • Deputy PAO Finance
  • Orlando Office number (407) 268-8899
  • stephen.brice_at_dca.state.fl.us

PUBLIC ASSISTANCE
68
Rebuilding Communities
  • A video overview of
  • Public Assistance
Write a Comment