EMCal Progress CR7 - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

EMCal Progress CR7

Description:

EMCal Progress CR7 – PowerPoint PPT presentation

Number of Views:115
Avg rating:3.0/5.0
Slides: 42
Provided by: josephe2
Category:
Tags: cr7 | e9j | emcal | progress

less

Transcript and Presenter's Notes

Title: EMCal Progress CR7


1
EMCal Progress CR-7
2
Detector Concept
3
A Total of 11 Super Modules 10 1/21/2
4
  • Support Structure
  • (CalFrame)
  • Construction Status Update

5
Anchor Cal Frame to
Slip Surface
TPC Rails
6
EMCal Support Structure Update
EMCal support structure shown with super modules
installed
7
Modified Design to Reduce Stress in Support Beams
Top outriggers
Super module rails
Bottom outriggers
8
Bottom Outrigger
Support Forks
9
Top Outrigger
10
Rails Used as aligment parts for assembly of
Calframe
11
1/2 Support Structure Completed at Fravit in Italy
12
(No Transcript)
13
Top Outriggers Welded
14
Fabrication Progress (Good News)
  • Fabrication of EMCAL support structure at Fravit
    was completed in first week of February
  • Top and bottom outriggers welded at Fravit
  • Support fork material is available at CERN.
    Machining should be completed before end of March

15
Shipping to CERN (Bad News)
  • Shipping company was behind schedule in getting
    all shipping documents approved
  • All documents were approved to go through Mt
    Blanc tunnel on 2 March
  • Mt Blanc tunnel was closed to all traffic due to
    rock slide on 3 March
  • Tunnel was opened to normal traffic 10 March
  • All special traffic not allowed until full repair
    is complete (could be several months)
  • Applied for permits to change route to Frejus
  • Juggling assembly schedule at CERN to minimize
    impact.

16
Remaining Tasks at CERN
  • Weld support forks
  • Align and connect the two half frames
  • Load test
  • Install SM rails
  • Install EMCal services
  • Ready for transfer to cavern
  • Once the CalFrame is at CERN, we need 8 weeks to
    get ready for installtion inside L3

17
Assembly Schedule based on CalFrame at CERN on 19
March
18
CalFrame Installation Fixture
  • Installation fixture will be used for load test,
    assembly and installation

19
(No Transcript)
20
Load Test Plan
Cables connecting the 200200 beams to the 53 ton
bloc
21
EMCal Services on the CalFrame
  • Design of service is complete
  • Fabrication of cable tray started
  • All cables and connectors ordered and ready for
    assembly
  • Water cooling components are on order
  • CERN techs will assemble cable trays and low
    voltage cables
  • EMCal techs will make up and install all other
    cables and cooling water tubes.

22
(No Transcript)
23
P. Panel (step 1)
C. Trays (LV sense)
P. Panel (step 1)
Cool. Pipe in
C. Trays (others cables)
Cool. Pipe out
C. Trays (opt. fiber)
24
(No Transcript)
25
Other Engineering Development
  • Prototype SM crate fabrication is complete
  • Goal is to be ready to perform a dummy SM
    insertion test ( full weight) before the end of
    the summer 07
  • 1. CERN has steel block that could be
    modified as SM dummy weight
  • 2. Design of platform to support SM
    insertion tooling has started

26
More Pics
Super Module Crate Parts
27
(No Transcript)
28
(No Transcript)
29
Ridges for StripModulesmachined on CAM /
CNCmilling machine
30
Insertion Toolingfabrication drawings completed,
tender for bids on the way, task on a tight
schedule, tests expected in July 2007
31
Insertion Tooling in operation (1200 and ½ SM
locations)
32
  • Detector Prototypes

33
First Generation Prototype Final Test Beam
Results
34
  • Second Generation (Final) Prototypes

35
Assembly of Final Design Mechanical Prototype
Modules
Stacking / Compressing
36
Accelerated Aging Study of Mechanical Stability
Deflection 150?m .. Work in progress
37
  • Final Prototypes and Subsequent Schedule
  • Design Completed February 2007
  • All Components Available May 2007
  • Modules ready June 2007
  • Electronics July 2007
  • Test Beam August 2007
  • Construction Funding
  • US DOE CD-2/3 October 2007
  • IN2P3/INFN Pending (January 2008?)

38
  • Provisional Project Control Milestone
  • (Provisional because they are computed for the
    presently approved but unfavorable funding
    profile)

39
EMCal Summary Milestones - Default Funding profile
40
EMCal Summary Milestones - Default Funding profile
US super modules for 2010 run
2 US 2-3 EU 4 - 5 of 11 Super Modules for 2010
41
EMCal Summary Milestones - Proposed Accelerated
Funding Profile
5-6 US 2-3 EU 7-9 of 11 Super Modules for 2010
This is still cash flow limited. There are no
technical limits to completion of the project for
2010
Write a Comment
User Comments (0)
About PowerShow.com