Software Project Management SPM - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Software Project Management SPM

Description:

Planned Value (PV) or Budget Cost of Work Schedule (BCWS) ... budget that was originally planned up to the same date: EV PV ... Activities PV(NEW) ... – PowerPoint PPT presentation

Number of Views:428
Avg rating:3.0/5.0
Slides: 19
Provided by: IBM84
Category:

less

Transcript and Presenter's Notes

Title: Software Project Management SPM


1
Software Project Management (SPM)
  • Lecture 7
  • Cost Management
  • Dr. Daniel Keret

2
Reading Assignment
  • Software Project Management, Bob Hughes and Mike
    Cotterell, McGraw-Hill, 3rd Edition.
  • Chapter 9
  • A Guide to the Project Management Body of
    Knowledge, PMI Publications, 3rd Edition, 2004
  • Chapter 7

3
Cost Management
  • Cost Management includes
  • Cost Estimation
  • Cost Budgeting
  • Cost Control
  • Estimation Budgeting Main Tools Techniques
  • Estimation Techniques
  • Reserve Analysis ( Risk, Unknown, Cost of
    Quality)
  • Cost Baseline
  • Funding Requirements Cash Flow
  • Cost Control.
  • Performance Measurement Analysis Planned value,
    Actual Cost, Cost Variance, Cost Performance
    Index, Estimate to Complete
  • Approved Change Requests

4
Estimating Schedule Activity
  • Estimation Cost of the Resources Needed to
    complete the activity
  • Includes variations to the cost estimate (Risk,
    Etc)
  • Take into consideration Alternative Costing for
    the overall project time period
  • Cost of extended design effort VS. additional
    maintenance costs
  • Cost estimates include ALL resources that will be
    charged to the project including Inflation
    Forecast, Salary Increase, Contingency cost.
  • ROM (Rough Order of Magnitude, E.G 50/100) is
    allowed in the first stages. Refinement is
    required at later stages ( E.G -10/15).

5
Activity Estimating Inputs Tools
  • Inputs
  • External Factors Marketplace Condition, External
    Cost Information Databases
  • Organization Assets Historical Information,
    Estimating Policies and Templates, Team Knowledge
  • Project Factors Scope, WBS, Management Plan,
    Schedule Plan, Staffing Plan, Risk
  • Tools
  • Analogous Estimates
  • Resource Cost Rates
  • Parametric Estimates ( Function Points Etc)
  • Vendor Bid Analysis
  • Project Management Software

6
Activity Estimating Inputs Tools(Cont.)
  • Reserve Analysis (Contingency Allowance)
  • Will Be Used at the Discretion of the Project
    Manager
  • Budgeting Project Unknowns
  • Risks
  • Will Be budgeted according to their severity
    level and probabilities
  • The budget will cover mitigation activities and
    workarounds and will be implemented upon the
    project manager decision.
  • Cost of Quality (COQ)
  • Costs added to the project in order to ensure
    conformance with quality standards
  • Cost of Non Quality Failure Cost/Rework. Costs
    that will added as a result of bugs and
    non-quality project activities

7
Activity Estimating - Output
  • Activity Cost Estimating Most likely estimates
    of all the activity resources
  • Estimate Details
  • Basis for the estimate (how it was developed)
  • Assumptions made
  • Constraints
  • Possible range of the estimate ( 100000
    -10/15)
  • Requested Changes ( If the estimate analysis
    recommends a change)
  • CA Control Account (the corporate accounting
    number that will incur the cost of the activity)
  • Cost Management Plan (Update)

8
Cost Baseline
  • Aggregating the estimated costs of the individual
    scheduled activities to establish a total COST
    BASELINE for measuring and budgeting the project
  • Inputs WBS, Activity Cost Estimate, Project
    Schedule, Resource Calendar, Contracts, Cost
    Management Plan
  • Tools Techniques Cost Aggregation, Reserve
    Analysis, Parametric Estimating ( adjustment to
    the aggregate cost), Funding Limit Reconciliation
    (can impact the schedule and overall cost)
  • Output Cost Baseline, Expected Cash Flow,
    Funding Requirements (including Management
    Reserve), Requested Changes, Updated Cost
    Management Plan

9
Cost control
  • Assuring the Potential Cost Overrun do not
    exceed the authorized funding PERIODICALLY and in
    TOTAL
  • Monitoring cost PERFORMANCE to detect and
    understand Variances from the Baseline
  • Detect Changes as they occur
  • Prevent unapproved changes
  • Ensuring Requested Changes are Agreed Upon
  • Report Changes to Stakeholders
  • Acting to bring expected overruns within
    acceptable limits
  • Influencing factors that creates changes to the
    cost baseline

10
Performance Measurements
  • Planned Value (PV) or Budget Cost of Work
    Schedule (BCWS) baseline budget up to a given
    point in time.
  • Earned Value of an Activity
  • 0/100 technique ( The Recommended One) 0 if the
    activity is not fully completed. Full Actual Cost
    if the activity was completed.
  • 50/50 technique 50 of the planned cost if the
    activity started, 100 of the actual cost if it
    was completed
  • Milestone Technique Actual Cost at the milestone
    date.
  • Earned Value (EV) or Budget Cost of Work
    Performed (BCWP) the sum of the baseline costs
    of the work performed up to a given point in time
  • Actual Cost (AC) or Actual Cost of Work Performed
    (ACWP) up to a given point in time

11
Performance Indicators
  • Cost Variance The difference between actual and
    budget cost spent up to a given point in time EV
    AC.
  • Schedule Variance The difference of the
    baseline budget actually spend up to a given
    point of time and the baseline budget that was
    originally planned up to the same date EV PV
  • CPI (Cost Performance\Overrun Indicator) EV/AC
    Earned Value/Actual Cost. CPI lt 1 indicates
    budget overrun
  • SPI (Schedule Performance\Overrun Indicator)
    EV/PV Earned Value/Planned Value SPIlt1 indicates
    schedule overrun

12
Example
13
Forecasting
  • Making Predictions or Estimates of the Project
    future Schedule or Cost based on the project
    available information at the time of the
    Forecasting.
  • Forecasting is USED TOGETHER with Manual
    Forecasting of the remaining work. (which is
    considered to be more accurate)
  • Definitions
  • BAC (Budget At Completion) Cost baseline at the
    end of the project
  • ETC (Estimate To Complete)
  • EAC (Estimate At Completion)
  • ADE Activity Duration Estimate

14
Forecasting Techniques - Cost
  • Recalculate Cost of Future Scheduled Activities
  • Based on Typical Variance (History performance is
    a good prediction for the future performance)
    EV(NEW)EV/CPI
  • Based On Atypical Variance ( History deviation of
    planned performance is irrelevant for this
    activity) EV(NEW)EV
  • ECT SIGMA(Future Activities PV(NEW)). If all
    the future activities are typical then
    ETC(BAC-EV)/CPI
  • EAC AC ETC (actual cost to date estimated
    cost to completion)

15
Forecasting Techniques - Time
  • Recalculate Time of Future Activities
  • Based on Typical Variance (History performance of
    activity duration estimate is a good prediction
    for the future performance) ADE(NEW) ADE/SPI
  • Based On Atypical Variance ( History deviation of
    planned performance is irrelevant for this
    activity) ADE(NEW)ADE
  • Estimate Time To Completion will be calculated
    according to the project work schedule and the
    critical path.
  • If the variance is typical across the project we
    can use a rough estimate ADE Planned time to
    completion/SPI

16
Example
17
Cost Control Workflow
  • Input Cost Baseline, Funding Requirements,
    Performance Information and Reports, Approved
    Change Requests, Project Management Plan
  • Tools Techniques Cost Change Control System,
    Performance Measurement Analysis, Forecasting,
    Project Performance Review/Meeting, Variance
    Management
  • Output Cost Estimate Update, Cost Baseline
    Update, Performance Measurements, Forecasted
    Completion, Requested Changes, Recommended
    Corrective Actions, Organization Process Assets
    (lessons learned), Project Management Plan
    (update)

18
Approved Change Requests
  • Changes in the Scope of the System
  • Requirements Requested By the Users and by
    Project Management.
  • May Change the Baseline Cost of the project as
    well as the Planned Completion Date.
  • Requires Stakeholders Approval
  • Changes that do not affect the project Scope
  • Usually Changed due to the project team requests
  • Changed in Design, Architecture, Delays, Etc.
  • Stakeholders will be notified if the changes are
    significant enough.
Write a Comment
User Comments (0)
About PowerShow.com