Title: Air and Ozone Sparging of TCE Using a Directionally Drilled Horizontal Well Site 86, Camp Lejeune
1Air and Ozone Sparging of TCE Using a
Directionally Drilled Horizontal WellSite 86,
Camp Lejeune
- Mark Strong, P.E. CH2M HILL
- Christopher Bozzini, P.E. CH2MĀ HILL
- Daniel Hood, NAVFAC Mid-Atlantic
- Bob Lowder, MCB Camp Lejeune EMD
2Camp Lejeune Background
- Second largest U.S. Marine Corps Base in the
Country - Camp Lejeune was established near the city of
Jacksonville, N.C, in 1942. - Base covers 236 square miles
- CERCLA site since 1989
- 22 Operable Units (OUs), 97 Sites.
3Site Location and History
- Site 86 is associated with three former waste oil
ASTs, used during the 70s and 80s - Over the course of several investigations since
1992, the solvent plume migrated away from the
source area and now extends several hundred feet
off-site
Bld. 25
4Pilot Test Objectives
- Prevent further migration of the TCE plume
off-site - Evaluate air (and ozone) distribution using a
horizontal well - Determine if ozone and/or air sparging can reduce
TCE impacts to below regulatory standards within
one year
5TCE in Plume in 2002 (30-35 bgs)
6TCE in Plume in 2002 (40-45 bgs)
7TCE in Plume in 2002 (50-55 bgs)
8Site 86 Cross Section
9Directional Drill Rig On-Site
10Air Sparge Screen
4 SDR 11 HDPE Pipe 0.020 Inch Wide Slots 0.5
Open Area
11Directional Sparge Well Layout
Total Length of Drill 950 Total Slotted Length
- 350
12Compressor and Ozone Generator Temporary
Buildings (Connex Boxes)
13Ozone Generator Chiller
14Air Compressor, Receiver, Gas Cooler
15Ozonia Generator (CFV-03, 60 ppd, air feed)
Photo courtesy Ozonia North America
16Baseline TCE Concentrations, Feb 05 30-35 ft bgs
17Baseline TCE Concentrations, Feb 05 40-45 ft bgs
18Baseline TCE Concentrations, Feb 05 50-55 ft bgs
19Schedule
- Three Months of Air Sparging (120-140 cfm)
- One Month of Rebound Monitoring
- Six Months of Ozone Enhanced Air Sparging ( 7000
ppmv) - Three Months of Rebound Monitoring (Recently
Completed)
20Ozone Injection Performance
- Ozone production began in late July, 2005
- Intermittent operation from July to December
- Mechanical issues desiccant dryer and chiller
- Total aggregate run time 2-1/2 months (50 up
time) - Total mass of ozone delivered 3900 pounds
21Average TCE ConcentrationsZone A Monitoring
Wells (30-35 Screen Depth)
22Average TCE ConcentrationsZone B Monitoring
Wells (40 - 45 Screen Depth)
23Average TCE ConcentrationsZone C Monitoring
Wells (50 - 55 Screen Depth)
24Discussion
- SVE was not conducted because of low permeability
overburden trace levels of TCE measured in
shallow vapor during operation (ppbv) - Air was diverted horizontally by overburden air
bubbling was observed 300 feet from the well - Lateral propagation of air fingering was
estimated to be 50 feet on either side of the
well, as indicated by dissolved oxygen
concentrations - Negligible increases in dissolved chloride from
baseline levels
25Conceptual Model
26Example Dissolved Oxygen and ORP Trend
27Summary of Analytical Data
28Conclusions
- 90 average reduction of TCE within three months
in wells with baseline TCE gt 50 Āµg/L - 99 average reduction within one year in wells
with baseline TCE gt 50 Āµg/L - No significant rebound after three months
(greater than 25 Āµg/L) - Distance of influence 50 ft on both sides of
the well (as indicated by DO measurements) - Possible contribution of ozone to TCE mass
reduction inconclusive - low TCE concentrations
and limited period of operation
29Summary of Costs
- 750K Total Budget
- Horizontal Well, Compressed Air System,
Container, Electrical 250K - Ozone System and Container 300K
- Monitoring 100K
- OM 100K