AMS02 Thermal Test Sequence in the LSS Requests to ESA - PowerPoint PPT Presentation

1 / 38
About This Presentation
Title:

AMS02 Thermal Test Sequence in the LSS Requests to ESA

Description:

ESA required additional information in the meeting at ESTEC to allocate the ... Time estimate for each detector tests. Thermal transient calculations ... – PowerPoint PPT presentation

Number of Views:52
Avg rating:3.0/5.0
Slides: 39
Provided by: mmol6
Category:

less

Transcript and Presenter's Notes

Title: AMS02 Thermal Test Sequence in the LSS Requests to ESA


1
AMS02 Thermal Test - Sequence in the LSS-
Requests to ESA
  • Marco Molina (CGS)
  • Ivan Corradino (CGS)
  • Serena Borsini (UNIPG)

2
Test specifications
  • TVTB Test specification issue 1
  • November 2007
  • ESA required additional information in the
    meeting at ESTEC to allocate the budget and start
    the procurement of the hardware
  • Feb 1st 2008
  • Subdetectors test requirements collected
  • TIM, February 2008
  • TVTB Test specification issue 2
  • Apr 14th 2008

3
Feb 2008- Apr 2008
  • Test requirements have been put in a sequence, to
    optimize test duration
  • First thermal analysis have been done (S. Borsini
    , UNI PG)
  • IR lamps and test hardware to be provided by ESA
    has been identified

4
TV test scope
  • Functional performance verification of the entire
    detector
  • Under vacuum conditions
  • At the extreme achievable thermal environment
    (hot and cold)
  • Respecting the flight hardware limits (WITHIN
    ACCEPTANCE LEVELS)
  • Driven by the test configuration
  • TVT stand
  • IR lamps
  • SUCCESS CRITERION Proper functioning of sub
    detectors and electronics.
  • REMARK IT IS NOT A (PROTO)-QUALIFICATION TEST
  • Equipments and detectors will not necessarily go
    to their flight extremes

5
MATERIALS COMPATIBILITY with vacuum
  • NASA-gtESTEC
  • AMS flight hardware DML
  • AMS-gt ESTEC
  • TVT test stand and all hardware used for the test
    outgassing data
  • AMS-provided cables
  • scaffolding
  • AMS-provided piping
  • valves
  • ESTEC -gt NASA/AMS
  • ESA-provided hardware outgassing data
  • Lamps and their rigs
  • Test MLI
  • Test heaters
  • ESTEC provided pipes

6
LSS shroud
  • LSS shroud will provide an isotropic heat sink at
    a temperature between -100C and 50C
  • When the shroud is cold, the lightest and most
    exposed parts of AMS may be too cold
  • Lower USS electronics

7
IR lamps
  • IR lamps are used
  • To locally warm lightest and most exposed parts
    heat heaters power are not sufficient to keep
    them alive.
  • To create temperature gradients in order to
    simulate high Beta angle thermal environment
    (un-balance thermal loading)
  • To create temperature gradients RAM-WAKE on the
    tracker radiators (Beta 0 like)

8
IR LAMPS
Lamps will be arranged in standard modules
(arranged in a matrix 4 x 2) A module will have a
size of 250 mm x 500 mm.
9
LAMP STANDARD MODULE
10
Lamp group 1 (AMS bottom)
11
LAMP GROUP 2 (ECAL/RICH side)
12
LAMP GROUP 3 (TRD side)
13
LAMP GROUP 4 (Tracker radiator)
14
Lamp groups 5 to 8 TVT stand
15
Lamp groups 9-18
16
Total IR lamps
  • 106 lamps (30 spares)
  • 18 independent controllable power supply
  • 13.25 kW total

17
Venting lines
  • cryogenic system (see paragraph 7.5 , connected
    to port A9)
  • Xe CO2 venting from TRD (connected to port C2).

18
TRD venting
  • TRD venting line shall be provided with a thermal
    control based on
  • an MLI blanket (with effective emittance lower
    than 0.05), wrapped around the pipe and
  • heating power along the pipe, underneath the MLI
    blanket of 2 W per meter length of the tube.
  • The target is to keep the TRD venting pipe at
    -25C.

19
Temperature sensors
  • 350 thermocouples are foreseen for the test
    article.
  • LSS shroud temperature shall be monitored with
    50 sensors to provide information on temperature
    uniformity.
  • 50 sensors shall be used to monitor the TVT
    stand temperature

20
ITEMS TO BE PROVIDED BY ESTEC
  • 450 Temperature sensors (thermocouples) (50
    spares)
  • Some of them, according to Tab. 8-1 will be
    needed in advance for being pre-installed at CERN
  • IR lamps with power supply, controllers and
    cabling, as specified in 7.2.3
  • 106 Lamps 30 spares
  • 18 independent power supply and controllers for
    the IR lamps
  • IR Lamps cabling
  • IR lamps rigs
  • Venting lines
  • TRD gas BOX vent line
  • Pipe inside and outside the LSS
  • Test MLI (0.05 effective emittance) to wrap-up
    the pipe
  • Heaters (2 W / m) underneath the MLI and power
    supply
  • Cryogenic system venting (see paragraph 7.5 )
  • Feed-through
  • AMS Power, Command and Data (see paragraph 7.3 )
  • For Helium lines (see figure Fig. 7-2)
  • For TRD vent lines
  • Test MLI for the LSS floor (as specified in
    paragraph 7.2 )

21
Test sequence
22
Test sequence
  • Time-optimized
  • Bake out
  • Initial coling down checking thermostats clicking
    AMS activation
  • Magnet charge in cold conditions
  • Cold Thermal Balance (TB), in steps. Detectors
    are powered on individually and chamber
    temperature is adjusted accordingly
  • TRD
  • TOF
  • TRACKER and TTCS, AST, GPS, ACC
  • RICH
  • ECAL
  • Power outage simulation at the end of the
    stabilization
  • Hot thermal balance (all ON)
  • A second cold TB, a second hot TB
  • Magnet discharge
  • Re-pressurization

23
At the end of the test each subdetector will have
undergone
  • Partial functional test
  • At ambient before the test
  • In a cold environment (twice)
  • In a hot environment (twice)
  • Transient data (cooling down in case of a power
    loss) will be collected
  • In a cold environment (twice)
  • In a hot environment (twice)
  • Response of some subdetctors (TRD, TOF) to
    environment variation will
  • AMS02 Activation sequence is tested
  • Magnet charge and discharge is tested
  • High beta-angle (heat unbalance) is tested for
    RICH, ECAL and TRD
  • RAM-WAKE unbalance is tested for the TTCS

24
Test steps
  • Functional checkout before vacuum
  • Bake out
  • Initial cooling down
  • Switch on
  • Magnet charge
  • Cold thermal balance
  • Cold to hot transition
  • Hot thermal balance
  • Hot to cold transition
  • Cold thermal balance number 2
  • Hot thermal balance number 2
  • Magnet discharge
  • Re-pressurization
  • Functional checkout at ambient conditions
  • End of the test

25
Bake out and thermostats check-out (initial
cooling down) - 200 hours
26
Switch on sequence and TTCS check-out before
charging the magnet
27
Magnet charge 10 hours
28
Cold thermal balance - 300 hours
29
Detectors switch on sequence in cold thermal
balance
  • Sequence is driven by detectors more sensitive to
    cold behaviour
  • TRD
  • TOF
  • Tracker and TTCS, AST, GPS, ACC
  • RICH
  • ECAL

30
Power outage in a cold case - 10 hours
31
Hot thermal balance 100 hours
32
Power outage in a hot case 10 hours
33
Cold TB number 2 80 hours
34
Hot TB number 2 80 hours
35
Magnet discharge 5 hours
36
LSS chamber re-pressurization 30 hours
37
Overall duration
  • Bake out and thermostats check-out (initial
    cooling down) 200 hours
  • Cold thermal balance (5 plateau) 300 hours
  • Power outage in a cold case 10 hours
  • Hot thermal balance 100 hours
  • Power outage in a hot case 10 hours
  • Cold TB number 2 80 hours
  • Hot TB number 2 80 hours
  • Magnet discharge 5 hours
  • LSS chamber re-pressurization 30 hours
    .
  • TOTAL 815 hours 34 days

38
Conclusions
  • TVTB test spec document can be found at
  • ftp//ftp.cgspace.it/Projects/AMS/TWG/DOC/SPEC/1-L
    SS/TVTB-TEST-SPEC/
  • Coming next TIM July 2008
  • Test duration stimate
  • Time estimate for each detector tests
  • Thermal transient calculations
  • Temperature ranges achievable for the detectors
  • Test procedure to ESTEC Sept 1st 2008
Write a Comment
User Comments (0)
About PowerShow.com