Title: AMS02 Thermal Test Sequence in the LSS Requests to ESA
1AMS02 Thermal Test - Sequence in the LSS-
Requests to ESA
- Marco Molina (CGS)
- Ivan Corradino (CGS)
- Serena Borsini (UNIPG)
2Test specifications
- TVTB Test specification issue 1
- November 2007
- ESA required additional information in the
meeting at ESTEC to allocate the budget and start
the procurement of the hardware - Feb 1st 2008
- Subdetectors test requirements collected
- TIM, February 2008
- TVTB Test specification issue 2
- Apr 14th 2008
3Feb 2008- Apr 2008
- Test requirements have been put in a sequence, to
optimize test duration - First thermal analysis have been done (S. Borsini
, UNI PG) - IR lamps and test hardware to be provided by ESA
has been identified
4TV test scope
- Functional performance verification of the entire
detector - Under vacuum conditions
- At the extreme achievable thermal environment
(hot and cold) - Respecting the flight hardware limits (WITHIN
ACCEPTANCE LEVELS) - Driven by the test configuration
- TVT stand
- IR lamps
- SUCCESS CRITERION Proper functioning of sub
detectors and electronics. - REMARK IT IS NOT A (PROTO)-QUALIFICATION TEST
- Equipments and detectors will not necessarily go
to their flight extremes
5MATERIALS COMPATIBILITY with vacuum
- NASA-gtESTEC
- AMS flight hardware DML
- AMS-gt ESTEC
- TVT test stand and all hardware used for the test
outgassing data - AMS-provided cables
- scaffolding
- AMS-provided piping
- valves
-
- ESTEC -gt NASA/AMS
- ESA-provided hardware outgassing data
- Lamps and their rigs
- Test MLI
- Test heaters
- ESTEC provided pipes
6LSS shroud
- LSS shroud will provide an isotropic heat sink at
a temperature between -100C and 50C - When the shroud is cold, the lightest and most
exposed parts of AMS may be too cold - Lower USS electronics
7IR lamps
- IR lamps are used
- To locally warm lightest and most exposed parts
heat heaters power are not sufficient to keep
them alive. - To create temperature gradients in order to
simulate high Beta angle thermal environment
(un-balance thermal loading) - To create temperature gradients RAM-WAKE on the
tracker radiators (Beta 0 like)
8IR LAMPS
Lamps will be arranged in standard modules
(arranged in a matrix 4 x 2) A module will have a
size of 250 mm x 500 mm.
9LAMP STANDARD MODULE
10Lamp group 1 (AMS bottom)
11LAMP GROUP 2 (ECAL/RICH side)
12LAMP GROUP 3 (TRD side)
13LAMP GROUP 4 (Tracker radiator)
14Lamp groups 5 to 8 TVT stand
15Lamp groups 9-18
16Total IR lamps
- 106 lamps (30 spares)
- 18 independent controllable power supply
- 13.25 kW total
17Venting lines
- cryogenic system (see paragraph 7.5 , connected
to port A9) - Xe CO2 venting from TRD (connected to port C2).
18TRD venting
- TRD venting line shall be provided with a thermal
control based on - an MLI blanket (with effective emittance lower
than 0.05), wrapped around the pipe and - heating power along the pipe, underneath the MLI
blanket of 2 W per meter length of the tube. - The target is to keep the TRD venting pipe at
-25C.
19Temperature sensors
- 350 thermocouples are foreseen for the test
article. - LSS shroud temperature shall be monitored with
50 sensors to provide information on temperature
uniformity. - 50 sensors shall be used to monitor the TVT
stand temperature
20ITEMS TO BE PROVIDED BY ESTEC
- 450 Temperature sensors (thermocouples) (50
spares) - Some of them, according to Tab. 8-1 will be
needed in advance for being pre-installed at CERN - IR lamps with power supply, controllers and
cabling, as specified in 7.2.3 - 106 Lamps 30 spares
- 18 independent power supply and controllers for
the IR lamps - IR Lamps cabling
- IR lamps rigs
- Venting lines
- TRD gas BOX vent line
- Pipe inside and outside the LSS
- Test MLI (0.05 effective emittance) to wrap-up
the pipe - Heaters (2 W / m) underneath the MLI and power
supply - Cryogenic system venting (see paragraph 7.5 )
- Feed-through
- AMS Power, Command and Data (see paragraph 7.3 )
- For Helium lines (see figure Fig. 7-2)
- For TRD vent lines
- Test MLI for the LSS floor (as specified in
paragraph 7.2 )
21Test sequence
22Test sequence
- Time-optimized
- Bake out
- Initial coling down checking thermostats clicking
AMS activation - Magnet charge in cold conditions
- Cold Thermal Balance (TB), in steps. Detectors
are powered on individually and chamber
temperature is adjusted accordingly - TRD
- TOF
- TRACKER and TTCS, AST, GPS, ACC
- RICH
- ECAL
- Power outage simulation at the end of the
stabilization - Hot thermal balance (all ON)
- A second cold TB, a second hot TB
- Magnet discharge
- Re-pressurization
23At the end of the test each subdetector will have
undergone
- Partial functional test
- At ambient before the test
- In a cold environment (twice)
- In a hot environment (twice)
- Transient data (cooling down in case of a power
loss) will be collected - In a cold environment (twice)
- In a hot environment (twice)
- Response of some subdetctors (TRD, TOF) to
environment variation will - AMS02 Activation sequence is tested
- Magnet charge and discharge is tested
- High beta-angle (heat unbalance) is tested for
RICH, ECAL and TRD - RAM-WAKE unbalance is tested for the TTCS
24Test steps
- Functional checkout before vacuum
- Bake out
- Initial cooling down
- Switch on
- Magnet charge
- Cold thermal balance
- Cold to hot transition
- Hot thermal balance
- Hot to cold transition
- Cold thermal balance number 2
- Hot thermal balance number 2
- Magnet discharge
- Re-pressurization
- Functional checkout at ambient conditions
- End of the test
25Bake out and thermostats check-out (initial
cooling down) - 200 hours
26Switch on sequence and TTCS check-out before
charging the magnet
27Magnet charge 10 hours
28Cold thermal balance - 300 hours
29Detectors switch on sequence in cold thermal
balance
- Sequence is driven by detectors more sensitive to
cold behaviour - TRD
- TOF
- Tracker and TTCS, AST, GPS, ACC
- RICH
- ECAL
30Power outage in a cold case - 10 hours
31Hot thermal balance 100 hours
32Power outage in a hot case 10 hours
33Cold TB number 2 80 hours
34Hot TB number 2 80 hours
35Magnet discharge 5 hours
36LSS chamber re-pressurization 30 hours
37Overall duration
- Bake out and thermostats check-out (initial
cooling down) 200 hours - Cold thermal balance (5 plateau) 300 hours
- Power outage in a cold case 10 hours
- Hot thermal balance 100 hours
- Power outage in a hot case 10 hours
- Cold TB number 2 80 hours
- Hot TB number 2 80 hours
- Magnet discharge 5 hours
- LSS chamber re-pressurization 30 hours
. - TOTAL 815 hours 34 days
38Conclusions
- TVTB test spec document can be found at
- ftp//ftp.cgspace.it/Projects/AMS/TWG/DOC/SPEC/1-L
SS/TVTB-TEST-SPEC/ - Coming next TIM July 2008
- Test duration stimate
- Time estimate for each detector tests
- Thermal transient calculations
- Temperature ranges achievable for the detectors
- Test procedure to ESTEC Sept 1st 2008