Title: Maine Financial and Administrative Statewide Information System MFASIS Upgrade Project


1
Maine Financial and Administrative Statewide
Information System (MFASIS) Upgrade Project
  • Agency Interface Status Meeting

May 17, 2006
2
MFASIS Upgrade Project
  • Agenda
  • Integrated Testing
  • Certification Criteria
  • Check Mailing/Distribution
  • Simulated Production Testing
  • Interface Testing Schedule
  • Securing Data Transmissions
  • Next Status Meeting June 21

3
Integrated Testing
4
MFASIS Upgrade ProjectIntegrated Testing
  • Testing in progress May 15 May 26
  • BIE training conducted
  • PDF files of 20-30 sample check images will be
    provided, let us know if additional images are
    needed
  • Certification letter will be issued

5
Certification Criteria
6
MFASIS Upgrade ProjectCertification Criteria
  • Agency must meet all certification criteria
    during integration testing
  • Full size parallel file is FTPd with INF file
  • Agency business staff adds BIE entry online
  • Detail, INF, and BIE must reconcile
  • All documents must process successfully through
    batch cycle
  • A limited number of checks will be supplied to
    the agency
  • A payment feedback file will be provided to
    agency
  • Agency must acknowledge that they can process the
    new payment feedback and vendor/customer files
  • Agency must review and accept the check output
  • Agency must reconcile payment feedback file with
    production file
  • Formal sign-off (certification letter) must be
    done by Controllers Office and agency

7
Check Mailing/Distribution
8
MFASIS Upgrade ProjectCheck Mailing /
Distribution
  • OIT/DOL printing operation will
  • Print Checks
  • Fold stock and stuff envelopes
  • Prepared for mailing
  • Special handling situations will require the
    setting of the vendor disbursement category in
    the vendor component of the GAX or PRC document
    to one of the following values
  • MRS Tax refunds requiring special envelopes
  • MS DHHS provider payments, courier pickup
  • TR Delivery to Treasury for agency pickup,
    requires pre-approval from Controllers Office

9
Simulated Production Testing
10
MFASIS Upgrade ProjectSimulated Production
Testing
  • Test of production environment
  • Test software modifications
  • Test production interface FTP site details will
    be provided in June
  • All interface partners must provide parallel
    production file
  • Utilize same guidelines as integrated testing

11
MFASIS Upgrade ProjectSimulated Production
Testing contd
  • Simulated Production Testing Guidelines
  • Use parallel production files
  • New vendor and customer crosswalk file will be
    provided the first week of June
  • Agency will FTP files and email Kishore include
    the date the file was originally processed in
    production
  • INF control file will be required, must use
    correct unit code
  • Each interface is assigned a processing date for
    testing purposes (see attached integration
    schedule doc.)
  • Agency files due no later than at noon (June
    26-30) on their scheduled submission date
  • INF batch id and import date must reflect
    assigned test date
  • INF and document file names must reflect assigned
    test date

12
MFASIS Upgrade ProjectSimulated Production
Testing contd
  • Test check distribution category, if appropriate
  • Scheduled payment date edit
  • Sched. Payment date must be or system date
  • Edit will be relaxed to accommodate integrated
    testing
  • Agency will make BIE entry online
  • File and batch id naming conventions must be
    followed
  • Batch interface processing will be fully tested
  • Payment feedback file will be provided
  • PDF file of sample checks will be provided
  • Simulated production testing of interfaces to be
    completed at the beginning of July

13
Interface Testing Schedule
14
MFASIS Upgrade Project Interface Testing Timelin
e
Test All Functions
4/19 6/2
Integration Testing
5/15 6/2
Interface Testing
Interface Certification
5/15 6/15
Test All Functions
6/12 7/20
Simulated Production Testing
6/26 6/30
Interface Testing
Review Results
7/1 7/15
15
Securing Data Transmissions
16
MFASIS Upgrade ProjectSecuring Data Transmissions
  • Transactions will be processed through Momentum
    FTP server instead of directly to MFASIS FTP
  • Directory structure will be exactly the same,
    userids will change.
  • Scripts will need to be changed so that files are
    transmitted to the Momentum server instead of
    the MFASIS server Information will be provided
    to agencies regarding server name.
  • For now Push and Pull from Server May be able
    to automate processes in the future.
  • Cleanup of outbound feedback files on the
    Momentum server will be the responsibility of the
    agencies, MFASIS will delete inbound files as
    they are used.
  • Ability to use different clients such as a free
    client from Momentum, Cute FTP, Move It Buddy,
    and WS/FTP Pro.
  • Investigating and testing web mailboxes for
    future HTTPS transfers.

17
MFASIS Upgrade Project
  • Next Status Meeting June 21