Title: Task7: NUSTAR2 Design and Prototype Construction of a RadiationResistant Magnet
1Task7 NUSTAR2 - Design and Prototype
Construction of a Radiation-Resistant Magnet
Martin Winkler Kick-off meeting EU DS
"DIRACsecondary-Beams", April 14-15, 2005, GSI,
Darmstadt, Germany
- The Pre-Separator of the Super-FRS
- Sub-Tasks of NUSTAR2 (Choice)
- Implementation Plan, Milestones Deliverables
- Project Resources and Budget
Task leader of NUSTAR2 Gebhard Moritz, GSI
2Design parameters and layout of the Super-FRS
Design Parameters
High-radiation area
- Large phase space ? large aperture magnets
- High beam energies large apertures
- ? high pole tip fields for quadrupols
- ? use superconducting magnets
3Requirements of Magnetic Elements of the
Preseparator
Can the magnets stay superconducting after the
target and beam dumps?
PF2
1,3
4Beam dump locations in the 1st stage of the
Pre-Separator
Trajectories of primary beams with different
DBr/ Brbeam
Target
Beam Dumps
Light fragments
The primary beam is always dumped in well-defined
positions outside the magnets !
5Exploration of radiation load on magnets behind
the high-power production target
Projectile 1500 MeV/u 238U 1012/s sx
1.0 mm sy 2.0 mm sp /p 0.5
Energy deposition distribution (calculated with
PHITS)
Target Carbon 4 g/cm2
Geometry
Avarage energy depositionon on the coil surface
ltDEgt/M 0.46 mJ/g (quench limit 2-3
mJ/g) Heat load on the cryogenic system for a 5
ton quadrupole magnet Expected FAIR cryogenic
power 20 kW
2.3 kW
6Exploration of radiation load on magnets behind
the beam dumps
Projectile 1500 MeV/u 238U 1012/s
sp/p 0.5 sy
1.0 cm sx 4.0 cm
(ltDEgt/M)coil 0.3 mJ/g limit 2-3 mJ/g
(ltDEgt/M)coil 0.76 mJ/g limit 2-3 mJ/g
7Radiation sensitivity of coil materials and
insulator
Behind target and beam dump Expected heat
load 1 mJ/g
? is equivalent to a
dose rate of 1 Gy/s
Assume 4000 h/year operation time ? 14 MGy
accumulated dose
? Ceramic
insulation is required
8Radiation resistant (normal-conducting) magnet
Magnet Cross Section
Parameter B 1.6 T I 600
A J 1.5 A/mm2 P 50 kW ?B/B
210-4 ?R 20 cm Weights (12.5 m, 11)
Fe 72 t Cu 9.5 t
Coil Cross Section
9Conceptual design of a high-precision Survey and
Alignment System for high-radiation areas of FAIR
After commissioning of the SuperFRS a very high
level of radiation is expected. SA "as usual"
will not be possible due to prohibited or limited
access.
No access of human personnel High demands on
accuracy (some 1/10 of mm) Handling curved
beamlines with a length up to 50 m
"RALF" - Remote ALignment on the Fly Based on
Photogrammetry non-contact high accuracy data
capture within a short time Automated guided
vehicle system Remotely controlled adjustment of
accelerator components
in cooperation with i3mainz Institute for Spatial
Information and Surveying Technology
10Multi-annual implementation plan for NUSTAR2
11Participating institutes in task7 (NUSTAR2)
12Milestones and Deliverables of NUSTAR2
- Milestones
- M7-1 Decision on insulating material, 10/2005
- M7-2 Delivery of model coil, 9/2006
- M7-3 Design and test for Surveying and
alignment system - finished, 4/2007
- M7-4 Prototype Magnet delivered, 12/2007
- Deliverables
- D13 Report on exploration of conductor and
cable, 1/2006 - D14 Report on the model coil, 1/2007
- D15 Report on surveying and alignment system
for high- - radiation areas, 7/2007
- D16 Report on design and construction of the
prototype - magnet, 12/2007
13Summary of Project Resources and Budget of the
DP NUSTAR
The requested 589 k from the EU correspond to
41 of the overall EU request for the DP NUSTAR