NEW PRIVATE FORM OF NOMINATED SUBCONTRACT By Gregory Tung W: http:www.jrk.com.hk E: gregory.tungjrkn - PowerPoint PPT Presentation

1 / 68
About This Presentation
Title:

NEW PRIVATE FORM OF NOMINATED SUBCONTRACT By Gregory Tung W: http:www.jrk.com.hk E: gregory.tungjrkn

Description:

http://www.jrk.com.hk. NEW PRIVATE FORM OF NOMINATED SUB-CONTRACT ... Tortious solution. Event materially caused delay suffices. http://www.jrk.com.hk. Emden ... – PowerPoint PPT presentation

Number of Views:552
Avg rating:3.0/5.0
Slides: 69
Provided by: janeg7
Category:

less

Transcript and Presenter's Notes

Title: NEW PRIVATE FORM OF NOMINATED SUBCONTRACT By Gregory Tung W: http:www.jrk.com.hk E: gregory.tungjrkn


1
NEW PRIVATE FORM OF NOMINATED SUB-CONTRACT By
Gregory TungW http//www.jrk.com.hkE
gregory.tung_at_jrknowles.com
2
  • Clause 1 definitions of terms

3
  • Clause 2 combines Green form Clauses 1 and 3

4
  • Same problems regarding incorporation of main
    contract terms remain

5
  • Paras 1039 to 1042 of
  • Emdens Construction Law Vol 1

6
  • Clause 3 NSCs obligations include organize and
    co-ordinate

7
  • Clause 4 changes Green form Clause 5

8
  • Main contractor is responsible for care of the
    sub-contract works

9
  • Under Green form, there is no express provision
    deals with the question of protection of
    sub-contract works

10
  • Now is same as the Hong Kong Government Form of
    Sub-Contract (deals with this matter in Clause
    13). The main contractor is responsible except
    insofar as the damage arises from the
    sub-contractors negligence.

11
  • Materials on site etc,
  • they are at NSCs risk

12
  • NNSC Clauses 4(1) and 22 do not sit well.
  • NNSC Clause 4(1) the main contractor is not
    responsible for care of the Sub-Contract works if
    the loss and damage arise from Excepted Risks.
  • NNSC Clause 22.2 NSC shall be responsible for
    restoration of lost or damaged Sub-Contract works
    except for those covered by CAR, by Excepted
    Risks or by Main Contractors/Employers default.
  • So who is responsible for damages caused by
    Excepted Risks?

13
  • If damages to Sub-Contract works are not covered
    by CAR, NSC is responsible for restoration under
    NNSC Clause 22.2.
  • NNSC Clause 22.4(2) limits NSCs recovery for
    damages covered by CAR to its share under CAR.
  • Contrary to NNSC Clause 4(1), NNSC Clause 22
    puts NSC to take care of the Sub-Contract works.

14
  • NNSC Clause 14.1 says the quantity and
    quality of work included in the Sub-Contract Sum
    shall be deemed to be that set out in the
    Sub-Contract Bills
  • Change in billed quantities variation
  • The clause is not an optional clause which in
    itself does not cater for situation where the
    sub-contract is let on specification and drawings.

15
  • Clause 23 two alternative treatments regarding
    completion of sub-contract works

16
Subcontractor's duties obligations Progress
17
To suit MC progress of works
18
Harsh arrangement
19
To compromise practicality
20
Cases
21
Subcontractor's duties obligationsCases on
Progress
22
Subcontractor's duties obligations Cases on
Progress
23
Tridant v. Mansion, 15 June 2000, HCCT 3 66 of
1996
24
Tridant v Mansion
  • KGJV (Main Contractor) To build in Guangzhou
  • Tridant (To conform Main Contractors programme)
  • (ME)
  • Mansion
  • (PD FS)

(back to back) to confirm Tridants and Main
Contractors programme
25
Court decision in Tridant case
26
Kitsons Sheet Metal case
27
Kitsons Sheet Metal (1989) 47 BLR 82
BAA Management contract, V.O. include
change of sequence TWC Matthew Hall
(Defendant) (Installation and insulation of
pipes/ducts) Refer to contracts between BAA and
TWC and between TWC and Matthew Hall Clause
18(1) plus 6th Schedule - Complete as per
defendants order Kitsons (Plaintiff) (Insulat
ion)
28
Court decision in Kitsons
29
Failure to completeCausation
30
Failure to complete Causation
31
NNSC Cl 24 / Green Form Cl 8(a)
32
Law on causation concurrent delay
33
Keating
34
Devlin
  • The one constitutes breach suffices

35
Dominant cause
  • Which delay has greater effect?

36
Burden of proof
  • To prove other's delay much greater than your
    breach

37
Tortious solution
  • Event materially caused delay suffices

38
Emden
39
Practical Legal Guide to FIDIC
40
Failure to completeRemoteness of damages
41
Failure to complete Remoteness of damages
42
Loss must not be
43
Hadley v. Baxendale
44
Keating Whether S/C normally knows of LD in MC
45
Keating Settlement of claim
46
  • Clause 24 governs damages for delay in completing
    the sub-contract works, viz NSC is liable to the
    main contractor for its loss and damages and LD
    incurred which are caused by the sub-contractors
    failure to complete.

47
  • Clause 25 deals with EOT.
  • Two notices required (28 28 days)

48
  • Clause 28 deals with NSCs claim for loss and
    expense but unlike the Green form, it now covers
    those caused by the main contractors breach.

49
  • Notice requirement.
  • Condition precedent.

50
  • Clause 33.1(7) still a pay when paid clause with
    14 days . Of the Contractor receiving payment
    from the Employer.

51
  • Set Off

52
  • Chinney v Po Kwong Marble (2003)

53
  • Clause 33.13 late payment carries interest

54
  • Clause 33.14 late payment entitles to suspension
    of works

55
  • Clause 33.9 to 33.11
  • conclusiveness of the final certificate

56
  • Clause 34 surety

57
  • Clause 37 now provides for NSCs determination

58
  • Clause 41 main contractors set off subject to
    pre-condition of serving notice by special
    delivery at least 7 days before deduction

59
TYPES OF SET OFF
  • There are 5 types of set off
  • 1.      Abatement
  • 2. Legal or Common Law set off
  • 3.      Equitable set off
  • 4.      Set off under the Contract
  • 5.      Statutory set off

60
ABATEMENT
  • With building contracts, the defendant does not
    need to set off (by a cross-action) the amount
    of damages he has sustained, but simply to defend
    himself by showing how much less the value of the
    claimants claim is by deducting the damages
    caused by the claimants breach.

61
LEGAL OR COMMON LAW SET OFF
  • B Hargreaves Ltd v Action 2000 Ltd (1992)
  •  
  • Plaintiff wanted to set off for work which had
    been omitted or not carried out correctly.
  •  
  • The Court of Appeal held that a set-off in common
    law is only available where the claims on both
    sides are in respect of liquidated debts or money
    demands which could readily and without
    difficulty be ascertained and that the claim
    which the defendant sought to set off were not
    liquidated debts but were claims which could only
    be ascertained by litigation or arbitration.

62
EQUITABLE SET OFF
  • Dole Dried Fruit v Trustin Kenwood (1990)
  •  
  • The test of whether a cross-claim can be relied
    as equitable set off is whether it is so closely
    connected with the claim that it would be
    manifestly unjust to allow the claim without
    taking into account the cross-claim.
  •  
  • Hanak v Green (1958)
  •  
  • Employer claimed damages for failure to complete
    properly. Contractor entitled to set off for
    additional work outside the Contract on quantum
    meruit.

63
STATUTORY SET OFF
  • For example Section 323 of the Insolvency
  • Act 1986
  • and
  • Section 212 of the Companies Ordinance
  • Cap 32

64
CONTRACTUAL SET OFF
  • Parties are free to agree any terms of set-off,
    including any exclusion of right of set off.
  •  
  • For example, the arrangement under NNSC Clause
    41. 

65
CONTRACTUAL SET OFF
  • See further
  • Dawnay v Minter (1971)
  • Gilbert Ash v Modern Engineering (1973)
  • Pilecon v Mightyton (1991)
  • Ryoden Engineering v Paul Y Construction (1991)
  • Steward Gill v Horatio Myer (1992)
  •  

66
CONTRACTUAL SET OFF
  • Where the contractual right of set-off is for the
    deduction of a cross-claim, this right is
    available (irrelevant of the Contract) under
    Common Law or Equitable set off.
  •  
  • However, in the absence of an express power in
    the Contract, set off can NOT (normally) be made
    against another unconnected contract between the
    parties.

67
CONTRACTUAL SET OFF
  • See further
  • Paul Y Construction Co Ltd v AG of Hong Kong
    (1992)
  • Anglian Building Products Ltd v WC French
    (Construction) Ltd (1972)

68
  • Clause 42 dispute resolution
  • At request of either party, Architect has to
    refer dispute to designated representatives. If
    not resolved, mediation, then arbitration.
  • Certificate final and binding under main contract
    is also final and binding on sub-contract.
  • Clause 43 name borrowing
Write a Comment
User Comments (0)
About PowerShow.com