Progress Photos March 2007 - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Progress Photos March 2007

Description:

Taxis were relocated to new rank on 9 March 2007. Official opening took place on 15 March 2007 ... Demolition of old taxi rank commenced on 12 March 2007 ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 16
Provided by: thebenm
Category:
Tags: march | photos | progress | taxis

less

Transcript and Presenter's Notes

Title: Progress Photos March 2007


1
Progress PhotosMarch 2007
2
Construction Progress
  • Park Station

General views of construction activities
Portal Shaft Excavation 16 March 2007
View towards South 16 March 2007
3
Construction Progress
  • Rosebank

View towards South 16 March 2007
General views of construction site, road
diversion and pedestrian footbridge spanning
Oxford Road and station site
View towards South 16 March 2007
View towards North 16 March 2007
4
Construction Progress
  • Rosebank

Site establishment is ongoing
Batch Plant 16 March 2007
Wheel Wash Pit 16 March 2007
5
Construction Progress
  • Shaft E5

Shaft depth 24 metres at 20 March 2007
Looking down from Platform 20 March 2007
Looking up from Platform 20 March 2007
6
Construction Progress
  • Sandton Station

New Taxi Rank 20 March 2007
Taxis were relocated to new rank on 9 March
2007 Official opening took place on 15 March
2007 Demolition of old taxi rank commenced on 12
March 2007
Demolition of Old Taxi Rank 20 March 2007
7
Construction Progress
  • Sandton Station

Completed Panels 20 March 2007
Diaphragm wall construction 4 D-Wall panels
concreted on 16 March 2007
Cutter Excavation at North Shaft 20 March 2007
8
Construction Progress
  • Mushroom Farm Park

Shaft depth 15 metres at 20 March 2007
Blast Preparation 19 March 2007
Mucking Out 20 March 2007
Blast Protection Grids 19 March 2007
9
Construction Progress
  • Marlboro Portal

Third set of canopy tubes installed Arch ribs
visible in preceding sections 29 metres of
tunnel excavated by 23 March 2007
View from Portal 20 March 2007
Santa Barbara 20 March 2007
10
Construction Progress
  • Marlboro Viaducts

View towards South 22 March 2007
View towards South showing Marlboro Station site
in foreground, Viaducts 1a and 11 in centre and
clearing of alignment towards Marlboro Portal
behind Piling (4 piles as at 23 March 2007) and
foundations in progress
Piling at Viaduct 11 22 March 2007
Foundations V11 and V1a 22 March 2007
11
Construction Progress
  • Area 2
  • Marlboro to Depot Section

Clearing and grubbing, topsoil stripped, and
earthworks in progress from Linbro Junction to
Depot
View towards Depot 19 March 2007
View towards East (behind Linbro) 19 March 2007
View from Landfill 19 March 2007
12
Construction Progress
  • Depot

Bulk earthworks to both Train and Bus Depot areas
is complete
Train Depot Earthworks Platform 20 March 2007
Bus Depot Admin Building 20 March 2007
13
Construction Progress
  • Depot
  • Precast Yard

Construction of M-Beam casting beds
M-Beam Pits 20 March 2007
M-Beam Pit Walls 20 March 2007
M-Beam Soffits 20 March 2007
14
Construction Progress
  • Viaduct 13

First lift of Pier 8 being backfilled Shutter
erected for first lift of Pier 7 on the opposite
side of Centenary Way
15
Construction Progress
  • OR Tambo Station

The station concourse shell is being constructed
by ACSA above the new elevated drop-off road CJV
site establishment at ORT will commence at the
end of March
Station Concourse Shell 22 March 2007