Overview of ATLAS Liquid Argon Frontend Crate Electronics John Parsons Nevis Labs, Columbia Universi - PowerPoint PPT Presentation

About This Presentation
Title:

Overview of ATLAS Liquid Argon Frontend Crate Electronics John Parsons Nevis Labs, Columbia Universi

Description:

DMILL Analog Reticle opamp, DAC, BiMUX. DMILL Digital Reticle SPAC, CALogic, Config, MUX. DSM Digital Reticle SCA Controller, GainSelector, CLKFO ... – PowerPoint PPT presentation

Number of Views:61
Avg rating:3.0/5.0
Slides: 38
Provided by: CdLT9
Category:

less

Transcript and Presenter's Notes

Title: Overview of ATLAS Liquid Argon Frontend Crate Electronics John Parsons Nevis Labs, Columbia Universi


1
Overview ofATLAS Liquid ArgonFrontend Crate
ElectronicsJohn ParsonsNevis Labs, Columbia
UniversityLAr Electronics ASSO Review, June 17
2002
ATLAS
2
Overview of ATLAS Liquid Argon (LAr) Calorimeter
Readout
3
Requirements of ATLAS LAr Frontend Crate
Electronics
  • read out ? 170k channels of calorimeter
  • dynamic range ? 16 bits
  • measure signals at bunch crossing frequency of 40
    MHz (ie. every 25 ns)
  • store signals during L1 trigger latency of up to
    2.5 ?s (100 bunch crossings)
  • digitize and read out 5 samples/channel at a max.
    L1 rate of 100 kHz
  • measure deposited energies with resolution lt
    0.25
  • measure times of energy depositions with
    resolution ltlt 25 ns
  • high density (128 channels per board)
  • low power (? 0.8 W/channel)
  • high reliability over expected lifetime of gt 10
    years
  • must tolerate expected radiation levels (10 yrs
    LHC, no safety factors) of
  • TID 5 kRad
  • NIEL 1.6E12 n/cm2 (1 MeV eq.)
  • SEU 7.7E11 h/cm2 (gt 20 MeV)

4
ATLAS LAr Frontend Crate Electronics Overview
  • On-detector electronics
  • Boards tested functionally on Mod 0
  • ATLAS rad-tol boards being finalized

Controller 116 boards
Calibration 116 boards _at_ 128 ch
Front End Board (FEB) 1524 boards _at_ 128 ch
Tower builder (TBB) 120 boards _at_ 32 ch
5
Module 0 Electronics Experience
  • Full functionality Module 0 CALIB and FEB
    boards were developed
  • Provided verification of the electronics design
    concepts
  • Used in testbeam runs with Module 0 and
    production calorimeter modules
  • Several CALIB boards and ? 6000 channels of FEBs
    were produced
  • Have been operating reliably in testbeam for
    past several years
  • Performance meets or exceed ATLAS specifications
  • Prototype Controller board was evaluated in
    dedicated test
  • Due to schedule, Mod0 boards developed with some
    short cuts
  • Did not use final control signal (TTC and SPAC)
    distribution
  • FEB used Cu output cables instead of optical
    links
  • Did not pay strict attention to radiation
    tolerance requirements
  • the main task remaining in the development of the
    final ATLAS boards was to radiation harden the
    designs, and in particular to replace several
    FPGAs and other COTs with custom rad-tol ICs

6
On-detector electronics control interfaces
  • LAr on-detector electronics uses common control
    signal distribution
  • TTC for 40 MHz CLK, L1Accept and other fast
    signals
  • SPAC serial protocol for downloading/reading
    back configuration parameters
  • Controller Board (one per 1/2 crate) is connected
    optically to external TTC system and SPAC Master,
    and fans signals out electrically to each of the
    boards within its 1/2 crate
  • Redundancy has been implemented to increase
    reliability, with no logic switching components
    required on-detector
  • TTC and SPAC Master ? Slave (MS) signals sent on
    two separate fibers each, with off-detector
    selection of which will be active
  • On-detector electronics configured to drive both
    of the SPAC Slave ? Master (SM) links
  • SPAC MS and SM redundancy preserved on SPAC bus
    (though Controller is common and must therefore
    be VERY reliable)

7
On-detector electronics control interfaces
(contd)
  • TTC
  • TTC fanount within crate is point-to-point over
    halogen-free USB2.0 mini-B cables connected
    through the boards front panels
  • Each board has TTCRx chip to receive 80 MHz
    encoded TTC signals
  • SPAC
  • Manchester-encoded serial protocol combining CLK
    and data with 20 MHz edges
  • Implementation uses separate (ie.
    uni-directional) MS and SM lines
  • SPAC signals are fanned out via SPAC bus,
    implemented as a PCB along the side of the crate
    with through comb connectors to boards
  • Each board has SPAC Slave to receive/transmit
    SPAC data using either 8-bit parallel interface
    or one of two I2C interfaces provided by SPAC
    Slave
  • Final SPAC Slave version includes separate
    address and data partial checksums for better
    fault and SEU tolerance
  • Some concerns
  • Cabling of TTC cables on crate, while still
    allowing extraction of single boards
  • Robustness/fault tolerance of SPAC bus (will be
    tested in system crate test)
  • Robustness/fault tolerance of Controller

8
Controller Board Overview (LPNHE-Paris)
9
Connectors on Controller
Up to 22 TTC connectors (by pairs on the 2 faces)
Optical Part for TTC and SPAC
TTC (USB mini-B) connector pinout
1 GND 2 (D-)TTC- 3 (D)TTC 4 not
connected 5 GND
shield connected to GND
10
Controller Board Status
  • Test board produced to evaluate fanout issues
  • Design of full prototype board underway delivery
    to BNL by September
  • Radiation tests of SPAC Slave V3 and optical
    receiver by end June

11
Controller Board Responsibility Chart
12
Calibration Board Overview (Annecy, Mainz,
Orsay)
  • Generate 0.1 precision calibration pulses
  • Rise time lt 1 ns
  • Current pulse amplitude from 200 nA up to 10 mA
  • Delay programmable from 0 to 24 ns in 1 ns steps
  • Number of current pulsers per CALIB board is 128

13
Overview of Main CALIB Components
DMILL
AMS
COTS
Enable
Spac
VDAC
6 CALogic
128 opamp 10 µV offset
1 DAC 16 bits
1 SPAC
128 Output signals
IDAC
TTC
CMD
16 driver
128 HF switch
1 TTCRx
2 delay
4 pos. Vreg and 1 (non-essential?) neg. Vreg
14
CALIB Control Interfaces
  • SPAC slave used only as I2C master, with one I2C
    link used for TTCRx and Delay chips, and the
    other I2C link used for all the other chips

15
Digital CALIB Testboard
  • Developed to test integration of digital ASICs on
    CALIB board
  • Tests with TTCRx, SPAC Slave, 2 Delay chips, 6
    CALogic all OK

16
8 Channel CALIB Prototype
  • Include digital control plus analog chain for 8
    channels
  • 3 boards received in April 02
  • Design of full-sized 128 channel board is
    underway delivery to BNL by Oct.

17
CALIB Responsibility Chart
18
Frontend Board Overview (Nevis)
  • functionality includes
  • receive input signals from calorimeter
  • amplify and shape them
  • store signals in analog form while awaiting L1
    trigger
  • digitize signals for triggered events
  • transmit output data bit-serially over optical
    link off detector
  • provide analog sums to L1 trigger sum tree

19
Overview of main FEB components
DMILL
AMS
DSM
COTS
  • 10 different custom rad-tol ASICs, relatively few
    COTs

128 input signals
32 SCA
16 ADC
8 GainSel
1 MUX
32 Shaper
32 0T
1 fiber to ROD
Analog sums to TBB
1 GLink
1 Config.
2 SCAC
2 LSB
TTC, SPAC signals
14 pos. Vregs 6 neg. Vregs
1 TTCRx
7 CLKFO
2 DCU
1 SPAC
20
FEB Analog Interfaces
  • Input signals
  • 128 signals per FEB, using the two outer rows of
    the two 96-pin VME-style DIN connectors
  • Middle row of 32 pins of each signal connector
    are shared Ground pins (ie. one GND pin per 2
    signal pins)
  • Signal connectors equipped with custom shields
    and additional grounding contacts, with mating
    springs mounted on crate baseplane
  • Mod 0 demonstrated this is necessary to achieve
    coherent noise specification
  • Output analog trigger sums
  • First level of summing provided by shaper chips,
    configured via switches to enable/disable
    individual channels
  • Next level of summing provided by plug-in Layer
    Sum Boards (LSB), the output stages of which
    drive the sums through the middle FEB connector
    to the baseplane, where they are routed to the
    TBB (or TDB for HEC)
  • LSB sums depend on calorimeter region, with up to
    32 separate O/P sums
  • Remaining 64 pins are GND pins, with GNDs
    separating adjacent signals

21
FEB Control Interfaces
Left Gain selector 0
..
Shaper 0
Shaper 1
Shaper 31
Left Gain selector 1
TTCRx
23
Left Gain selector 2
5 MHz
I2C_0
Left Gain selector 3
4
Configuration controller
Right Gain selector 0
data70
subadd60
4
SPAC slave
n_read
n_write
Right Gain selector 1
Right Gain selector 2
I2C_1
8
8
4
Right Gain selector 3
4

Left SCA controller
Right SCA controller
Regulator 19
Regulator 0
DCU 1
DCU 0
22
FEB Optical Links
  • one GLink output link per FEB, with rate of 1.6
    Gbps
  • link collaboration includes SMU, ISN,
  • Stockholm, and Taiwan
  • FEB integration complete (ROD integ. underway)

1.6 Gb/s
23
1/4 Digital FEB
  • Test setup for FEB digital ASICs
  • Complete operation of SCAC, GainSel, Config,
    SPAC, TTCRx, MUX, GLink
  • Allowed quick testing/integration of new ASICs as
    they became available
  • Integration was carried over to FEB design, which
    worked properly first time

DMILL TTCRx
Optical Tx
Agilent GLink
DMILL SPAC
DMILL MUX
DMILL Config controller
DSM/DMILL Gain selector
DSM/DMILL SCA Controller
24
FEB Prototype
  • 128 channels/FEB
  • large 10 layer PCB
  • components on both
  • sides to achieve density
  • layout, with STm
  • Vregs, done Oct. 01
  • first FEB assembled
  • and successfully
  • tested Nov. 01
  • pos. STm Vregs
  • added Dec. 01
  • 2nd FEB assembled/tested and shipped to Orsay,
    Mar. 02
  • Need neg. Vregs before launching 20 FEB
    preproduction

25
FEB Responsibility Chart
26
Organizational Issues
  • Meeting the specifications, particularly
    radiation tolerance, has required development of
    a LARGE number of custom ASICs and other devices
  • Final PCB designs, while the responsibility of
    one (sometimes 2) labs, must integrate custom
    devices developed by a number of different
    institutions
  • Due to radiation concerns with COTs, custom
    devices need to work together without resorting
    to glue logic
  • For this integration to work as well as it has
    required careful attention to interfaces during
    ASIC design and development
  • Occasional workshops, including engineers, to
    develop and agree on architecture
  • Many meetings and discussions
  • Design reviews for each individual device
  • Documentation and agreement on interfaces
  • In limited (critical) cases, simulation of ASICs
    together (eg. SPAC and Config)
  • As we move toward production, the complexity of
    the distribution of responsibilities will present
    us with a new set of challenges

27
Moving Toward Production
  • Final prototypes of each of the various boards in
    the frontend crate are currently being developed
    and/or tested individually
  • However, a system crate test using all the
    various boards together is necessary to validate
    the designs before launching production
  • Are boards functionally compatible with each
    other? (eg. TTC and SPAC)
  • Does crate performance meet specifications? (eg.
    coherent noise)
  • Are environmental issues under control? (eg.
    power, cooling)
  • Test will be performed at BNL, with first boards
    delivered for Sept. 02
  • Some concerns
  • Coupling of schedules increases schedule risk
  • Continued problems with radtol negative Vreg are
    causing a significant delay
  • Since we cannot wait too long to produce the
    radtol ASICs, most of the components will be
    submitted for production before completion of the
    system crate test

28
Component Production
  • Lab which developed a given component (eg. ASIC
    or plug-in) is responsible for the production and
    delivery of that component
  • Separate PRRs to be held for all major custom
    components
  • So far, have been held for preamps, HEC
    preshapers, shapers, LSBs, SCAs
  • To achieve cost savings, many radtol ASICs will
    be produced together on shared wafers
  • DMILL Analog Reticle opamp, DAC, BiMUX
  • DMILL Digital Reticle SPAC, CALogic, Config,
    MUX
  • DSM Digital Reticle SCA Controller,
    GainSelector, CLKFO
  • PRRs for the ASICs on these shared wafers are
    expected by end 2002
  • Some concerns
  • Sharing of ASIC wafers for production increases
    schedule risk
  • Careful tracking required during ASIC packaging
    and delivery

29
Component Quality Assurance and Tracking
  • QA plan developed and presented as part of PRR
    to be archived in EDMS
  • For LSB example, see B. Clelands Trigger Sums
    presentation
  • For plug-in assemblies (preamps, preshapers,
    LSBs) this includes
  • Initial inspection
  • Pre-test
  • Burn-in at elevated temperature
  • Re-test
  • Custom ASICs will be individually tested, but not
    burned in
  • Serial numbers are to be printed on the
    components
  • Results of component testing and QA procedures
    are to be entered in database and tracked via
    serial number

30
Example of Component Tracking
  • BNL document for following preamp acceptance
    procedures

31
Example of Component Quality Results
(Final sample of 50000 channels 50W/1 mA preamps
from INFN-Milano)
Gain
Peaking time (5-100)
Equivalent Noise Current
Acceptance limits
32
Component Qualification and Testing
  • In most cases, lab which developed a given
    component (eg. ASIC or plug-in) is responsible
    for radiation qualification and
  • for functional testing of production parts
  • prior to delivery for assembly onto PCBs
  • For shapers and SCAs, where gt 50000 chips
  • needed, ISN Grenoble developed robotic tester
  • Shaper testing completed (last week)
  • SCA testing to start soon
  • Remaining ASICS must be tested manually
  • Some concerns
  • PCB complexity makes re-work difficult, requiring
    excellent pre-testing and rejection of faulty
    parts
  • Achieving the necessary very high quality of
    automated PCB assembly process requires no damage
    to pins
  • Most of the critical ASIC testing is being done
    long before the start of PCB production, meaning
    there is no chance for feedback to the testing
    procedures

33
PCB Design/Testing Issues
  • Each PCB includes many custom components
    developed by other labs
  • Responsibility charts have been created for all
    PCBs, identifying individuals responsible for
    delivery of each of the major components (see
    earlier slides)
  • Steps to ensure successful design and integration
  • Usually, dedicated jigs developed first to test
    integration of custom ASICs
  • All final schematics made available via WWW
  • Relevant contact person asked to verify schematic
    related to their ASIC
  • Board design documentation and reviews (eg. later
    this week)
  • System crate test before launching board
    production
  • All final PCBs will be fully tested before
    delivery to CERN
  • Test procedures still being developed
  • Take FEB as example, since it is by far the PCB
    of largest quantity
  • Nevis and LAL are working on developing and
    defining the final FEB test procedure (see next
    slide)

34
FEB Testing Procedures
  • FEB test steps as currently envisioned include
  • Receipt and visual inspection of assembled PCBs
    at Nevis
  • Boards will be fully assembled in industry, but
    NOT including preamp/LSB plug-ins
  • Labelling of FEBs with serial numbers
  • Initial test without preamps/LSB
  • Full testing/debugging of digital part
  • Partial testing/debugging of analog part (from
    shaper outputs)
  • Limited burn-in (eg. overnight? room
    temperature?)
  • Does not appear practical to perform a long
    burn-in on the full set of FEBs
  • Re-test
  • In parallel, full testing (ie. with preamps/LSBs)
    at Nevis of sample (5-10) of FEBs to allow quick
    feedback to Assembler
  • Shipment to LAL of FEBs which passed Nevis tests
  • Installation of preamps and LSBs of appropriate
    combinations
  • Full testing/debugging/calibration of analog part
  • Shipment to CERN of FEBs which passed LAL tests
  • Installation and testing of cooling plates
  • Functional re-test
  • Ready for installation/commissioning in the pit

35
Radiation Tolerant Voltage Regulators
  • CERN-driven development of rad-tol Vregs by STm
    has long been identified as a critical item,
    particularly for the FEB development
  • Each FEB requires 14 positive Vregs and 6
    negative Vregs
  • As one backup possibility, we asked MDI in early
    2001 to consider an SBIR to develop a hybrid
    radtol Vreg they did so, but it was NOT approved
    by DoE
  • We irradiated with protons samples of 9
    different commercial Vregs, including several
    advertised as radtol (but only wrt ionizing
    radiation)
  • Only the Intersil HS9S-117RH positive Vreg
    survived as a backup (? 75 unit cost)
  • We worked on designing our own radtol Vreg with
    COTs, but with little in the way of encouraging
    results
  • STm delivered first positive Vreg prototypes in
    Dec. 01, which we have since then been using
    successfully on the FEB ? ve Vreg issue would
    appear to be resolved
  • In May 02, STm announced they were still having
    stability problems with the neg. Vreg design, and
    an additional design iteration was required
  • STm has not yet announced a new schedule for the
    negative radtol Vreg
  • Past experience would imply a delay of order 6
    months (assuming no further problems are
    encountered!)

36
Radiation Tolerant Voltage Regulators (contd)
  • Intersil has recently announced a new neg.
    Vregulator, radtol to 300 kRad
  • We acquired a few samples (85 each)
  • On May 24, we irradiated 2 samples at HCL ?
    results look encouraging
  • STm remains the most attractive solution
    (assuming availability)
  • Cheaper (10 unit cost versus ? 50 - 70??, about
    10k devices needed for FEBs)
  • Higher current (3 Amp versus 1 Amp)
  • Better voltage range (we need 1.7 V, while
    Intersil rated for lt 2.5 V)
  • Same control logic as STm positive Vreg
  • Next steps
  • Complete evaluation of Intersil devices
  • Further statistics needed for irradiation
    qualification ( HCL no longer available!)
  • Produce jig to interface to allow FEB electrical
    measurements
  • Discuss procurement/financial aspects with
    Intersil
  • Keep pestering STm for updated delivery schedule
    for their development
  • In September, re-visit situation and decide how
    to proceed
  • Dates of PRRs will be fixed in September once
    this issue is resolved
  • (given the Vreg delay, FEB PRR will not be
    before Summer 2003)

37
Summary
  • Building on the success of the Module 0
    electronics development, we are finalizing the
    designs of the final ATLAS LAr readout boards
  • The system crate test is the remaining major
    milestone before moving to production
  • Prototypes of the large number of required custom
    ASICs have been successfully developed and
    integrated
  • Most devices will move into production before the
    end of 2002
  • Continued problems with STm negative radtol Vreg
    are now dominating schedule
  • We are aggressively pursuing a backup, and
    working to minimize delay
  • As we move toward production, we are working to
    formalize the documentation, QA and tracking
    procedures that will be required to sucessfully
    manage the complex production process
Write a Comment
User Comments (0)
About PowerShow.com