Title: Water for Monterey County Regional Project Capital and O
1Water for Monterey CountyRegional
ProjectCapital and OM Cost Description
Lyndel Melton, P.E. RMC Water and Environment
2Capital and OM Cost Description Agenda
- Regional Project Description
- Basis for Cost Estimates
- Capital and OM Costs
- Comparison of Costs
3Regional ProjectUpdated Phase 1 Description
4Phase 1 Project Description
- DEIR Phase 1 Project
- 10 mgd Desal Plant
- 14 mgd SWTP
- 3 ASR Wells
- Common Facilities
- Terminal Reservoir
- ASR Wells PS
- Monterey Pipeline
- Valley Greens PS
- Revised Phase 1 Project
- 10 mgd Desal Plant
- No SWTP
- No Added ASR Wells
- Common Facilities
- Terminal Reservoir
- ASR Wells PS
- Monterey Pipeline
- Valley Greens PS
5Surface Water Treatment Plant
With Surface Water Treatment Plant
6No Surface Water Treatment Plant
7Regional Project Supply Sources
To ASR
To MCWD
To MCWD
CAW Only Supplies
8Coastal Water Project Supply Sources
CAW Only Supplies
9Desal Plant Vicinity Plan
10Desal Plant Site Plan
11Need for Partial Second Pass RO System
- With single pass
- Boron concentrations can be toxic to some crops
foliage - Maximum chloride and sodium concentrations are
anticipated to be 200 180 mg/L - Partial second pass would
- Reduce boron levels to lt0.5 mg/L
- Reduce chloride and sodium concentrations to 100
80 mg/L
12Intake Well Locations
13Intake Well Locations
14Regional ProjectBasis for Cost Estimates
15Basis for Capital Cost Estimating
- Used CAWs cost criteria/unit costs
- Reviewed for appropriateness and agree with bases
- Supplemented with vendor quotes
- Design/Build for Desal
- Design-Bid-Construct for Other Facilities
16Basis for OM Estimating
- Used CAWs OM
- Labor
- Chemical
- RR
- Membrane Replacement
- Power supply costs
- Desal Plant MRWMD
- Winter 0.08/kW-hr
- Summer - 0.12/kW-hr
- Desal Wells PGE
- Winter 0.09/kW-hr
- Summer - 0.14/kW-hr
17Expected Accuracy Ranges for Cost Estimating
(Same as CAW Estimates)
60
40
Expected Accuracy Range for Cost Estimate
20
Project Completion
0
-20
Level of Project Definition 10 Project Complete
(Class 4) 30 Project Complete (Class 3) 100
Project Complete (Class 1)
18Regional ProjectCapital and OM Cost Estimates
19Table 7 Estimated Cost Phase 1 DEIR Project
20Table 8 Estimated Costs of Common Facilities
21Table 9 Estimated Costs of Phase 1 Project With
No Surface Water Supply
22Alternative Project Cost Comparisons
23Basis for Cost Comparisons
- Used CAWs MCWDs cost and production numbers
- Cost of capital for Regional Project 5.15 over
30 years - Cost of funds for CAW alternatives 8.55 over
30 years - Unit water costs developed to compare all
alternatives
24Table 10 Comparison of Estimated Costs of DEIR
Based Projects
25Table 11 Comparison of Estimated Costs with no
Surface Water Supply
26Table 13 Sensitivity Analysis
27Regional Project Phase 1 Implementation Schedule