New Product Development NPD Project Management Tools Harris Corporation - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

New Product Development NPD Project Management Tools Harris Corporation

Description:

Budget Constraints. Fixed Skill Mix. Strategic Priority (previously shown) ... Weinberg calculator (Excel) Risk spread sheet. Past experience. NPD PM Tools ... – PowerPoint PPT presentation

Number of Views:1213
Avg rating:3.0/5.0
Slides: 49
Provided by: graph80
Category:

less

Transcript and Presenter's Notes

Title: New Product Development NPD Project Management Tools Harris Corporation


1
New Product Development (NPD) Project Management
Tools Harris Corporation
  • Southwest Ohio
  • PMI Chapter Meeting
  • April 16, 2003
  • Presented by Philip Schmitt

2
Agenda
  • Basic overview of New Product Development (NPD)
    process at Harris
  • Project Management (PM) tools
  • Portfolio Level
  • Planning
  • Execution
  • Next Steps (as time allows)

3
Introduction
  • Phil Schmitt Supervisor, Power Supply and Low
    Frequency RF Design
  • Joined Harris in November, 1998
  • Lead Design Engineer and Project Manager for AM
    radio projects
  • Team member of Process Improvement Team (PIT) for
    NPD process
  • Achieved PMP Certification in July 2001
  • Tom Jones - Sr. Manager, Project Management
  • Joined Harris in September, 1999
  • Member of team that originally created Harris
    NPD Process
  • Team lead of Process Improvement Team (PIT) for
    NPD process
  • Facilitated 3 NPD related Sub-teams
  • Achieved PMP Certification in November 2002

4
Harris NPD Process
  • Patterned after Dr. Robert Coopers Stage
    GateTM Process
  • Provides interim decision points throughout the
    life-cycle of a project to review cost and
    schedule status, problems, risks, etc.
  • At these decision points (Gates), a review of
    the projects previous Stage is made and a
    decision to continue is reached
  • Only after successfully passing the gate with a
    GO, would the funding for the next phase be
    approved.

5
NPD Stages
  • Stage 1 Idea Generation Collection
  • Gate 1 Business Case
  • Stage 2 Business Case Development
  • Gate 2 Product Planning
  • Stage 3 Product Planning
  • Gate 3 Product Development
  • Stage 4 Product Development
  • Gate 4 Pilot Production Readiness
  • Stage 5 Pilot Production
  • Gate 5 Production Readiness
  • Stage 6 Production Complete

6
Tool Overview
  • Designed to facilitate NPD process
  • Use multitude of software programs
  • MS Project 2000 (and 2002)
  • MS Excel 2000
  • MS Word 2000
  • Minx (Back Office System)
  • Sharepoint
  • Lightly coupled and requires some manual entry
    and manipulation
  • Utilizes limited automation using standard VBA
    (Visual Basic for Applications) macros

7
Stage 1-2 Portfolio Level Analysis
  • Traditional product specific organization
  • Evolving into a weak matrix organization with
    goal toward strong matrix
  • Evolution has led to priority issues

8
Old Organization
9
Weak Matrix Organization
10
What Projects?
  • The matrix organization has many benefits
  • Alignment of projects across the division and
    ensures the right projects get the highest
    priority
  • Ensures right resources are applied to the right
    projects
  • Requires a more mature and disciplined
    organization to make work.
  • Tools to align various competing projects are
    essential

11
Priority
  • Harris uses multiple methods to determine the
    order of priority for potential projects
  • ROI
  • Payback Period
  • Potential Revenue
  • Investment
  • Market Analysis
  • The projects are combined on a single list
    (Excel) with ranking criteria to establish
    marketing and strategic priority

12
Project Priority Reporting Tool
13
Ok, So I know what they want, but what can I work
on?
  • Limits in determining what projects can be
    completed
  • Budget Constraints
  • Fixed Skill Mix
  • Strategic Priority (previously shown)
  • Project Portfolio Manager
  • Combines existing approved project schedules and
    1st order estimates of potential projects
  • Use project templates and historical references
    to help create these 1st order estimates
  • Schedules loaded into a master schedule for
    leveling
  • Data is exported into custom Excel Spreadsheet
    for analysis

14
MS Project High Level Template
15
MS Project Master Project File
16
Portfolio Manager
17
Portfolio Manager
18
Stage 3 - Planning
  • Product Line use Portfolio Manager data to help
    determine the next best project and begin
    development of business case
  • Approval of Stage 2 Business Case provides
    limited funding for next stage of work.
  • Stage 3 - Planning
  • Team Development
  • Scope Definition
  • WBS
  • Task Definition, Estimation, Sequencing
  • Risk Assessment
  • Schedule Creation

19
Planning Tools
  • Project Guidelines Document
  • Requirements Matrices
  • Standard WBS
  • Risk Analysis
  • MS Project Template
  • Project Plan Template
  • Gate Matrix

20
RACI (RAM) Matrix
  • (RACI) Responsible, Accountable, Consult, Inform
  • Defines cross functional department
    responsibility to NPD processes.

21
Guidelines
  • A project guide assists project managers in
    developing their project plan
  • Provide instruction on how to plan the project

22
Scope Definition
  • Product line manager (sponsor) and team work to
    define the scope of the project
  • Specification and requirements matrix (excel)
    document the requirements
  • At Gate 3, these are placed under revision control

23
WBS
  • Based on our Stage-Gate process
  • Standardized down to level 3
  • Accounting system is aligned to level 3 for
    tracking actual costs

24
MS Project Template
  • Allows quicker start of new project plans
  • Provides consistent reporting (standard reports)
  • Provides standard options, views, and macros
  • Allows better alignment of our projects for
    portfolio management

25
MS Project Templates
26
MS Project Defaults
  • For each Option window, Harris defaults have been
    selected to improve MS Project performance and
    provide consistency among projects
  • Customizations are documented for reference

27
Custom Views
28
Task Definition
  • Project planning sessions to flesh out WBS
  • Single subject reviews to flesh out the
    activities
  • Task estimation sheet used to provide detailed
    task inputs to PM

29
Task Estimation
  • Expert Judgment
  • 50/50 Rule
  • Contingency Reserve
  • Weinberg calculator (Excel)
  • Risk spread sheet
  • Past experience

30
Risk Analysis
  • Document known risk items
  • Provides relative pain score
  • Supports CR estimates and duration estimates

31
Project Plan
  • The project plan template includes
  • Project Scope
  • Major Project Deliverables
  • Product Requirements and Performance
    Specifications (Reference to Matrices)
  • Planning Assumptions
  • WBS (high level)
  • Schedule and Budget Summary
  • Resources (Core Team RACI)
  • Risk Management
  • Product Cost Summary

32
Project Plan Example
33
Gate Matrix
  • Ensures NPD requirements have been met.
  • Simple method for tracking requirements of
    process
  • Provides quick visual indication of status

34
Project Execution
  • Passing Gate 3 provides the authority to
    implement the plan (and an excuse for a party)
  • Tools for managing the execution and control
  • Weekly Task Reports
  • Project Performance Tracker (Spreadsheet)
  • Monthly Management Flash Report
  • Monthly Department Budget Estimate Report
  • Sharepoint

35
Weekly Task Reports
  • Provides simple interface to project data for
    team members
  • Task list is individualized for each member
  • Uses standard client software (excel)
  • Allows data extraction from team member to be
    completed ahead of team meeting to reduce meeting
    times
  • Macro developed to automate extraction to excel
  • Still need big picture review in team meeting

36
Weekly Task List
37
Project Performance
  • EV is recorded on a periodic basis
  • Use SPI / CPI as main indicators
  • Threshold set at 0.95 to show off schedule and
    a plan for recovery needs to be considered
  • At 0.90 a recovery plan should be available and
    ready for management approval to get back on
    track.
  • This data is reviewed with team on weekly basis
  • Flash Report give upper management a one page
    view of project status (monthly)

38
Performance Tracker
39
Flash Report
40
Monthly Budget Estimate
41
Sharepoint
  • Communicate information to core team members as
    well as other project participants
  • Central storage of key files and information
  • Ease of use and access by team
  • Conclusions

42
Next Steps
  • Currently the tools we are using are working but
    require a great deal of manual work to make
    effective.
  • Data is located in separate systems and is not
    centrally available to all who need the data.
  • Historical data is hard to extract to provide
    meaningful help in estimating future projects.
  • Timeliness of data has been an issue limiting our
    ability to control and react to changes

43
Next Steps
  • A Process Improvement Team (PIT) has reviewed our
    systems and suggested improvements
  • Primary focus on Enterprise Project tools
  • Reviewed many off the shelf packages
  • Winner MS Project 2002 and Server 2002

44
Tool Selection Criteria
45
Why MS Project 2002?
  • Attractive capital investment costs
  • Installed base of users using Project 2000
  • Internal expertise in customization
  • Predefined interfaces to Peoplesoft
  • Project 2002 and Server 2002 provide a platform
    that can be considered a real project
    management tool (compared with earlier versions).
  • Microsoft should continue to provide new features
    and capabilities.
  • Viability of some of the smaller players in this
    space

46
Conclusions
  • These tools are designed around our processes and
    make our jobs easier
  • They provide consistent means of tracking and
    reporting
  • They provide a common focus of our development
    efforts allowing us to apply the right resources
    to the right project at the right time
  • They dont make up for poor planning, poor
    management, or lack of training

47
Acknowledgements
  • The following people contributed to the creation
    of these tools
  • Geoff Mendenhall, VP of Advanced Development
    Engineering
  • Dave Glidden, Director of TV Transmission Product
    Line
  • Tim Dittmer, Sr. Manager- DSP and RF Design
  • Tom Jones, PMP, Sr. Manager- Project Management
  • Jeff Malec, PMP, Sr. Manager-Transmitter
    Development
  • Randy Restle, PMP, Sr. Manager- Digital Design
  • Jason Rieg, TV Product Line Manager
  • Frank Walker, TWG Project Management

48
Questions?
  • If you have any questions after this meeting,
    please contact
  • Tom Jones
  • Office (513-459-3606)
  • E-mail wjones11_at_harris.com
  • Phil Schmitt
  • Office 513-459-3491
  • Email pschmitt_at_harris.com
  • Thank you!