Time Management Week 7 - Learning Objectives - PowerPoint PPT Presentation

About This Presentation
Title:

Time Management Week 7 - Learning Objectives

Description:

Time Management Week 7 - Learning Objectives You should be able to: List and describe the processes, activities, inputs, and outputs in time management – PowerPoint PPT presentation

Number of Views:106
Avg rating:3.0/5.0
Slides: 30
Provided by: DrC103
Learn more at: http://ruby.fgcu.edu
Category:

less

Transcript and Presenter's Notes

Title: Time Management Week 7 - Learning Objectives


1
Time Management Week 7 - Learning Objectives
  • You should be able to
  • List and describe the processes, activities,
    inputs, and outputs in time management
  • Create and interpret a network diagram
  • Create and interpret a GANTT chart
  • Define and use CPM, critical path and time,
    slack time, crash time, fast-tracking

2
Time Management Issues
  • Frequent source of project failure
  • Often used as a success measure
  • Frequent source of project conflict
  • Time / cost / scope tradeoffs
  • Less negotiable, least flexibility
  • Stakeholder involvement
  • communication and commitment

3
Time Management Processes
  • Define Activities
  • further defines scope
  • Sequence Activities
  • further defines time
  • Estimate Duration
  • further defines cost
  • Develop Schedule
  • Control Schedule

4
Activity
  • Element of work - on WBS
  • cost
  • duration
  • resources
  • Tasks vs. activities?
  • Doesnt matter, as long as the work to be done is
    described accurately and understood by those who
    must do the work

5
Define Activities
  • Steps needed to produce deliverables
  • Inputs
  • WBS, Scope, historical data, constraints,
    assumptions
  • Outputs
  • Activity list, descriptions, supporting detail,
    updates to WBS
  • complete understanding of work involved

6
Sequencing Activities
  • Identifying dependencies
  • relationships between activities
  • Mandatory dependencies
  • technical, defined by type of work
  • Discretionary dependencies
  • defined by project team
  • External dependencies
  • relationships to non-project activities

7
Activity Sequencing Tools
  • Network diagrams
  • schematic display of activities and dependencies
  • activity on arrow (AOA or ADM)
  • Precedence diagramming
  • activity on node (AON or PDM)

8
D (15)
6
2
J (8)
A (20)
E (10)
F (14)
3
B (20)
7
1
G (4)
I (18)
C (10)
5
4
H (11)
9
Precedence Diagram (PDM)
  • Boxes represent activities
  • Types of dependencies
  • finish-to-start
  • start-to-start (can be parallel)
  • finish-to-finish (can be parallel)
  • start-to-finish (rarely used)

10
(No Transcript)
11
Estimating Duration
  • Should involve stakeholders, people doing the
    work
  • Inputs
  • Activity list, constraints, assumptions
  • Resource requirements
  • Resource capabilities (human and materials)
  • Use historical data, previous projects,
    experience, simulations
  • Outputs duration estimates
  • quantitative assessments of likely number of work
    periods required to complete activity

12
Developing the Schedule
  • Inputs to schedule development
  • project network diagram
  • activity duration estimates
  • resource requirements
  • resource pool description
  • calendars (project and resource)
  • constraints, assumptions, leads and lags

13
Scheduling Tools
  • GANTT charts
  • CPM Critical Path Method
  • PERT probabilistic time estimation
  • Simulation

14
GANTT Chart
  • shows planned vs. actual progress
  • multiple tasks on horizontal time scale
  • easy to read, easy to construct
  • monitoring and control of progress
  • requires frequent updating
  • limited display of dependencies

15
Components of GANTT Chart
  • Activities - scheduled and actual
  • Precedence relationships
  • Milestones (identifiable points in project)
  • usually represents reporting requirements
  • usually corresponds to critical events
  • Can add budget information
  • Does not show technical interdependencies
  • Need network diagram to interpret, control, and
    compensate for delays

16
Gantt Chart symbols
  • Milestone
  • diamond
  • Summary task
  • dark bar
  • Individual task
  • light bar
  • Arrows
  • dependencies

17
CPM Definitions
  • Activity uses resources and takes time
  • Event result of completing an activity
  • has identifiable end state at a point in time
  • Network combined activities events in a
    project
  • Path series of connected activities
  • Critical activities, events, or paths which, if
    delayed, will delay project completion
  • Critical path sequence of critical activities
    from start to finish
  • Node start or end of an activity
  • Arrow (Arc) shows path

18
A-C-F 19 B-E 9 B-D-F 14 Critical Path is
A-C-F Critical Time 19
C,6
2
4
F,8
A,5
D,2
1
5
3
B,4
E,5
19
  • EOT
  • earliest occurrence time for event
  • time required for longest path leading to event
  • LOT latest occurrence time for event
  • EST earliest starting time for activity
  • LST latest starting time for activity
  • Critical time shortest time in which the project
    can be completed
  • Slack time difference between earliest and
    latest start times

20
D (15)
6
2
J (8)
A (22)
E (10)
F (14)
3
B (20)
7
1
G (4)
I (18)
C (10)
5
4
H (11)
21
(No Transcript)
22
  • What is the critical path? Critical time?
  • B-F 34
  • B-E-J 38
  • A-D-J
  • B-G-I
  • C-H-I
  • What is the earliest occurrence time of event 6?
  • What is the latest start time for activity F?

23
Probabilistic Time Estimation
  • More realistic, includes uncertainty
  • Expected completion time
  • optimistic, pessimistic, most likely times
  • take weighted average of the 3 times
  • TE (a 4m b)/6
  • uncertainty variance (range of values)
  • Probability of completion of project in desired
    time D
  • Z (D - ì)/(sqrt(ó2 ì))

24
(No Transcript)
25
Outputs of Scheduling Process
  • Date-enhanced project network diagram
  • GANTT charts, milestone charts
  • Time-scaled network diagrams
  • combines GANTT, network diagram
  • Supporting detail
  • Schedule management plan

26
Shortening the Schedule
  • Duration compression
  • Crashing
  • time/cost tradeoff
  • Fast tracking
  • parallel vs. sequential
  • Resource loading and leveling
  • more even distribution of resource usage

27
Slope (crash cost - normal cost ) (crash
time - normal time) cost per day of crashing
activity
28
Schedule Control
  • Determining, managing schedule changes
  • Influencing changes so they are beneficial
  • Inputs
  • schedule, performance reports, change requests,
    schedule management plan
  • Outputs
  • schedule updates notification
  • corrective action to minimize delays
  • lessons learned

29
Controlling Schedule Changes
  • Involve stakeholders
  • manage expectations
  • progress meetings
  • no surprises
  • Leadership, discipline, negotiation
  • review draft schedule and add details
  • realistic estimates
  • allow for contingencies
  • empower and incent employees
  • Proper use of tools
Write a Comment
User Comments (0)
About PowerShow.com