Targoviste Cogeneration and District Heating Municipal Project ... The contract for gas supply Next Steps Carry out the detailed design of ... oil-extracting ... – PowerPoint PPT presentation

Number of Views:93
Avg rating:3.0/5.0
Slides: 17
Provided by: Vior6
Category:

less

Transcript and Presenter's Notes

Title: Understanding between Romania and Netherlands Regarding the Achievement of Joint Implementation Activities


1
Understanding between Romania and Netherlands
Regarding the Achievement of Joint Implementation
Activities
  • Targoviste Cogeneration and District Heating
    Municipal Project
  • April, 2002

2
The City Of Targoviste Background
The town was first mentioned by the bavarian
crusader Johann Schiltberger in 1396. -
Between 1396 - 1714 it used to be the capital of
Romanian Country starting with Vlad the Impaler
reign. - Until 1600 when Michael the Brave
succeeded in achieving the first Union of the
Romanian principalities, Targoviste remains the
capital of Romanian Country. -Today ,Targoviste
is the capital of Dambovita County - 98.000
inhabitants - Industrial potential- sheets and
rolled goods of rustproof steel -special
steels -light source facilities -laquers
and dyes -lathes of different types
oil-extracting equipement
3
Dutch Romanian Joint Implementation Activities
  • On December 11,1997, Romania and The
    Netherlands signed The Kyoto Protocol regarding
    the reduction of emissions that are generating
    climate changes, especially the CO2 emissions.
  • The Romanian Government ratified the Kyoto
    Protocol on February 2001. ( Law No. 3 dated
    February,2001).
  • The Kyoto Protocol is stimulating the realization
    of Joint Implementations Projects in order to
    reduce the CO2 emissions whereby the investment
    result is the biggest one.

4
Dutch Romanian Joint Implementation Activities
  • In 1999, Romania , Bulgaria and Slovakia signed
    with The Netherlands a Memorandum of
    Understanding related to the realization of J.I.
    Projects through crediting and transferring the
    obtained CO2 emissions reduction to the
    Netherlands Government , reductions obtained
    between the years 2008 and 2012.

5
CO2 emission reduction crediting and transfer
ERUs Emission Reduction Units
ERUs
Claims on ERUs
ERU-PT Public Procurement
COMENOR
Emission Reduction
6
Why J.I. Projects

Fossil Fuel Generation and
related Carbon Dioxide Emissions
2
TWh
RO
Mton
NL
CO2
kg CO
/kWh
2
0
50
100
0
0,5
1
1,5
7
Joint Implementation Projects Contracts
Agreements
RO. Government
NL- Government
Memorandum of Understanding
IFC
Agreement of Cooperation
NCC
CL, TERMICA, NUON
S.C. Comenor Târgoviste S.R.L.

Engineering, Procurement Contracting (EPC)
Intretinere si Exploatare (OM) PPA, HSA GSA
8
Romanian Benefits
  • Mitigation of Heat supply deficit in Targoviste
    City
  • Encouragement of other foreign investments in the
    municipality infrastructure
  • Improved air quality
  • Decrease of CO2 emissions
  • Complying with UE environmental standards

9
Romanian Benefits
  • Utilization of the latest technology
  • Reducing fuel consumption,discharging the balance
    sheet.
  • Creating new skilled jobs in The City of
    Targoviste
  • Economic benefits energy power cheaper than the
    alternative.

10
J.I. Cogeneration ProjectsHistory
  • 1997 Preliminary Analysis 11 projects (Sep)
  • 1998 In depth evaluation 5 projects (NCC)
  • 1999 - 2000 Final Analysis 2 projects
  • (Cluj-Napoca and Târgoviste)
  • In cooperation with IFC (World Bank)
  • Financing analysis ING Barings
  • Total costs around 40 millions (Cluj-Napoca)
  • around 40 millions (Târgoviste)

11
J.I. Cogeneration ProjectsHistory
  • Documentation submmited to SENTER by NUON and
    Termica in order to participate to the ERU-PT
    Tender
  • Octomber 2000 The project was selected to
    participate for the ERU-PT Tender
  • February 15th, 2001 The final proposal to
    SENTER
  • April 2001The Minister of Economic Affairs of
    Netherlands agrred to award the offer with a
    contract concerning the generation and delivery
    of claims on 1.536.140 ERUs at a price of EUR9 /
    ERU for a total contract value of EUR
    13.825.260 only after the following compulsory
    elements will be achieved

12
J.I. Cogeneration ProjectsHistory
  • A copy of the deed of foundation of the project
    company , including a specification of the
    shareholders and their share in the project
    company
  • A copy of the concession agreement in which the
    transfer of ERUs from the project company to
    NUON Warmte NV is specified
  • A proof of financial arrangements
  • A proof of credit and participation arrangements
    and a proof of insurance

13
J.I. Cogeneration ProjectsHistory
  • A copy of The Environmental Impact Study
  • A copy of a letter issued by the appropriate
    Romanian governmental institution which contains
    the conformation that the hardware to be
    delivered in the framework of this project is
    free of import duties
  • A full guarantee by NV NUON on the delivery of
    Claims on ERUs and the fulfillment of financial
    obligations in case of non delivery

14
Targoviste ProjectDescription
  • Installed capacity 26.4 MWe / 32.8 MWth
  • Heat gaz engines ( total net efficiency 88
    ?e39 si ?th49)
  • Total Costs 37 millions
  • The annual total energy power output 147,127 MWh
  • The total heat energy output 224,145 Gcal (70
    by cogeneration and 30 by Heat Only Boilers)

15
Urgently Steps to Follow
  • Obtaining notice from The National Regulatory
    Agency (ANRE) regarding the heat and power energy
    tariff.
  • Finalizing the negotiations with S.C. Electrica
    S.A.
  • The foundation of The Project Company (PC)
  • PC signs the PPA with Electrica S.A., S.D.
    Târgoviste
  • PC negotiates and signs
  • The contract for gas supply

16
Next Steps
  • Carry out the detailed design of the project
  • The final negotiation of financing
  • The final decision to realise the project
  • To sign the Financing Agreement
  • To sign the contract for the project
    implementation
  • Start date of works 2003
  • End date of works 2004
  • Operating date June 2004