Finishing Projects Fast - PowerPoint PPT Presentation

About This Presentation
Title:

Finishing Projects Fast

Description:

Finishing Projects Fast James R. Burns Professor of Operations Management and Information Technology Texas Tech University * Tuesday, March 23, 2004 Presentation by ... – PowerPoint PPT presentation

Number of Views:93
Avg rating:3.0/5.0
Slides: 46
Provided by: JamesR126
Learn more at: http://burns.ba.ttu.edu
Category:

less

Transcript and Presenter's Notes

Title: Finishing Projects Fast


1
Finishing Projects Fast
  • James R. Burns
  • Professor of Operations Management and
    Information Technology
  • Texas Tech University

2
Outline--Sources
  • Generalities
  • Goldratt concepts
  • Mascitelli concepts
  • McCONNELL concepts
  • Kerzner concepts
  • Maturity concepts
  • Other sources

3
Goal
  • Make some suggestions as to how projects can be
    completed fast and frugally

4
Why Projects????
  • A way to discretize and plan work that
  • Enables comparisons among projects
  • Enables the work to be
  • formally defined
  • formally planned
  • formally budgeted
  • formally executed
  • formally controlled
  • Formally finished

5
Most firms
  • Recognize project management to be a core
    competence today
  • Have established project management centers of
    excellence for training and development of
    project managers and project management careers
  • Encourage its employees to propose project
    initiatives with simple one-page statements of
    work

6
The Stages in the Project Management Lifecycle
Conceptualization Definition
Planning Budgeting
Executing Controlling
Termination Closure
The product the project is to produce is defined
here
7
Notes on shortening project durations
  • (Most of this must be done in the Planning and
    Budgeting stage)
  • Crashing
  • Reducing the duration of tasks on the critical
    path by adding resources
  • Fast-tracking
  • Starting tasks sooner
  • Checking for parallelism opportunities in the
    schedule
  • Pull as much work off of the critical path as you
    can
  • Be aware of critical chain issues

8
More Tips on shortening project durations
  • REUSE, REUSE, REUSE
  • Do it right the first time
  • Eliminate non-value-added work activities
  • Make projects lean
  • Avoid changes to requirements
  • But what if the requirements are unstable??

9
Knowledge Reuse
  • Requirements Reuse
  • Classification of projects
  • Mapped/Programmed Projects--Everything is driven
    by and proceeds from the requirements
  • Project Plan
  • Functional Specification
  • Design Document
  • Code
  • Tests and Test Documentation
  • ALL OF WHICH CAN BE REUSED

10
The Quality View on FAST projects
Do it Right the First Time!!!
  • The further down the lifecycle the defects are
    found, the more expensive and time consuming they
    are to fix.

11
The problem of Complexity
  • In the early days of simpler code, it used to
    take a day or less to fix a bug
  • Now, with greatly increased code complexity, it
    takes weeks sometimes.

Complexity greatly increases time and cost
12
Avoid changes to requirements
  • If possible freeze requirements during execution
    and control stage

13
Lean Project Management
  • Customer-perceived value should drive everything
  • What is the value proposition??
  • If we were to advertise in the WSJ that we have
    twice as many walkthroughs as our closest
    competition, would that garner any additional
    customers for us?
  • Remove what does not add value

14
Principles of Lean Concepts Applied to Projects
  1. Precisely specify the value of the project
  2. Identify the value stream for each project
  3. Allow value to flow without interruptions
  4. Let the customer pull value from the project team
  5. Continuously pursue perfection

15
Which of the following adds value?
  • Conducting a weekly team coordination
  • Hunting for needed information
  • Presenting Project status to upper management
  • Creating formal project documents
  • Gaining multiple approvals for a project document
  • Waiting in queues for available resources

16
Time Batching--Another Time Waster
  • Analysis paralysis
  • Approval cycles
  • Formal document release
  • Regularly scheduled meetings
  • Planning cycles
  • Work queues

17
More techniques for shortening projects
  • Scrub the requirements during or prior to the
    planning and budgeting stage
  • Remove from the requirements those items that add
    little or no value
  • Remember the Pareto principle80 of the value
    comes from 20 of the functionality
  • REMOVE SAFETYGOLDRATT
  • Resist multitasking and student syndrome

18
Safety
  • Extra time placed in an estimated task time
  • Remove safety and put it in a time buffer at the
    end of the project
  • Safety, when its buried in the tasks of the
    project, is a bad thing because of.
  • Multitasking, also a bad thing
  • Student syndrome
  • Task dependencies
  • Cant be passed along or accumulated

19
Task Duration Probability -- a Beta distribution
20
A Scenario
  • You have been asked to do two tasks TASK A ---gt
    TASK B
  • TASK A whose most likely duration is 10 days,
    but optimistic duration is 6 days, pessimistic
    duration is 20 days
  • TASK B whose most likely duration is 10 days, but
    optimistic duration is 6 days, pessimistic
    duration is 20 days
  • Estimate how long, ON AVERAGE, it will take you
    to complete these two tasks?
  • What is the probability that you will finish in
    20 days?

21
Everybody overestimates the time required to do
their task
  • According to Goldratt
  • (This is called SAFETY, as we said)
  • Does anybody want to talk about how much safety
    they put into their estimates?
  • Is this true in software development?
  • It is if you have an expert doing the estimating,
    who really knows how long it will take him

22
What happens after that--a possible scenario
  • The team leader adds safety time to the task to
    cover his responsibilities
  • The project leader adds more safety time
  • The project manager may add still more safety time

23
Implicationgtgtgt
  • Most of the time we have built into our projects
    is ..

24
The project manager must stay focused
  • Or the project will not be finished on time,
    within budget
  • This means applying the Pareto principle
  • 80 of the benefit comes from 20 of the
    activities
  • By the time progress reports indicate something
    is wrong, its usually too late
  • Progress reports tell you that 90 of the project
    is finished in 90 of the required time.
  • However, another equal period of time is required
    to complete the remaining 10, in many cases

25
It is hard to stay focused when
  • There are too many project paths on-going, in
    parallel
  • There are many critical or near critical paths
  • There are many projects being managed concurrently

26
Measurements are a major problem with projects
  • Measurements should induce the parts to do what
    is good for the system as a whole
  • Measurements should direct managers to the point
    that needs their attention
  • So often it occurs that we measure the wrong
    thing.
  • The wrong measure leads to wrong behavior
  • Tell me how you measure me and I will show you
    how I behave

27
More Measurements
-5
-5
-5
15
28
Projects are like chains
  • Each task in sequence is a link in a chain
  • Each link has two things
  • weight, to which cost is analogous
  • strength, to which throughput is analogous

29
Cost vs Throughput
  • Goldratt maintains that management in the cost
    world is a mirage
  • efficiency becomes paramount
  • local improvements are necessary to get global
    ones
  • Goldratt suggests the managers should manage in
    the throughput world, a totally different
    paradigm
  • must find the constraint--the weakest link
  • concentrate on that
  • By the way, what is the ultimate constraint???

30
Remember the five steps of TOC
  • IDENTIFY the project constraint--the critical
    path
  • Decide how to EXPLOIT that constraint
  • SUBORDINATE everything to that decision
  • ELEVATE the systems constraint
  • Go back to step 1, and find another constraint

31
Safety
  • Safety is however much time is added on to a task
    beyond its mean time of completion

32
Probabilistic task durations
  • Late durations tend to accumulate and may
    increase the length of the project
  • Early durations do not show up
  • This explains why safety disappears

33
More Measurements
-5
-5
-5
15
34
Other problems with safety
  • Is wasted by the student syndrome
  • Basically, this is procrastination
  • Is wasted by multitasking (a person who works on
    several tasks at the same time)
  • With each change of task, a set up is required
  • Is wasted by dependencies between steps
  • These dependencies cause delays to accumulate,
    but advances are wasted
  • Delays get passed on advances dont

35
Problems other than safety
  • Early start vs. late start
  • Existing measurements are worthless because they
    are based on a cost world mentality, according to
    Goldratt
  • Existing measurements (Earned Value Analysis) do
    not take into consideration the critical path
  • Were talking about BCWP, BCWS, ACWP, CV, SV,
    CPI, SPI, BAC, EAC, etc.

36
Early Start vs. Late Start
B 5
A 5
E 10
D 10
C 10
37
How much Safety is there likely to be?
  • Will project professionals admit how much safety
    they are putting into their estimates?
  • What happens when these professionals are asked
    to cut their durations by 10, next time?
  • These professionals want to be 100 sure of
    getting finished on time
  • Therefore, the durations are likely to be twice
    as long as they should be
  • So CUT THEM IN HALF

38
Solutions
  • Take the safety out of the individual tasks and
    put it at the end of the critical path in the
    time buffer, called a project buffer
  • This means making the tasks roughly 50-60 as
    long as they would otherwise be.

39
More solutions
  • At the point where each feeding path intersects
    with the critical path, place another time
    buffer, called a feeding buffer. The feeding
    buffer protects the critical path from delays
    occurring in the corresponding non-critical
    paths.
  • When resources are needed on the critical path,
    these resources are advised ahead of time exactly
    when they must make themselves available. When
    that time comes, they must drop everything else
    and do the required critical tasks.

40
Measurement solutions
  • Measure progress only on the critical path what
    percent of the critical path we have already
    completed. This is all we care about!!
  • Have a project leader measure progress on a non
    critical path in terms of unused buffer days

41
Shrinking the task time Effects
  • There is less procrastination
  • There is much more focus
  • There is less multitasking

42
More Suggestions
  • Put your BEST people on the critical path
  • Watch out for critical chains

43
What are the ramifications of a delayed software
product, intended for commercial sale?
  • Less market share
  • Less profit maybe no profit
  • Lower analyst profit expectations
  • Declining share price
  • Out of business?
  • How many firms has Microsoft driven out of
    business?
  • Ask Philippe Khan (founder of Borland) what the
    implications of getting a product late to the
    marketplace are

44
What about Procurement
  • Most firms enter into LOSE/LOSE Strategies
  • A fixed-price lowest bidder contract is
    LOSE/LOSE Strategy
  • This forces Contractors to under bid their costs,
    hoping to make it back on the changes to the
    requirements that the customer will have to pay
    for
  • Instead, Contractors should be induced to deliver
    product on time, with as much functionality as
    possible
  • How would you do this?

45
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com